Home / Browse projects / Pune, Maharashtra / iOS Tathawade

Registration lapsed No litigation declared Residential / Group Housing project

iOS Tathawade

By Linux Group

RG-MH-17145 · RERA P52100027952 · Last updated on MahaRERA portal: 14 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 48 complaints at MahaRERA
  • Completion date moved by 5 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
21 of 22Construction stages doneacross 2 buildings; furthest along: Stilt Floor, 0%
41 of 165Units unsoldnot recorded sold or booked
48Complaints at MahaRERAon this registration
Jump to the 106 documents Report an error

iOS Tathawade is a Residential / Group Housing project by Linux Group in Pune, Maharashtra, registered with MahaRERA as P52100027952 on 21 Jan 2021. Possession was promised by 30 Dec 2024 and is now 22 months past that date. The completion date has moved by 5 months from the original filing. 124 of the 165 units on this registration are recorded sold or booked, and 21 of 22 construction stages are filed complete. 48 complaints are on record with the regulator.

At a glance

Project

  • NameiOS Tathawade
  • TypeResidential / Group Housing
  • Location
    • Jeevan nagar
    • Tathawade
    • Tathwade
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100027952
  • ReraGenie IDRG-MH-17145

Builder

  • NameLinux Group
  • Entity typePartnership
  • GSTIN27AAHFL1485D1ZD
  • PartnerNidhi Rajput
  • PartnerSanjaykumar Tej Bahadur Singh
  • Other registrations5 more →
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

22 months past promisethis monthRegisteredJan 2021First promiseJul 2024Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on21 Jan 2021
  • Promised completion30 Dec 2024
  • Revised completionRevised to 30 Dec 2024 (originally 10 Jul 2024)
  • Buildings2 building records
  • Documents filed106 files

Current status

75%124 of 165 units booked
100.0%Work done, per cost certificate

Figures as on 14 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
iOS TathawadeNA17121400140
iOS ComplexNA4302525

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 14 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

21 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Stilt Floor, at 0%.

iOS Tathawade100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
iOS Complex91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 14 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed127

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots127
Closed/Covered2
Open Space125
BuildingClosed/CoveredOpen SpaceTotal
iOS Tathawade1100101
iOS Complex12526

Land and ownership6

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on14 Jan 2026
LandownerVillageDistrict
Linux GroupWakadPune
Mrs Kalabai alias Laxmi Bhagwant GaikwadPune (M Corp.)Pune
Smt. Phulbai Gulab GaradePune (M Corp.)Pune
Mrs Sulochana Anandrao GaradePune (M Corp.)Pune
Sanjay Kumar SinghBanerPune
Kalabai @ Laxmi Bhagwant GaikwadBanerPune

Approvals and building plan

Sanctioning authorityPCMC
Permissible FSI12265.59
Proposed, not sanctioned3,266 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchbavdhan,Pune-411045
Estimated costRs 42.00 cr
Cost incurredRs 42.00 cr
Work done100.0%
BuildingWingEstimatedIncurred
iOS TathawadeNARs 38.00 crRs 38.00 cr
-NARs 4.00 crRs 4.00 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Sidharth Harishndrakar
ArchitectA DESIGN STUDIO
EngineerSachin Pawar
Chartered AccountantCA Krinjal Shingavi
PartnerRole in project
Linux Group-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100021925Jul 2024 → Dec 2024

Reason as filed by the promoterThe reasons for Project Extension Application are e.g., financial crunch, market conditions, government Certificates like OCC, Fire NOC, Slow work speed because of heavy Rain like External Plaster, Painting, Project Internal Road etc.

Complaints filed with MahaRERA48

Case no.ComplainantRespondentFiled
CC005000000258823Mangesh Tukaram SurkarNeeraj04/08/2024
CC005000000289997ASHISH KASHINATH THAKREios Tathawade11/01/2024
CC005000000471303Nitin Karnish AgarwalSanjay Singh/ Linux Group04/08/2024
CC005000000471452Pankaj Prabhakar KhairnarLinux Group04/08/2024
CC005000000471548Vivek Ramrao LabhadeLinux Group15/08/2024
CC12400365SHIRISH VITTHALRAO DESHMUKHLinux Group07/10/2024
CC12400056Sumit Shashikant PatkiSumit Shashikant Patki (For Compensation)06/09/2024
CC12400329Mayur Rameshrao BijweLinux Group04/10/2024
CC12400341Swarup Sanjay SuryawanshiLinux Group05/10/2024
CC12400343SURAJ ASHOK BILONELinux Group05/10/2024
CC12400370Bhushan Narendra TeliLinux Group07/10/2024
CC12400344Nilesh Madhav KokaneLinux Group05/10/2024
CC12601180Nitin Harishchandra NawaleLinux Group04/03/2026
CC12400607Diptish Deepak KolekarLinux Group28/10/2024
CC12400374anil raman lala bankeyLinux Group08/10/2024
CC12400417Rahul Ankush BangarLinux Group15/10/2024
CC12400476shivkailash kaurbhan agarwalLinux Group20/10/2024
CC12401214ASHISH KASHINATH THAKRELinux Group24/12/2024
CC12500036Somnath Eknath NagareLinux Group04/01/2025
CC12500075LALIT MOHAN BADGUJARLinux Group08/01/2025
CC12500092VIKAS BHAGOJI BANDREvikas bandre09/01/2025
CC12600244Tushar JadhavLinux Group14/01/2026
CC12600976Uzma Ashraf LambeLinux Group23/02/2026
CC12600935Akhilesh Manohar KshirsagarLinux Group20/02/2026
CC12600975Rahul JagtapLinux Group23/02/2026
CC12600992Ashish PowarLinux Group23/02/2026
CC12600993Arjun PaithaneLinux Group23/02/2026
CC12600994Pankaj RakibeLinux Group23/02/2026
CC12600997Snehal BhavsarLinux Group24/02/2026
CC12601004Trunal ZambareLinux Group24/02/2026
CC12601157Shree KulkarniLinux Group03/03/2026
CC12601158Aamir Ashraf LambeyLinux Group03/03/2026
CC12601159Arunabh TripathiLinux Group03/03/2026
CC12601160SHUBHAM NERKARLinux Group03/03/2026
CC12601161Akash MalpaniLinux Group03/03/2026
CC12601166Ajit GangathadeLinux Group03/03/2026
CC12601169Tanaji SuryavanshiLinux Group03/03/2026
CC12601170Alpana GodboleLinux Group03/03/2026
CC12601171Somnath Eknath NagareLinux Group03/03/2026
CC12601173Chetan SonawaneLinux Group03/03/2026
CC12601175Pooja LavhaleLinux Group03/03/2026
CC12601472Manoj NavghareLinux Group16/03/2026
CC12601473Ritesh JaiswalLinux Group16/03/2026
CC12601476Deepak ShindeLinux Group17/03/2026
CC12601477Nikhil GhawadeLinux Group17/03/2026
CC12601478Swati KumariLinux Group17/03/2026
CC12602758Vishakha PatilLinux Group11/05/2026
CC12603078LALIT MOHAN BADGUJARLinux Group24/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Jan 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 May 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 May 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 14 Nov 2024

Documents filed106

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 106 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 3File: FORM 3-IOS A BLDG.pdf14 Jan 2026
Disclosure of Sold and Booked InventoryFile: Linux Group.pdf14 Jan 2026
Form 1File: form 1_page-0001.pdf14 Jan 2026
Form 2File: form 2 (1)_page-0001.pdf14 Jan 2026
Withdrawal Update Form 1File: form 1_page-0001.pdf14 Jan 2026
Withdrawal Update Form 1File: form 1_page-0001.pdf14 Jan 2026
Withdrawal Update Form 2File: form 2 for Extension.pdf14 Jan 2026
Withdrawal Update Form 2File: form 2 for Extension.pdf14 Jan 2026
Withdrawal Update Form 3File: FORM 3-IOS A BLDG.pdf14 Jan 2026
Withdrawal Update Form 3File: FORM 3-IOS A BLDG.pdf14 Jan 2026
Form 1File: form 1.pdf13 Jan 2026
Form 2File: form 2 (1).pdf13 Jan 2026
Form 3File: FORM 3-IOS A BLDG.pdf13 Jan 2026
Disclosure of Sold and Booked InventoryFile: Linux Group.pdf13 Jan 2026
Form 1File: form 1.pdf13 Jan 2026
Form 2File: form 2 (1).pdf13 Jan 2026
Form 3File: FORM 3-IOS A BLDG.pdf13 Jan 2026
Disclosure of Sold and Booked InventoryFile: Linux Group.pdf13 Jan 2026
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Competition A-Building, 150, 149-2 Thathwade.pdf14 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 IOS Extension.pdf3 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 IOS Extension.pdf2 Jul 2024
Declaration in FORM BFile: Form B for Extenstion.pdf7 Jun 2024
Declaration in FORM BFile: Form B for Extension.pdf7 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 for Extension.pdf7 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 for Extension.pdf7 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A for Extension.pdf7 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A for Extension.pdf7 Jun 2024
Disclosure of sold/ booked inventoryFile: Disclosure IOS tathawade.pdf7 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DocScanner Jul 25, 2023 5-06 PM_compressed.pdf25 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: DocScanner Jun 3, 2023 2-08 PM_compressed.pdf3 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: DocScanner Jun 3, 2023 2-11 PM_compressed.pdf3 Jun 2023
Layout approvalFile: SANCTION 1_compressed.pdf24 May 2023
Layout approvalFile: SANCTION 1_compressed.pdf24 May 2023
Layout approvalFile: SANCTION 2_compressed.pdf24 May 2023
Layout approvalFile: SANCTION 3 (2)_compressed.pdf24 May 2023
Layout approvalFile: SANCTION 4 (2)_compressed.pdf24 May 2023
Layout approvalFile: SANCTION 5_compressed.pdf24 May 2023
Layout approvalFile: SANCTION 6_compressed.pdf24 May 2023
Layout approvalFile: SANCTION 7 (1)_compressed.pdf24 May 2023
Layout approvalFile: SANCTION 8_compressed.pdf24 May 2023
Layout approvalFile: SANCTION 9_compressed.pdf24 May 2023
Building plan approvalFile: SANCTION 10_compressed.pdf24 May 2023
Layout approvalFile: SANCTION11_compressed.pdf24 May 2023
Copy of Layout Approval (in case of layout)File: SANCTION 1_compressed.pdf24 May 2023
Copy of Layout Approval (in case of layout)File: SANCTION 1_compressed.pdf24 May 2023
Copy of Layout Approval (in case of layout)File: SANCTION 2_compressed.pdf24 May 2023
Copy of Layout Approval (in case of layout)File: SANCTION 3 (2)_compressed.pdf24 May 2023
Copy of Layout Approval (in case of layout)File: SANCTION 4 (2)_compressed.pdf24 May 2023
Copy of Layout Approval (in case of layout)File: SANCTION 5_compressed.pdf24 May 2023
Copy of Layout Approval (in case of layout)File: SANCTION 6_compressed.pdf24 May 2023
Copy of Layout Approval (in case of layout)File: SANCTION 7 (1)_compressed.pdf24 May 2023
Copy of Layout Approval (in case of layout)File: SANCTION 8_compressed.pdf24 May 2023
Copy of Layout Approval (in case of layout)File: SANCTION 9_compressed.pdf24 May 2023
Copy of Layout Approval (in case of layout)File: SANCTION11_compressed.pdf24 May 2023
Building Plan Approval / NA Order for plotted developmentFile: SANCTION 10_compressed.pdf24 May 2023
Details of encumbrances concerned to FinanceFile: Mortgage deed 2023 regi index 2.pdf18 May 2023
Details of encumbrancesFile: Mortgage deed 2023 regi index 2.pdf18 May 2023
Details of encumbrances concerned to LegalFile: Mortgage deed 2023 regi index 2.pdf18 May 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: IOS Tathawade 150 bank statement.pdf21 Mar 2023
Details of encumbrancesFile: DocScanner Sep 28, 2022 11-57 AM.pdf28 Sep 2022
CERSAI detailsFile: CERSAI_Search_Report_200239439005_For_Asset_Based_Search_10_06_2022_13_23_09_832.pdf10 Jun 2022
Layout approvalFile: SANCTION 1_compressed_compressed (2).pdf27 Apr 2022
Copy of Layout Approval (in case of layout)File: SANCTION 1_compressed_compressed (2).pdf27 Apr 2022
Commencement Certificates / NA Order for plotted developmentFile: COMMESIMENT LATTER_compressed.pdf27 Apr 2022
Layout approvalFile: Tathawade 9-10_compressed.pdf4 Aug 2021
Layout approvalFile: Tathawade 7-10_compressed.pdf4 Aug 2021
Layout approvalFile: Tathawade 5-10_compressed.pdf4 Aug 2021
Layout approvalFile: Tathawade 2-10_compressed.pdf4 Aug 2021
Layout approvalFile: Tathawade 6-10_compressed.pdf4 Aug 2021
Layout approvalFile: Tathawade 8-10_compressed_compressed.pdf4 Aug 2021
Layout approvalFile: Tathawade 4-10_compressed.pdf4 Aug 2021
Layout approvalFile: Tathawade 3-10_compressed_compressed.pdf4 Aug 2021
Copy of Layout Approval (in case of layout)File: Tathawade 9-10_compressed.pdf4 Aug 2021
Copy of Layout Approval (in case of layout)File: Tathawade 7-10_compressed.pdf4 Aug 2021
Copy of Layout Approval (in case of layout)File: Tathawade 5-10_compressed.pdf4 Aug 2021
Copy of Layout Approval (in case of layout)File: Tathawade 2-10_compressed.pdf4 Aug 2021
Copy of Layout Approval (in case of layout)File: Tathawade 6-10_compressed.pdf4 Aug 2021
Copy of Layout Approval (in case of layout)File: Tathawade 8-10_compressed_compressed.pdf4 Aug 2021
Copy of Layout Approval (in case of layout)File: Tathawade 4-10_compressed.pdf4 Aug 2021
Copy of Layout Approval (in case of layout)File: Tathawade 3-10_compressed_compressed.pdf4 Aug 2021

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Bonheur A wingP52100032282vinode nagar, Pune64Dec 2021OngoingDec 2024Not delivered
BonheurP52100026648Vinode nagar, Pune69Oct 2020CompletedJun 2024Jun 2024
VientoP52100023329Sus, Pune-Dec 2019CompletedDec 2022Dec 2022

How this compares with Pune

75%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 5 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep iOS Tathawade on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Tathawade13,700+ in Pune

2 kmiOS TathawadeCompleted 102Lapsed / revoked 31Other 115Dot size: filed unitsN

Filed coordinates, straight-line distance. 248 registered projects within 2 km.

Builder: Linux Group

Linux Group has 6 registrations on MahaRERA, including Viento and Bonheur. Its filings disclose 5 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that iOS Tathawade shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if iOS Tathawade is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of iOS Tathawade?

The registered promoter entity is Linux Group, a partnership as per the filing. Its GSTIN 27AAHFL1485D1ZD can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in iOS Tathawade?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against iOS Tathawade?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for iOS Tathawade?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at iOS Tathawade?

The professionals named in the filing: Architect: Ar Sidharth Harishndrakar; Architect: A DESIGN STUDIO; Engineer: Sachin Pawar; Chartered Accountant: CA Krinjal Shingavi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in iOS Tathawade?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About iOS Tathawade. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save iOS Tathawade to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.