INDRAPRASTHANAGARI-PHASE 1
RG-MH-25893 · RERA P52100014352 · Last updated on MahaRERA portal: 15 Jan 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 28 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 66 months
- 7 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
INDRAPRASTHANAGARI-PHASE 1 is a Residential / Group Housing project by D.B.DEVELOPERS LTD in Pune, Maharashtra, registered with MahaRERA as P52100014352 on 24 Nov 2017. Possession was promised by 30 Jun 2024 and is now 28 months past that date. The completion date has moved by 66 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameINDRAPRASTHANAGARI-PHASE 1
- TypeResidential / Group Housing
- Location
- MIDC Road
- wadgaon
- Wadagaon (CT)
- Mawal
- Pune
- 412106
- Pincode412106
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100014352
- ReraGenie IDRG-MH-25893
Builder
- NameD.B.DEVELOPERS LTD
- Entity typeCompany
- PartnersMADHURI DILIP GAIKWAD, PREM DILIP GAIKWAD, VAIBHAV DILIP GAIKWAD, SHANKAR DNYANOBA KALBHOR, SANJAY NARAYAN JOSHI, SAHEBRAO NAMDEO MANDE, KRUSHNAMURTY VYANKATESH DESAI
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on24 Nov 2017
- Promised completion30 Jun 2024
- Revised completionRevised to 30 Jun 2024 (originally 31 Dec 2018)
- Buildings3 building records
- Documents filed51 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| INDRAPRASTHANAGARI A -PHASE 1 | NA | 9 | 0 | 0 | 0 | 0 |
| INDRAPRASTHANAGARI-B PHASE 1 | NA | 9 | 0 | 0 | 0 | 0 |
| INDRAPRASTHANAGARI-C PHASE 1 | NA | 9 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 15 Jan 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
15 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 90%.
INDRAPRASTHANAGARI A -PHASE 176%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 5% |
INDRAPRASTHANAGARI-B PHASE 154%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
INDRAPRASTHANAGARI-C PHASE 154%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 15 Jan 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 90% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed3
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| INDRAPRASTHANAGARI A -PHASE 1 | 1 | 1 |
| INDRAPRASTHANAGARI-B PHASE 1 | 1 | 1 |
| INDRAPRASTHANAGARI-C PHASE 1 | 1 | 1 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| GAYATRI BUILDERS | Nigade | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MANISH KUTE |
| Partner | Role in project |
|---|---|
| D.B.DEVELOPERS LTD | - |
Extensions applied for7
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe promoter has completed the project around 65% but due to lack of funds for completing the project, promoter is seeking the extension of project completion date for one year. It is also stated that the Promoter will be completing the project within the extended date of completion i.e. 31/12/2020. The Promoter is carrying on construction work on daily basis and for the purpose of extension of project completion permission of Allottees is acquired by the Promoter. A copy of resolution of Allottee is attached wherein the total units sold is 45 and total permission of allottee received is 28 un
Reason as filed by the promoterWE HAVE A DELAY OF SHORT FUND PROBLEM FOR COMPLETION THE CONSTRUCTION ACTIVITIES IN SITE, WE ARE SURE THAT COMPLETED ALL ACTIVATE BEFOUL DELAY DATE .
Reason as filed by the promoterThe promoter has completed the project around 66 % but due to lack of funds for completing the project, promoter is seeking the extension of project completion date for one year. It is also stated that the Promoter will be completing the project within the extended date of completion . The Promoter is carrying on construction work on daily basis and for the purpose of extension of project completion permission of Allottees is acquired by the Promoter. A copy of resolution of Allottee is attached wherein the total units sold is 48 and total permission of allottee received is 24 units for extens
Reason as filed by the promoterwe have done almost 95% Building work completed I need some more time for compilation certificate and society formation formality so I request you please give me some time
Reason as filed by the promoterThe said extension for project completion to the promoter may be granted till 31/12/2022 so that shall be completed and possession shall be given to the unit purchasers in the said project D.B.DEVELOPERS LTD. The said extension may be given in the promoter was not able to complete the project due to short of funds for construction. but we are 98% work done request you please give me last extation and handover building .
Reason as filed by the promoterNEED SOME MORE TIME FOR SOCETY FORMATION AND BUILDING OUTSIDE WORK COMPLITION WORK
Reason as filed by the promoterAlthough we have completed 98% of the project, we need more time for work and occupancy certificate, we request you to give us some time.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000053820 | DINESH KUMAR AND GAYATRI RAJBALLI PRASAD | D B DEVELOPERS LIMITED | 26/12/2019 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Nov 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Sep 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Sep 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 Jul 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed51
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: FORM 3 DB (1).pdf | 15 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 DB.pdf | 15 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FY 21-22.pdf | 15 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 D B.pdf | 13 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 DB.pdf | 13 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A D B.pdf | 13 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOUSER.pdf | 13 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: archi certificates final.pdf | 27 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Site superwiser.pdf | 27 Jan 2023 |
| Declaration about Commencement CertificateFile: form d.pdf | 26 Jan 2023 |
| Declaration in FORM BFile: affidevit cum decl form B.pdf | 26 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form no1.pdf | 26 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: sold unsold.pdf | 26 Jan 2023 |
| Certificates of CA (Form 3)File: ca form 3.pdf | 26 Jan 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: ann-a db.pdf | 11 Jan 2023 |
| Proforma of Agreement for saleFile: agg gor sale db.pdf | 9 Jan 2023 |
| CERSAI detailsFile: CERSAI.pdf | 9 Sep 2022 |
| Deviation Report with respect to model copy of AgreementFile: db agg.pdf | 9 Sep 2022 |
| Details of encumbrances concerned to LegalFile: FORM B_11zon.pdf | 25 Aug 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK FORMAT A .pdf | 19 Aug 2022 |
| Deviation Report with respect to Allotment letterFile: ALLOTMENT DB_1-2_11zon.pdf | 19 Aug 2022 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf | 29 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: avl list db-converted (12).pdf | 29 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: avl list db-pdf.pdf | 29 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engg Cert 2-converted.pdf | 23 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Cert 1-converted.pdf | 23 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: DBG_2019-20_FORM 5.pdf | 23 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: DBG_2020-21_FORM 5.pdf | 23 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: DB Developers LTD_2018-19_Form 5.pdf | 27 Dec 2019 |
| Certificates of CA (Form 5)File: jpg2pdf.pdf | 15 Oct 2018 |
| Certificates of CA (Form 5)File: C A DB.pdf | 15 Oct 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: CC1.pdf | 2 Jul 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: CC2.pdf | 2 Jul 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: CC3.pdf | 2 Jul 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: CC4.pdf | 2 Jul 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: CC5.pdf | 2 Jul 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: CC6.pdf | 2 Jul 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: CC7.pdf | 2 Jul 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: CC8.pdf | 2 Jul 2018 |
| Certificates of CA (Form 3)File: CA CERTIFICAT-ilovepdf-compressed.pdf | 10 Nov 2017 |
| Copy of the legal title reportFile: Legal title Report.pdf | 7 Nov 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certi.pdf | 6 Nov 2017 |
| Proforma of Allotment letterFile: Agreement Draft as per rera.pdf | 6 Nov 2017 |
| Building plan approvalFile: Project Layout.pdf | 19 Sep 2017 |
| Layout approvalFile: Indraprasthanagari Project Layout final.pdf | 19 Sep 2017 |
| Details of encumbrancesFile: No Encumbrances Certificate.pdf | 19 Sep 2017 |
| Copy of Layout Approval (in case of layout)File: Indraprasthanagari Project Layout final.pdf | 19 Sep 2017 |
| Building Plan Approval (IOD)File: Project Layout.pdf | 19 Sep 2017 |
| PAN CardFile: PAN CARD.pdf | 18 Sep 2017 |
| Declaration in FORM BFile: Declaration B.pdf | 18 Sep 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTI.pdf | 18 Sep 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 51 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep INDRAPRASTHANAGARI-PHASE 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near wadgaon13,700+ in Pune
Filed coordinates, straight-line distance. 26 registered projects within 2 km.
Residential Building on CTS No 107/1P -GIRIVAR
SHRIVAR BUILDERS LLP
Aranya
Naiknavare Township LLP.
Land of Dreams
Krisala Buildscape LLP
Mount Vista
Tirupati Lands and Building Constructions
Osian LifeLands 2
Planet-i Realty
RKL INDRAYANI CITY
R K LUNKAD HOUSING COMPANY
Builder: D.B.DEVELOPERS LTD
D.B.DEVELOPERS LTD has 1 registration on MahaRERA, including INDRAPRASTHANAGARI-PHASE 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that INDRAPRASTHANAGARI-PHASE 1 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if INDRAPRASTHANAGARI-PHASE 1 is delayed beyond 30 Jun 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of INDRAPRASTHANAGARI-PHASE 1?
The registered promoter entity is D.B.DEVELOPERS LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in INDRAPRASTHANAGARI-PHASE 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against INDRAPRASTHANAGARI-PHASE 1?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for INDRAPRASTHANAGARI-PHASE 1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at INDRAPRASTHANAGARI-PHASE 1?
The professionals named in the filing: Architect: MANISH KUTE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in INDRAPRASTHANAGARI-PHASE 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback