Home / Browse projects / Mumbai Suburban, Maharashtra / IRENE WING A PHASE 1

Registration lapsed No litigation declared Residential / Group Housing project

IRENE WING A PHASE 1

By Sheth Creators and Sunvision Private Limited

RG-MH-76208 · RERA P51800015507 · Last updated on MahaRERA portal: 6 May 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 5 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
6 of 11Construction stages donefurthest along: Internal walls, 99%
5Complaints at MahaRERAon this registration
Jump to the 62 documents Report an error

IRENE WING A PHASE 1 is a Residential / Group Housing project by Sheth Creators and Sunvision Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800015507 on 7 Mar 2018. Possession was promised by 30 Dec 2025 and is now 10 months past that date. 5 complaints are on record with the regulator.

At a glance

Project

  • NameIRENE WING A PHASE 1
  • TypeResidential / Group Housing
  • Location
    • NEAR MITTAL COLLEGE
    • MALAD WEST
    • Andheri
    • Mumbai Suburban
    • 400064
  • Pincode400064
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800015507
  • ReraGenie IDRG-MH-76208

Builder

  • NameSheth Creators and Sunvision Private Limited
  • Entity typeCompany
  • DirectorsJitendra Natwarlal Sheth, Vallabh Natwarlal Sheth, Suraj Menghraj Shroff
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

10 months past promisethis monthRegisteredMar 2018PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on7 Mar 2018
  • Promised completion30 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed62 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
IRENE WING A PHASE 1NA680000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 99%.

IRENE WING A PHASE 1: 79% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks76%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.71%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.22%

Progress on shared amenities32

As on 6 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Yoga DeckYes0%
Alfresco DeckYes0%
AmphitheatreYes0%
BBQ DeckYes0%
Entrance LobbyYes0%
GymnasiumYes0%
Kids Play AreaYes0%
Walk WayYes0%
Tot Lot AreaYes0%
T V LoungeYes0%
Reflexology AreaYes0%
Reading ZoneYes0%
Party LawnYes0%
Outdoor SeatingYes0%
Old Falks CornerYes0%
Multi Purpose CourtYes0%
Landscape AreaYes0%

Parking filed285

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots285
Closed/Covered285

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area504 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI9000.0
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHallmark Business Plaza Near Guru Nanak Hospital Bandra East

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARUN GURAV
PartnerRole in project
Sheth Creators and Sunvision Private Limited-

Litigation declared7

CaseCourtStatus
7190 /2016MUMBAI HIGH COURTPENDING
1162/2016BOMBAY CITY CIVIL COURTPENDING
1016 /2012MUMBAI HIGH COURTPENDING
200274 /2016Honerable Court of Sessions for Borivali Division Goregaon BombayPENDING
80 /2010Additional Chief Metropolitan Magistrates twentyfourth CourtPENDING
SS/2400513 /2010Additional Chief Metropolitan Magistrates Twentyfourth CourtPENDING
331/2018BOMBAY CITY CIVIL COURTPENDING

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC006000000090091deepak kenisheth creators and sun vision pvt ltd15/07/2019
CC006000000591424Sidharth DhanjaniSheth Creators and Sunvision Private Limited04/08/2024
CC006000000303104Sheth Creators and Sun Vision Pvt. Ltd. Sheth Creators and Sun Vision Pvt. Ltd.Mr. Sumit Anil Shrivastava19/10/2022
CC006000000480068vicky madanmohan guptaSHETH CREATORS & SUN-VISION PRIVATE LIMITED13/04/2024
CC12600425Sheth Creators and Sunvision Private LimitedGanesh Bamnote23/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Feb 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Sep 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Sep 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 24 Apr 2025

Documents filed62

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: 19 Irene Tower-A As on Dec-23.pdf6 May 2025
Certificates of CA (Form 3)File: 21 Irene Tower-A As on 30 Mar-24.pdf6 May 2025
Certificates of CA (Form 3)File: 22 Irene Tower-A As on 30 June-24_compressed (1).pdf6 May 2025
Certificates of CA (Form 3)File: 24 Irene Tower-A As on 30 Sep-24.pdf6 May 2025
Certificates of CA (Form 3)File: 26 Irene Tower-A As on 31 Dec-24.pdf6 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 19 Irene Tower-A As on Dec-23.pdf6 May 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Letter Irene Sale Bldg A- wing.pdf24 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 TOWER A JUNE 2023.pdf18 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 TOWER A JUNE 2023.pdf18 Sep 2023
Certificates of CA (Form 3)File: FORM 3 TOWER A JUNE 2023.pdf18 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Tower A.pdf4 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Tower A.pdf4 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form-05_Irene_Tower-A_Mar-21[1].pdf2 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form-05 Irene Tower-A Mar-20.pdf24 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form-05 Irene Tower-A Mar-22.pdf24 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: irene a form 1.pdf10 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate -Irene Dec-22 - Tower-A.pdf10 Feb 2023
Certificates of CA (Form 3)File: 12 Irene Tower-A As on March-22_11zon.pdf6 Feb 2023
Certificates of CA (Form 3)File: 13 Irene Tower-A As on June-22_11zon.pdf6 Feb 2023
Certificates of CA (Form 3)File: 14 Irene Tower-A As on Sept-22_11zon.pdf6 Feb 2023
Certificates of CA (Form 3)File: 15 Irene Tower-A As on Dec-22.pdf6 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: CC Irene Sale 30 Aug 2022.pdf6 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer's Cirtificate Irene Tower A Date-31-Mar-2022.pdf7 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer's Certificate Irene Tower-A Date-30-Jun-2022.pdf7 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer's Certificate Irene, Tower -A Date- 30-Sep-2022.pdf7 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Irene -Tower A 30-Sep-2022.pdf5 Dec 2022
Layout approvalFile: IOA LAYOUT 19 08 2021.pdf9 Sep 2021
Building plan approvalFile: Irene Sale IOA 19 08 2021.pdf9 Sep 2021
Copy of Layout Approval (in case of layout)File: IOA LAYOUT 19 08 2021.pdf9 Sep 2021
Building Plan Approval (IOD)File: Irene Sale IOA 19 08 2021.pdf9 Sep 2021
Building plan approvalFile: Ammended letter Irene 07-08-2020 Wing A sale.pdf7 Sep 2020
Layout approvalFile: Irene Layout plan 02-03-2020 Malad.pdf7 Sep 2020
Copy of Layout Approval (in case of layout)File: Irene Layout plan 02-03-2020 Malad.pdf7 Sep 2020
Building Plan Approval (IOD)File: Ammended letter Irene 07-08-2020 Wing A sale.pdf7 Sep 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA Engineers Certificate - Irene, Form - 2 - Combined file.pdf1 Aug 2020
Certificates of CA (Form 3)File: 08 Irene - As on Mar-20- Form 3.pdf21 Jul 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: RERA - Irene Annual Audited Report 2018-19 Form - 5.pdf21 Jul 2020
Commencement Certificates / NA Order for plotted developmentFile: Sale Wing A Irene CC 05-03-2020 _For RERA1.pdf16 Jul 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering.pdf8 Jul 2020
Certificates of CA (Form 3)File: Form_3 Irena Tower A Phase-I.PDF8 Jul 2020
Building plan approvalFile: RERA IRENE IOA FEB 2020.pdf13 Feb 2020
Building Plan Approval (IOD)File: RERA IRENE IOA FEB 2020.pdf13 Feb 2020
Building plan approvalFile: IRENE AMENDED IOA.pdf11 Feb 2020
Building Plan Approval (IOD)File: IRENE AMENDED IOA.pdf11 Feb 2020
Certificates of CA (Form 3)File: CA Certificate IRENE Sept 18 as per 40 floors.pdf19 Dec 2019
Certificates of CA (Form 3)File: RERA Irene - Form -3 As on Sept-19.pdf19 Dec 2019
Certificates of CA (Form 5)File: RERA IRENE Form 5 March 19 dt 16 dec 2019.pdf19 Dec 2019
Certificates of CA (Form 3)File: CA Certificate IRENE Sept 18 as per 40 floors.pdf20 Feb 2019
Proforma of Allotment letterFile: RERA Agreement For Sale Irene.pdf4 Jan 2019
Certificates of CA (Form 5)File: Sunvision 30 sept 18.pdf3 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: Sale Bldg CC New Malad.pdf30 Mar 2018
Declaration in FORM BFile: Authority Letter for Form B - New Malad.pdf1 Mar 2018
Certificates of CA (Form 3)File: CA Certificate Irene.pdf1 Mar 2018
Proforma of Allotment letterFile: Performa for Agreement for Sale and Allotment Letter - New Malad.pdf1 Mar 2018
Declaration in FORM BFile: New Malad Form B for RERA.pdf23 Feb 2018
Building plan approvalFile: IOA New Malad.pdf21 Feb 2018
Layout approvalFile: Layout Plan New malad IOA.pdf21 Feb 2018
PAN CardFile: PAN CARD SUNVISION.pdf21 Feb 2018
Copy of the legal title reportFile: Title Certificate dated 13 02 2018 - New Malad compressed.pdf21 Feb 2018
Details of encumbrancesFile: Index-II.pdf21 Feb 2018
Copy of Layout Approval (in case of layout)File: Layout Plan New malad IOA.pdf21 Feb 2018
Building Plan Approval (IOD)File: IOA New Malad.pdf21 Feb 2018

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep IRENE WING A PHASE 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MALAD WEST6,700+ in Mumbai Suburban

2 kmIRENE WING A PHASE 1Completed 115Lapsed / revoked 68Other 134Dot size: filed unitsN

Filed coordinates, straight-line distance. 317 registered projects within 2 km.

Builder: Sheth Creators and Sunvision Private Limited

Sheth Creators and Sunvision Private Limited has 2 registrations on MahaRERA, including IRENE WING A PHASE 1 and IRENE WING B PHASE 1. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that IRENE WING A PHASE 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if IRENE WING A PHASE 1 is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of IRENE WING A PHASE 1?

The registered promoter entity is Sheth Creators and Sunvision Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in IRENE WING A PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against IRENE WING A PHASE 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for IRENE WING A PHASE 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at IRENE WING A PHASE 1?

The professionals named in the filing: Architect: ARUN GURAV. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in IRENE WING A PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About IRENE WING A PHASE 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save IRENE WING A PHASE 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.