Home / Browse projects / Thane, Maharashtra / ISHWAR NEW AMIT

Completed No litigation declared Others project

ISHWAR NEW AMIT

By ISHWAR DEVELOPERS

RG-MH-05338 · RERA P51700050877 · Last updated on MahaRERA portal: 5 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
May 2026Possession promisedregistration recorded completed
8 of 11Construction stages donefurthest along: Installation of Lifts, 95%
25 of 31Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 64 documents Report an error

ISHWAR NEW AMIT is a Others project by ISHWAR DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700050877 on 15 May 2023. The registration is recorded completed; possession was promised by 30 May 2026. The completion date has moved by 12 months from the original filing. 6 of the 31 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameISHWAR NEW AMIT
  • TypeOthers
  • Location
    • VADAVALI
    • Ambarnath(M Cl)
    • Ambarnath
    • Thane
    • 421501
  • Pincode421501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700050877
  • ReraGenie IDRG-MH-05338

Builder

  • NameISHWAR DEVELOPERS
  • Entity typePartnership
  • PartnersJAGDISH RAMA BANJAN, PRADEEP NATHU CHAVAN, BECHAR RAGHAVJI PATEL
  • Other registrations3 more →
  • Completed2 of 4
  • No longer live2 lapsed, de-registered or revoked

Key dates

this monthRegisteredMay 2023First promiseMay 2025Revised toMay 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on15 May 2023
  • Promised completion30 May 2026
  • Revised completionRevised to 30 May 2026 (originally 31 May 2025)
  • Buildings1 building record
  • Documents filed64 files

Current status

19%6 of 31 units booked
90.9%Work done, per cost certificate

Figures as on 5 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NEW AMIT CO OPERATIVE HOUSING SOCIETY LTDNA8826531

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

NEW AMIT CO OPERATIVE HOUSING SOCIETY LTD: 81% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 5 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed11

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots11
Open Space11

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area490 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Jul 2025
LandownerVillageDistrict
JANARDAN RAMSURAT YADAVAmbarnath(M Cl)Thane

Approvals and building plan

Sanctioning authorityAmbernath Nagar Parishad
Permissible FSI1579.8
Proposed, not sanctioned1,580 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPLOT NO 31, SURYODAY CO OP HOUSING SOCIETY, AMBERNATH EAST 421501
Estimated costRs 3.85 cr
Cost incurredRs 3.50 cr
Work done90.91%
BuildingWingEstimatedIncurred
NEW AMIT CO OPERATIVE HOUSING SOCIETY LTDNARs 3.60 crRs 3.30 cr
-NARs 25.00 lakhRs 20.00 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPRAMOD KAMBLE
EngineerPRAMOD KAMBLE
Chartered AccountantCHANCHLANI & ASSOCIATES
Chartered AccountantVRP ASSOCIATIES
PartnerRole in project
ISHWAR DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700028366May 2025 → May 2026

Reason as filed by the promoterWe are writing to request an extension for the completion date of our project “Ishwar New Amit”. The project is under construction & we have completed more than 75% work on the project. Despite our concerted efforts, we have encountered unforeseen challenges, namely a scarcity of essential construction materials and a shortage of skilled labor. there is a slight delay in finishing activities of the project. Under the above circumstances, we humbly request your kind consideration to grant an extension for the project completion date. The revised proposed date of completion as 30/05/2026 for our

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Mar 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Mar 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed64

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: arc new amit.pdf5 May 2026
Withdrawal Update Form 1File: Form 1 New Amit Q4.pdf5 May 2026
Withdrawal Update Form 2File: New Amit Engineers certificate Q3.pdf5 May 2026
Withdrawal Update Form 2File: Form 2 New Amit Q4_11zon.pdf5 May 2026
Withdrawal Update Form 3File: FORM3 0625 SIGN.pdf5 May 2026
Withdrawal Update Form 3File: FORM3 0625 SIGN.pdf5 May 2026
Occupational CertificateFile: 23684_signed.pdf5 May 2026
Withdrawal Update Form 1File: Form 1.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2.pdf20 Jan 2026
Withdrawal Update Form 3File: FORM3 0625 SIGN.pdf20 Jan 2026
Form 5 (FY 2024-2025)File: Ishwar developer Signed.pdf30 Sep 2025
Withdrawal Update Form 1File: Form 1-New Amit.pdf19 Jul 2025
Withdrawal Update Form 2File: Form 2-New Amit.pdf19 Jul 2025
Withdrawal Update Form 3File: FORM3 0625 SIGN.pdf19 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3 0325 sign.pdf7 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 4 Form2A FY24-25.pdf7 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A fy2324.pdf5 Jun 2025
Declaration in FORM BFile: ishwar new amit FORM B SIGNED.pdf3 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 new amit.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate new amit.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold New Amit.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect cert 311224.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer cert 311224.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECH FORM 1.pdf17 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate.pdf17 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: signed-Form 5 Ishwar Developer.pdf29 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NEW AMIT ARCHITECT.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: New Amit Engineer Certificte.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ishwar New Amit Architect's Certificate.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: New Amit Engineer's Certificate.pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arc certificate new amit.pdf17 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: eng certificate new amit.pdf17 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SIGNED CA certificate 30-06-23.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SIGNED CA certificate 30-09-23.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Cert 30-06-23.pdf16 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Cert 30-09-23.pdf16 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect New Amit 30-09-23.pdf14 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect New Amit 30-06-23.pdf14 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch Cert 30-06-23.pdf4 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf5 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf5 Apr 2023
CERSAI detailsFile: CERSAI P1.pdf1 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SIGNED CA certificate_11zon.pdf1 Apr 2023
Proforma of Agreement for saleFile: Draft Agreement for Sale.pdf1 Apr 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Declaration- Ishwar Developers-01-04-23.pdf1 Apr 2023
Deviation Report with respect to Allotment letterFile: 1 Deviation Allotment.pdf1 Apr 2023
Building plan approvalFile: Plan Layout Compressed.pdf31 Mar 2023
Copy of the legal title reportFile: SEARCH REPORT 1.pdf31 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan Layout Compressed.pdf31 Mar 2023
CERSAI detailsFile: Cersai Declaration.pdf31 Mar 2023
Layout approvalFile: Plan Layout Compressed.pdf30 Mar 2023
PAN CardFile: Firm Pan card.pdf30 Mar 2023
Copy of the legal title reportFile: Legal Title Compressed.pdf30 Mar 2023
Details of encumbrances concerned to FinanceFile: 1 No Encumbernace.pdf30 Mar 2023
Details of encumbrances concerned to LegalFile: 1 No Encumbernace.pdf30 Mar 2023
Copy of Layout Approval (in case of layout)File: Plan Layout Compressed.pdf30 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: CC compressed.pdf30 Mar 2023
Declaration about Commencement CertificateFile: Format D.pdf30 Mar 2023
Declaration in FORM BFile: notarized Form B jagdish_11zon.pdf30 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Annexure A- Jagdish.pdf30 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 2 Annexure A Pradeep.pdf30 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 3 Bechar Patel (1).pdf30 Mar 2023
Proforma of Allotment letterFile: Draft allotment letter compressed.pdf30 Mar 2023
Deviation Report with respect to model copy of AgreementFile: 1 Deviation Agreement.pdf30 Mar 2023

How this compares with Thane

19%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ISHWAR NEW AMIT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VADAVALI7,600+ in Thane

2 kmISHWAR NEW AMITCompleted 106Lapsed / revoked 37Other 82Dot size: filed unitsN

Filed coordinates, straight-line distance. 225 registered projects within 2 km.

Builder: ISHWAR DEVELOPERS

ISHWAR DEVELOPERS has 4 registrations on MahaRERA, including UMIYA LEELA APARTMENT and ISHWAR APARTMENT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if ISHWAR NEW AMIT is delayed beyond 30 May 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ISHWAR NEW AMIT?

The registered promoter entity is ISHWAR DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ISHWAR NEW AMIT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ISHWAR NEW AMIT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ISHWAR NEW AMIT?

The professionals named in the filing: Architect: PRAMOD KAMBLE; Engineer: PRAMOD KAMBLE; Chartered Accountant: CHANCHLANI & ASSOCIATES; Chartered Accountant: VRP ASSOCIATIES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ISHWAR NEW AMIT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ISHWAR NEW AMIT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ISHWAR NEW AMIT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.