Home / Browse projects / Pune, Maharashtra / INFINITY WORLD

Completed No litigation declared Others project

INFINITY WORLD

By TULIP DEVELOPERS

RG-MH-05002 · RERA P52100021151 · Last updated on MahaRERA portal: 12 Apr 2025

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedregistration recorded completed
24 of 44Construction stages doneacross 4 buildings; furthest along: Staircases, 90%
1Complaints at MahaRERAon this registration
Jump to the 223 documents Report an error

INFINITY WORLD is a Others project by TULIP DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100021151 on 10 Jun 2019. The registration is recorded completed; possession was promised by 30 Dec 2026. 1 complaint is on record with the regulator.

At a glance

Project

  • NameINFINITY WORLD
  • TypeOthers
  • Location
    • PUNAWALE
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • RERA no.P52100021151
  • ReraGenie IDRG-MH-05002

Builder

  • NameTULIP DEVELOPERS
  • Entity typePartnership
  • Other registrations4 more →
  • Completed5 of 5

Key dates

this monthRegisteredJun 2019PromisedDec 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on10 Jun 2019
  • Promised completion30 Dec 2026
  • Revised completionNone
  • Buildings4 building records
  • Documents filed223 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA220000
B WINGNA220000
C WINGNA220000
D WINGNA230000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 12 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 90%.

A WING68%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B WING68%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C WING79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises25%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
D WING78%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 12 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed318

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots318
Closed/Covered227
Open Space91
BuildingClosed/CoveredOpen SpaceTotal
A WING572481
B WING572481
C WING562177
D WING572279

Land and ownership21

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners21
LandownerVillageDistrict
VAIBHAV SAMARTH DARSHALEPunawalePune
PUSHPA PANDURANG DARSHALEPunawalePune
POOJA PANDURANG DARSHALEPunawalePune
MANISHA SUNIL DARSHALEPunawalePune
ABHIJIT SUNIL DARSHALEPunawalePune
AKSHAY SUNIL DARSHALEPunawalePune
ARJUN DASHARATH DARSHALEPunawalePune
BHIMABAI ARJUN DARSHALEPunawalePune
YOGITA RAVINDRA DARSHALEPunawalePune
RUPALI MARUTI DARSHALEPunawalePune
SUVARNA NAVNATH GOREPunawalePune
PRAFUL KASHINATH DARSHALEPunawalePune
KISAN DASHRATH DARSHALEPunawalePune
SARUBAI KISAN DARSHALEPunawalePune
BALU KISAN DARSHALEPunawalePune
RUPALI BALU DARSHALEPunawalePune
SUNITA SANJAY BANEKARPunawalePune
ARATI KASHINATH DARSHALEPunawalePune
Satish Machindra DarshalePunawalePune
RUPALI SATISH DARSHALEPunawalePune
SAMARTH SOPAN DARSHALEPunawalePune

Approvals and building plan

Permissible FSI36000.81
Proposed, not sanctioned7,891 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRAVET, PRADHIKARAN, SECTOR 32A, PUNE 411044

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectLANDMARK DESIGN GROUP
EngineerM/S JW CONSULTANTS LLP (MR. UMESH JOSHI)
Chartered AccountantVaibhav Mayur
Chartered AccountantS U N S V G & Associates
PartnerRole in project
TULIP DEVELOPERS-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12600851Dashrath Vitthal PansareTULIP DEVELOPERS15/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 May 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Apr 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Oct 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 27 Jul 2024

Documents filed223

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 223 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Annual Report - TD World 04-04-2025.pdf12 Apr 2025
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 World.pdf9 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate Infinity World.pdf27 Jul 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Certificate Infinity World.pdf27 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate World Q1.pdf26 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 FY 2024-25 Q1 Infinity World.pdf26 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold world Q1.pdf26 Jul 2024
Certificates of CA (Form 3)File: Form 3 FY 2024-25 Q1 Infinity World.pdf26 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate Infinity World Q4.pdf4 Jul 2024
Certificates of CA (Form 3)File: Form 3 FY 2023-24 Q3.pdf4 Jul 2024
Certificates of CA (Form 3)File: Form 3 FY 2023-24 Q4.pdf4 Jul 2024
Disclosure of sold/ booked inventoryFile: Promoter Disclosure Q3 World.pdf1 Jul 2024
Disclosure of sold/ booked inventoryFile: Promoter Disclosure FY23-24 Infinity World Q4.pdf1 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A FY 23-24 Quality World.pdf5 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cirtificate World Q3.pdf17 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Infinity World Q4.pdf17 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate World Q3.pdf17 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Infinity World RERA Q2.pdf23 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Q2 IW.pdf23 Jan 2024
Disclosure of sold/ booked inventoryFile: Promoter Disclosure Infinity world Q2.pdf23 Jan 2024
Certificates of CA (Form 3)File: Form 3 - Infinity World FY 23-24 Q2.pdf23 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Annual Report - IW FY 2022-23.pdf10 Jan 2024
Declaration about Commencement CertificateFile: Declaration about commencement Certification.pdf25 Oct 2023
Building plan approvalFile: Plan 1.pdf22 Oct 2023
Building plan approvalFile: Plan 2.pdf22 Oct 2023
Building plan approvalFile: Plan 3.pdf22 Oct 2023
Building plan approvalFile: Plan 3.pdf22 Oct 2023
Building plan approvalFile: Plan 5.pdf22 Oct 2023
Building plan approvalFile: Plan 6.pdf22 Oct 2023
Building plan approvalFile: Plan 7.pdf22 Oct 2023
Building plan approvalFile: Plan 8.pdf22 Oct 2023
Building plan approvalFile: Plan 9.pdf22 Oct 2023
Building plan approvalFile: Plan 10.pdf22 Oct 2023
Building plan approvalFile: Plan 11.pdf22 Oct 2023
Building plan approvalFile: Plan 12.pdf22 Oct 2023
Building plan approvalFile: Plan 13.pdf22 Oct 2023
Building Plan Approval (IOD)File: Plan 1.pdf22 Oct 2023
Building Plan Approval (IOD)File: Plan 2.pdf22 Oct 2023
Building Plan Approval (IOD)File: Plan 3.pdf22 Oct 2023
Building Plan Approval (IOD)File: Plan 3.pdf22 Oct 2023
Building Plan Approval (IOD)File: Plan 5.pdf22 Oct 2023
Building Plan Approval (IOD)File: Plan 6.pdf22 Oct 2023
Building Plan Approval (IOD)File: Plan 7.pdf22 Oct 2023
Building Plan Approval (IOD)File: Plan 8.pdf22 Oct 2023
Building Plan Approval (IOD)File: Plan 9.pdf22 Oct 2023
Building Plan Approval (IOD)File: Plan 10.pdf22 Oct 2023
Building Plan Approval (IOD)File: Plan 11.pdf22 Oct 2023
Building Plan Approval (IOD)File: Plan 12.pdf22 Oct 2023
Building Plan Approval (IOD)File: Plan 13.pdf22 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: Commncement Certificate_21-06-2023.pdf22 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Cirtificate IW Q1.pdf6 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- IW Q1.pdf6 Sep 2023
Disclosure of sold/ booked inventoryFile: Promoter Disclosure - IW Q1.pdf6 Sep 2023
Certificates of CA (Form 3)File: CA Certificate Form 3 IW (Q1).pdf6 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate IW Q2.pdf19 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate- IW Q2.pdf19 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineers Certificate on Quality Assurance 22-23.pdf19 Jul 2023
Disclosure of sold/ booked inventoryFile: Promoters Disclosure - IW Q2.pdf19 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineers Certificate World Q4 Quality.pdf27 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Rera Architect Certificate 12-04-2023 World_compressed.pdf3 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate World Q4 Cost_compressed.pdf3 May 2023
Disclosure of sold/ booked inventoryFile: Promoters Disclosure World Q4_compressed.pdf3 May 2023
Certificates of CA (Form 3)File: Form 3_compressed.pdf3 May 2023
PAN CardFile: PAN Card - TD.pdf1 Apr 2023
Details of encumbrances concerned to FinanceFile: Encumm.pdf1 Apr 2023
Details of encumbrances concerned to LegalFile: Encumm.pdf1 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineers Certificate Quality World ABCD Q4.pdf1 Apr 2023
Proforma of Agreement for saleFile: AFS.pdf1 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Infinity World FY 19-20.pdf31 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Infinity World FY 20-21.pdf31 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Infinity World FY 21-22.pdf31 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate (Infinity World) Q3.pdf5 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate-World Q3.pdf5 Mar 2023
Disclosure of sold/ booked inventoryFile: Promoters Disclosure-World-Q3.pdf5 Mar 2023
Certificates of CA (Form 3)File: CA Certificate Q3 IW.pdf5 Mar 2023
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate-World.pdf10 Dec 2022
Certificates of CA (Form 3)File: CA Certificate Q2 IW - Final.pdf3 Dec 2022
Certificates of CA (Form 3)File: CA Certificate Q2 IW (1).pdf29 Nov 2022
Building plan approvalFile: Plan 7.pdf6 Sep 2022
Building plan approvalFile: Plan 5.pdf6 Sep 2022

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep INFINITY WORLD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUNAWALE13,700+ in Pune

Builder: TULIP DEVELOPERS

TULIP DEVELOPERS has 5 registrations on MahaRERA, including INFINITY TOWER - B WING and SHUBHKALASH B WING. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if INFINITY WORLD is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of INFINITY WORLD?

The registered promoter entity is TULIP DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in INFINITY WORLD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against INFINITY WORLD?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for INFINITY WORLD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at INFINITY WORLD?

The professionals named in the filing: Architect: LANDMARK DESIGN GROUP; Engineer: M/S JW CONSULTANTS LLP (MR. UMESH JOSHI); Chartered Accountant: Vaibhav Mayur; Chartered Accountant: S U N S V G & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in INFINITY WORLD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About INFINITY WORLD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save INFINITY WORLD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.