Home / Browse projects / Raigarh, Maharashtra / INFINITY IVY

Completed No litigation declared Others project

INFINITY IVY

By INFINITY BUILDERS & DEVELOPERS

RG-MH-29099 · RERA P52000027689 · Last updated on MahaRERA portal: 9 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
8 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 95%
28 of 45Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 95 documents Report an error

INFINITY IVY is a Others project by INFINITY BUILDERS & DEVELOPERS in Raigarh, Maharashtra, registered with MahaRERA as P52000027689 on 31 Dec 2020. The registration is recorded completed; possession was promised by 31 Dec 2025. The completion date has moved by 18 months from the original filing. 17 of the 45 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NameINFINITY IVY
  • TypeOthers
  • Location
    • SECTOR 52
    • NAVI MUMBAI
    • Bokadvira
    • Uran
    • Raigarh
    • 400702
  • Pincode400702
  • RERA no.P52000027689
  • ReraGenie IDRG-MH-29099

Builder

  • NameINFINITY BUILDERS & DEVELOPERS
  • Entity typePartnership
  • PartnerBIMLA RULDURAM JINDAL
  • Other registrations1 more →
  • Completed2 of 2
  • Declared earlier projects3 →

Key dates

this monthRegisteredDec 2020First promiseJun 2024Revised toDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Dec 2020
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2024)
  • Buildings1 building record
  • Documents filed95 files

Current status

38%17 of 45 units booked
92.2%Work done, per cost certificate

Figures as on 9 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
INFINITY IVYNA8741445

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

INFINITY IVY: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 9 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed14

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots14
Closed/Covered14

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area850 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityCIDCO LTD
Permissible FSI1272.86
Proposed, not sanctioned1,273 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAPMC VASHI SEC 19D
Estimated costRs 5.05 cr
Cost incurredRs 4.65 cr
Work done92.16%
BuildingWingEstimatedIncurred
INFINITY IVYNARs 4.77 crRs 4.43 cr
-NARs 28.00 lakhRs 22.40 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHEMANT DHAVALE
EngineerA G GOKHALE
Chartered AccountantCA HITESH M SHAH
Chartered AccountantP. R. VORA & ASSOCIATES
PartnerRole in project
INFINITY BUILDERS & DEVELOPERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000024207Jun 2024 → Jun 2025

Reason as filed by the promoterSince the project got delayed due to issues with labour contractor.

EA03072501945Jun 2024 → Dec 2025

Reason as filed by the promoterThe project got delayed due to issues with labour contractor.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Dec 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Dec 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Dec 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Dec 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed95

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 95 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Mail Occupancy Certificate granted on plot no 87 Sector 52 at Dronagiri Navi Mumbai by CID9 Jul 2026
Occupational CertificateFile: FORM 4.pdf14 May 2026
Occupational CertificateFile: Form 1.pdf14 May 2026
Withdrawal Update Form 1File: fINAL fORM 1.pdf25 Dec 2025
Withdrawal Update Form 1File: fINAL fORM 1.pdf25 Dec 2025
Withdrawal Update Form 2File: fINAL fORM 2.pdf25 Dec 2025
Withdrawal Update Form 2File: fINAL fORM 2.pdf25 Dec 2025
Withdrawal Update Form 3File: fINAL fORM 3.pdf25 Dec 2025
Withdrawal Update Form 3File: fINAL fORM 3.pdf25 Dec 2025
Occupational CertificateFile: Infinty IVY OC Copy_Signed.pdf25 Dec 2025
Form 5 (FY 2023-2024)File: Final Form 5.pdf1 Jul 2025
Form 5 (FY 2022-2023)File: Form-5.pdf1 Jul 2025
Form 1File: Final Form 1.pdf30 Jun 2025
Form 2File: Final Form 2.pdf30 Jun 2025
Form 3File: Final FORM 3.pdf30 Jun 2025
Disclosure of Sold and Booked InventoryFile: Inventory Sold Letter June-24 (Plot-87).pdf30 Jun 2025
Form 1File: Final Form 1.pdf30 Jun 2025
Form 2File: Final Form 2.pdf30 Jun 2025
Form 3File: Final FORM 3.pdf30 Jun 2025
Disclosure of Sold and Booked InventoryFile: Inventory Sold Letter Sep-24 (Plot-87).pdf30 Jun 2025
Form 1File: Form -1.pdf30 Jun 2025
Form 2File: form no-2.pdf30 Jun 2025
Form 3File: Final Form 3.pdf30 Jun 2025
Disclosure of Sold and Booked InventoryFile: Inventory Sold Letter Sep-23 (Plot-87).pdf30 Jun 2025
Form 1File: Form 1_.pdf30 Jun 2025
Form 2File: Form 2.pdf30 Jun 2025
Form 3File: Form 3 with sign.pdf30 Jun 2025
Disclosure of Sold and Booked InventoryFile: Inventory Sold Letter Dec-23 (Plot-87).pdf30 Jun 2025
Form 1File: FORM 1.pdf30 Jun 2025
Form 2File: FORM 2.pdf30 Jun 2025
Form 3File: Form 3 with sign.pdf30 Jun 2025
Disclosure of Sold and Booked InventoryFile: Sold Inventory details.pdf30 Jun 2025
Form 1File: Form 1 - Triarch.pdf30 Jun 2025
Form 2File: Form 2 - A G Gokhle.pdf30 Jun 2025
Form 3File: Final FORM 3.pdf30 Jun 2025
Disclosure of Sold and Booked InventoryFile: Inventory Sold Letter Dec-24 (Plot-87).pdf30 Jun 2025
Disclosure of Sold and Booked InventoryFile: Inventory Sold Letter March-25 (Plot-87).pdf30 Jun 2025
Form 1File: fINAL fORM 1.pdf30 Jun 2025
Form 2File: fINAL fORM 2.pdf30 Jun 2025
Form 3File: fINAL fORM 3.pdf30 Jun 2025
Form 1File: FORM 1.pdf30 Jun 2025
Form 2File: FORM 2.pdf30 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold_ booked inventory.pdf30 Jun 2025
Form 3File: fINAL fORM 3.pdf30 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Triarch.pdf7 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final FORM 3.pdf7 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - A G Gokhle.pdf7 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final FORM 3.pdf18 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final FORM 3.pdf18 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form 1.pdf27 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final Form 1.pdf27 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Final Form 2.pdf27 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Final Form 2.pdf27 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Final Form 5.pdf30 Oct 2024
Declaration in FORM BFile: FORM B.pdf29 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf29 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 with sign.pdf29 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 with sign.pdf29 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf27 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf27 Jun 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory details.pdf27 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_.pdf3 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf3 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3 march 23_11zon.pdf30 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3.pdf30 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1.pdf17 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form no-2.pdf17 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form no-5.pdf17 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE 87.pdf5 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf5 May 2023
Disclosure of sold/ booked inventoryFile: Inventory Sold Letter.pdf5 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf28 Feb 2023
Details of encumbrances concerned to FinanceFile: Decalaration of legal.pdf18 Feb 2023
Details of encumbrances concerned to LegalFile: Decalaration of legal.pdf18 Feb 2023
Declaration about Commencement CertificateFile: Declataion CC.pdf18 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf18 Feb 2023
Disclosure of sold/ booked inventoryFile: Inventory sold letter.pdf18 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration of separate bank.pdf18 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 infinity.PDF5 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5_compressed (1).pdf25 Feb 2022

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
INFINITY ELITEP52000003960NAVI MUMBAI, Raigarh-Aug 2017CompletedDec 2022Dec 2022
INFINITY AVENUEPLOT NO 47B SEC 8 ULWE20-CompletedJun 2015Late, Sep 2015

How this compares with Raigarh

38%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 18 months
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep INFINITY IVY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NAVI MUMBAI5,900+ in Raigarh

Builder: INFINITY BUILDERS & DEVELOPERS

infinity builders & developers has 2 registrations on MahaRERA, including infiniti homes and INFINITY IVY. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if INFINITY IVY is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of INFINITY IVY?

The registered promoter entity is INFINITY BUILDERS & DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in INFINITY IVY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for INFINITY IVY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at INFINITY IVY?

The professionals named in the filing: Architect: HEMANT DHAVALE; Engineer: A G GOKHALE; Chartered Accountant: CA HITESH M SHAH; Chartered Accountant: P. R. VORA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in INFINITY IVY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About INFINITY IVY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save INFINITY IVY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.