Registration lapsed No litigation declared Residential / Group Housing project

Ivana Residency

By Siddhidata Infra

RG-MH-73148 · RERA P52100053060 · Last updated on MahaRERA portal: 13 Feb 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 17 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
May 2025Possession promised17 months past this date
4 of 11Construction stages donefurthest along: Internal walls, 50%
3 of 10Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 41 documents Report an error

Ivana Residency is a Residential / Group Housing project by Siddhidata Infra in Pune, Maharashtra, registered with MahaRERA as P52100053060 on 12 Oct 2023. Possession was promised by 31 May 2025 and is now 17 months past that date. 7 of the 10 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameIvana Residency
  • TypeResidential / Group Housing
  • Location
    • Wakad
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • RERA no.P52100053060
  • ReraGenie IDRG-MH-73148

Builder

  • NameSiddhidata Infra
  • Entity typePartnership

Key dates

17 months past promisethis monthRegisteredOct 2023PromisedMay 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on12 Oct 2023
  • Promised completion31 May 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed41 files

Current status

70%7 of 10 units booked

Figures as on 13 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Ivana ResidencyNA5010010

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 50%.

Ivana Residency: 45% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 13 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed3

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3
Closed/Covered3

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area350 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on13 Feb 2026
LandownerVillageDistrict
Mr Dhananjay Shivdas DhamPashanPune
Mrs Gauri Dhananjay DhamPashanPune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI615.91
Proposed, not sanctioned616 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWakad Pune

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Shubham Ombhase
EngineerMr Sujit Dashrath
Chartered AccountantCA P G Agarwal and Co
PartnerRole in project
Siddhidata Infra-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Sep 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Sep 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Sep 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed41

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Certificate (1).pdf13 Feb 2026
Withdrawal Update Form 1File: Architect Certificate (1).pdf13 Feb 2026
Withdrawal Update Form 2File: Form 2.pdf13 Feb 2026
Withdrawal Update Form 2File: Form 2.pdf13 Feb 2026
Withdrawal Update Form 3File: Form 3- Ivana_compressed.pdf13 Feb 2026
Withdrawal Update Form 3File: Form 3- Ivana_compressed.pdf13 Feb 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate (1).pdf18 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf18 Jul 2024
Disclosure of sold/ booked inventoryFile: Ivana- Sold Unsold.pdf18 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Siddhidata Infra (1)_compressed.pdf18 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Ivana.pdf22 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate - Ivana.pdf22 Apr 2024
Disclosure of sold/ booked inventoryFile: Ivana- Sold Unsold.pdf22 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Ivana_compressed.pdf22 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Ivana.pdf18 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Ivana.pdf18 Jan 2024
Disclosure of sold/ booked inventoryFile: Ivana- Sold Unsold.pdf18 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed (2).pdf18 Jan 2024
Layout approvalFile: 01_compressed.pdf25 Sep 2023
Building plan approvalFile: 02_compressed.pdf25 Sep 2023
PAN CardFile: Company Pan Card.pdf25 Sep 2023
Copy of the legal title reportFile: Revise Format A.pdf25 Sep 2023
Copy of the legal title reportFile: search report ivana_compressed (1).pdf25 Sep 2023
Details of encumbrances concerned to FinanceFile: Encumbrance (1).pdf25 Sep 2023
Details of encumbrances concerned to LegalFile: Encumbrance (1).pdf25 Sep 2023
Copy of Layout Approval (in case of layout)File: 01_compressed.pdf25 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: 02_compressed.pdf25 Sep 2023
Commencement Certificates / NA Order for plotted developmentFile: commecment ivana wakad_compressed.pdf25 Sep 2023
Declaration about Commencement CertificateFile: Format D.pdf25 Sep 2023
Declaration in FORM BFile: Notary- Promoter_compressed.pdf25 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (2)_compressed.pdf25 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Ivana.pdf25 Sep 2023
CERSAI detailsFile: Cersai Declaration (1).pdf25 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ilovepdf_merged_compressed (1).pdf25 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Ivana.pdf25 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure.pdf25 Sep 2023
Proforma of Allotment letterFile: Model form of AL - Ivana.pdf25 Sep 2023
Proforma of Agreement for saleFile: AFS- IVANA.pdf25 Sep 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format 1- Bank Ivana.pdf25 Sep 2023
Deviation Report with respect to Allotment letterFile: Deviation- AL.pdf25 Sep 2023
Deviation Report with respect to model copy of AgreementFile: Deviation- Afs.pdf25 Sep 2023

How this compares with Pune

70%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Ivana Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wakad13,700+ in Pune

Builder: Siddhidata Infra

Siddhidata Infra has 1 registration on MahaRERA, including Ivana Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Ivana Residency shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Ivana Residency is delayed beyond 31 May 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ivana Residency?

The registered promoter entity is Siddhidata Infra, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ivana Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Ivana Residency?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ivana Residency?

The professionals named in the filing: Architect: Ar Shubham Ombhase; Engineer: Mr Sujit Dashrath; Chartered Accountant: CA P G Agarwal and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ivana Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ivana Residency. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ivana Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.