Indrayani
RG-MH-26156 · RERA P51700012357 · Last updated on MahaRERA portal: 31 Oct 2022
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
- 8 complaints at MahaRERA
- Completion date moved by 66 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Indrayani is a Residential / Group Housing project by Jangid Developers in Thane, Maharashtra, registered with MahaRERA as P51700012357 on 1 Sep 2017. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 66 months from the original filing. 8 complaints are on record with the regulator.
At a glance
Project
- NameIndrayani
- TypeResidential / Group Housing
- Location
- Mira-Bhayandar (M Corp.)
- Thane
- 401107
- Pincode401107
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700012357
- ReraGenie IDRG-MH-26156
Builder
- NameJangid Developers
- Entity typePartnership
- PartnersOmprakash Leelaram Jangid, Purshottam Leelaram Jangid, Jangid Developers Pvt Ltd, Leelaram Sagataram Jangid
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on1 Sep 2017
- Promised completion31 Dec 2024
- Revised completionRevised to 31 Dec 2024 (originally 30 Jun 2019)
- Buildings2 building records
- Documents filed47 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A Wing | NA | 16 | 0 | 0 | 0 | 0 |
| B Wing | NA | 23 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 31 Oct 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 76%.
A Wing66%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 76% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 55% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
B Wing66%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 76% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 55% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Progress on shared amenities15
As on 31 Oct 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 40% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed26
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A Wing | 25 | 25 |
| B Wing | 1 | 1 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Chetan Sarvaiya |
| Engineer | Desai & Associates |
| Partner | Role in project |
|---|---|
| Jangid Developers | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoteras per letter attached
Reason as filed by the promoterScarcity of Materials & Funds
Complaints filed with MahaRERA8
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000012736 | ARCHANA SANDEEP MATTA | M/S. JANGID DEVELOPERS | 21/05/2018 |
| CC006000000023892 | Lad Harikishan Kaur | Jangid Group | 26/03/2018 |
| CC006000000193075 | Natwar Agarwal | Jangid Developers Pvt. Ltd. | 12/06/2020 |
| CC006000000057956 | CHANDRASHEKAR DEVADIGA | Jangid Developers | 05/02/2019 |
| CC006000000192930 | Indrayani A CHS Ltd | Jangid Developers | 11/03/2020 |
| CC006000000193986 | VARUGHESE KOSHY | Jangid Developers | 11/09/2020 |
| CC006000000292875 | Natwar Hariprasad Agrawal | JANGID DEVELOPERS | 06/10/2022 |
| CC12502278 | Vishal Pramodkumar Sharma | Jangid Developers | 06/07/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Sep 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Sep 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed47
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Proforma of Agreement for saleFile: Indrayani B Agreement - as per RERA.pdf | 31 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: JD-Disclosure of Sold - Booked Inventory 21 Sep 2022.pdf | 11 Oct 2022 |
| Layout approvalFile: MYSCAN_20220915_0003.pdf | 17 Sep 2022 |
| Layout approvalFile: MYSCAN_20220915_0004.pdf | 17 Sep 2022 |
| Layout approvalFile: MYSCAN_20220915_0005.pdf | 17 Sep 2022 |
| Layout approvalFile: MYSCAN_20220915_0006.pdf | 17 Sep 2022 |
| Layout approvalFile: MYSCAN_20220915_0007.pdf | 17 Sep 2022 |
| Copy of Layout Approval (in case of layout)File: MYSCAN_20220915_0003.pdf | 17 Sep 2022 |
| Copy of Layout Approval (in case of layout)File: MYSCAN_20220915_0004.pdf | 17 Sep 2022 |
| Copy of Layout Approval (in case of layout)File: MYSCAN_20220915_0005.pdf | 17 Sep 2022 |
| Copy of Layout Approval (in case of layout)File: MYSCAN_20220915_0006.pdf | 17 Sep 2022 |
| Copy of Layout Approval (in case of layout)File: MYSCAN_20220915_0007.pdf | 17 Sep 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Indrayani B Wing CC_.pdf | 17 Sep 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_Indrayani.pdf | 16 Jul 2022 |
| Declaration about Commencement CertificateFile: Jangid Developer - Declaration.pdf | 15 Jul 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Jangid Developer Form 2A Mar 22.pdf | 15 Jul 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Jangid Developer Form 2A Mar 22.pdf | 15 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: JD - Discolsure Of sold -Booked Inventory Jun 22.pdf | 15 Jul 2022 |
| Certificates of CA (Form 5)File: JD_FORM 5 _March 2018.pdf | 13 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: JD_FORM 5_March 2019.pdf | 13 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: JD_FORM 5_March 2020.pdf | 13 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: JD_FORM 5_March 2021.pdf | 13 Jul 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: JD_Indrayani- Form 2A Jun21.pdf | 22 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: JD_Indrayani- Form 2A Sep21.pdf | 22 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: JD_Indrayani- Form 2A Sep21.pdf | 22 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: JD_Indrayani- Form 2A Jun19.pdf | 9 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: JD_Indrayani- Form 2A Sep19.pdf | 9 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: JD_Indrayani- Form 2A Dec19.pdf | 9 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: JD_Indrayani- Form 2A Mar20.pdf | 9 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: JD_Indrayani- Form 2A Jun20.pdf | 9 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: JD_Indrayani- Form 2A Sep20.pdf | 9 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: JD_Indrayani- Form 2A Dec20.pdf | 9 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: JD_Indrayani- Form 2A Mar21.pdf | 9 Oct 2021 |
| Certificates of CA (Form 5)File: Form 5 Indrayani.PDF | 18 Jul 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Indrayani CC 1.PDF | 30 Mar 2018 |
| Building plan approvalFile: Indrayani CC.pdf | 30 Jul 2017 |
| Layout approvalFile: Indrayani Layout.pdf | 30 Jul 2017 |
| PAN CardFile: PAN Jangid Developers.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: Title Indrayani.pdf | 30 Jul 2017 |
| Details of encumbrancesFile: JD - Indrayani non eNc.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Indrayani Layout.pdf | 30 Jul 2017 |
| Building Plan Approval (IOD)File: Indrayani CC.pdf | 30 Jul 2017 |
| Declaration in FORM BFile: Form B Indrayani .pdf | 30 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - Form 1.pdf | 30 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate -Form 2.pdf | 30 Jul 2017 |
| Certificates of CA (Form 3)File: Indrayani CA Form 3.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: JD Agree.PDF | 30 Jul 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Saryu | Jangid Complex MTNL Road Mira Road East Thane 401107 | 60 | Completed | Nov 2014 | Nov 2014 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 47 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Indrayani on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mira-Bhayandar (M Corp.)7,600+ in Thane
Filed coordinates, straight-line distance. 272 registered projects within 2 km.
Codename StarLife
JP Infra Realty Private Limited
Prestige Garden Trails
PRESTIGE ESTATES PROJECTS LIMITED
TIARA HILLS PHASE I BLDG NO 3, 5 AND 2
PNK SPACE DEVELOPMENT PVT LTD
The Palace Tower B
JP Infra Realty Private Limited
Sector 2A - Wings JKL
Eversmile Properties Private Limited
CRESCENT WTC - WESTERN TRADE CENTER - PHASE -
CRESCENT SHELTERS
See every Thane project, with the district possession charts
Builder: Jangid Developers
Jangid Developers has 1 registration on MahaRERA, including Indrayani. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that Indrayani shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Indrayani is delayed beyond 31 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Indrayani?
The registered promoter entity is Jangid Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Indrayani?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Indrayani?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Indrayani?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Indrayani?
The professionals named in the filing: Architect: Chetan Sarvaiya; Engineer: Desai & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Indrayani?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.