Home / Browse projects / Pune, Maharashtra / INDRAPRASTHANAGARI-PHASE 1

Registration lapsed No litigation declared Residential / Group Housing project

INDRAPRASTHANAGARI-PHASE 1

By D.B.DEVELOPERS LTD

RG-MH-25893 · RERA P52100014352 · Last updated on MahaRERA portal: 15 Jan 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 28 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 66 months
  • 7 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2024Possession promised28 months past this date
15 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 90%
1Complaints at MahaRERAon this registration
Jump to the 51 documents Report an error

INDRAPRASTHANAGARI-PHASE 1 is a Residential / Group Housing project by D.B.DEVELOPERS LTD in Pune, Maharashtra, registered with MahaRERA as P52100014352 on 24 Nov 2017. Possession was promised by 30 Jun 2024 and is now 28 months past that date. The completion date has moved by 66 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameINDRAPRASTHANAGARI-PHASE 1
  • TypeResidential / Group Housing
  • Location
    • MIDC Road
    • wadgaon
    • Wadagaon (CT)
    • Mawal
    • Pune
    • 412106
  • Pincode412106
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100014352
  • ReraGenie IDRG-MH-25893

Builder

  • NameD.B.DEVELOPERS LTD
  • Entity typeCompany
  • PartnersMADHURI DILIP GAIKWAD, PREM DILIP GAIKWAD, VAIBHAV DILIP GAIKWAD, SHANKAR DNYANOBA KALBHOR, SANJAY NARAYAN JOSHI, SAHEBRAO NAMDEO MANDE, KRUSHNAMURTY VYANKATESH DESAI

Key dates

28 months past promisethis monthRegisteredNov 2017First promiseDec 2018Revised toJun 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Nov 2017
  • Promised completion30 Jun 2024
  • Revised completionRevised to 30 Jun 2024 (originally 31 Dec 2018)
  • Buildings3 building records
  • Documents filed51 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
INDRAPRASTHANAGARI A -PHASE 1NA90000
INDRAPRASTHANAGARI-B PHASE 1NA90000
INDRAPRASTHANAGARI-C PHASE 1NA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 15 Jan 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 90%.

INDRAPRASTHANAGARI A -PHASE 176%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.5%
INDRAPRASTHANAGARI-B PHASE 154%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
INDRAPRASTHANAGARI-C PHASE 154%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 15 Jan 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes50%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed3

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3
Closed/Covered3
BuildingClosed/CoveredTotal
INDRAPRASTHANAGARI A -PHASE 111
INDRAPRASTHANAGARI-B PHASE 111
INDRAPRASTHANAGARI-C PHASE 111

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area14,700 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
GAYATRI BUILDERSNigadePune

Approvals and building plan

Permissible FSI9264.86
Proposed, not sanctioned9,265 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKOREGAONPARK,285,KOREGAONROAD, ,TARABAUG, PUNE,411001

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMANISH KUTE
PartnerRole in project
D.B.DEVELOPERS LTD-

Extensions applied for7

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100005196Dec 2018 → Dec 2020

Reason as filed by the promoterThe promoter has completed the project around 65% but due to lack of funds for completing the project, promoter is seeking the extension of project completion date for one year. It is also stated that the Promoter will be completing the project within the extended date of completion i.e. 31/12/2020. The Promoter is carrying on construction work on daily basis and for the purpose of extension of project completion permission of Allottees is acquired by the Promoter. A copy of resolution of Allottee is attached wherein the total units sold is 45 and total permission of allottee received is 28 un

EXT52100001422Dec 2018 → Dec 2020

Reason as filed by the promoterWE HAVE A DELAY OF SHORT FUND PROBLEM FOR COMPLETION THE CONSTRUCTION ACTIVITIES IN SITE, WE ARE SURE THAT COMPLETED ALL ACTIVATE BEFOUL DELAY DATE .

EXT52100011017Dec 2018 → Aug 2022

Reason as filed by the promoterThe promoter has completed the project around 66 % but due to lack of funds for completing the project, promoter is seeking the extension of project completion date for one year. It is also stated that the Promoter will be completing the project within the extended date of completion . The Promoter is carrying on construction work on daily basis and for the purpose of extension of project completion permission of Allottees is acquired by the Promoter. A copy of resolution of Allottee is attached wherein the total units sold is 48 and total permission of allottee received is 24 units for extens

EXT52100013567Dec 2018 → May 2023

Reason as filed by the promoterwe have done almost 95% Building work completed I need some more time for compilation certificate and society formation formality so I request you please give me some time

EXT52100012536Dec 2018 → Dec 2022

Reason as filed by the promoterThe said extension for project completion to the promoter may be granted till 31/12/2022 so that shall be completed and possession shall be given to the unit purchasers in the said project D.B.DEVELOPERS LTD. The said extension may be given in the promoter was not able to complete the project due to short of funds for construction. but we are 98% work done request you please give me last extation and handover building .

EXT52100016620Dec 2018 → Oct 2023

Reason as filed by the promoterNEED SOME MORE TIME FOR SOCETY FORMATION AND BUILDING OUTSIDE WORK COMPLITION WORK

EXT52100018796Dec 2018 → Jun 2024

Reason as filed by the promoterAlthough we have completed 98% of the project, we need more time for work and occupancy certificate, we request you to give us some time.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000053820DINESH KUMAR AND GAYATRI RAJBALLI PRASADD B DEVELOPERS LIMITED26/12/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Nov 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Sep 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Sep 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Jul 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed51

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: FORM 3 DB (1).pdf15 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 DB.pdf15 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FY 21-22.pdf15 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 D B.pdf13 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 DB.pdf13 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A D B.pdf13 Jan 2024
Disclosure of sold/ booked inventoryFile: DISCLOUSER.pdf13 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: archi certificates final.pdf27 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Site superwiser.pdf27 Jan 2023
Declaration about Commencement CertificateFile: form d.pdf26 Jan 2023
Declaration in FORM BFile: affidevit cum decl form B.pdf26 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form no1.pdf26 Jan 2023
Disclosure of sold/ booked inventoryFile: sold unsold.pdf26 Jan 2023
Certificates of CA (Form 3)File: ca form 3.pdf26 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: ann-a db.pdf11 Jan 2023
Proforma of Agreement for saleFile: agg gor sale db.pdf9 Jan 2023
CERSAI detailsFile: CERSAI.pdf9 Sep 2022
Deviation Report with respect to model copy of AgreementFile: db agg.pdf9 Sep 2022
Details of encumbrances concerned to LegalFile: FORM B_11zon.pdf25 Aug 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK FORMAT A .pdf19 Aug 2022
Deviation Report with respect to Allotment letterFile: ALLOTMENT DB_1-2_11zon.pdf19 Aug 2022
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf29 Oct 2021
Disclosure of sold/ booked inventoryFile: avl list db-converted (12).pdf29 Oct 2021
Disclosure of sold/ booked inventoryFile: avl list db-pdf.pdf29 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engg Cert 2-converted.pdf23 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Cert 1-converted.pdf23 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: DBG_2019-20_FORM 5.pdf23 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: DBG_2020-21_FORM 5.pdf23 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: DB Developers LTD_2018-19_Form 5.pdf27 Dec 2019
Certificates of CA (Form 5)File: jpg2pdf.pdf15 Oct 2018
Certificates of CA (Form 5)File: C A DB.pdf15 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: CC1.pdf2 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: CC2.pdf2 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: CC3.pdf2 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: CC4.pdf2 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: CC5.pdf2 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: CC6.pdf2 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: CC7.pdf2 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: CC8.pdf2 Jul 2018
Certificates of CA (Form 3)File: CA CERTIFICAT-ilovepdf-compressed.pdf10 Nov 2017
Copy of the legal title reportFile: Legal title Report.pdf7 Nov 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certi.pdf6 Nov 2017
Proforma of Allotment letterFile: Agreement Draft as per rera.pdf6 Nov 2017
Building plan approvalFile: Project Layout.pdf19 Sep 2017
Layout approvalFile: Indraprasthanagari Project Layout final.pdf19 Sep 2017
Details of encumbrancesFile: No Encumbrances Certificate.pdf19 Sep 2017
Copy of Layout Approval (in case of layout)File: Indraprasthanagari Project Layout final.pdf19 Sep 2017
Building Plan Approval (IOD)File: Project Layout.pdf19 Sep 2017
PAN CardFile: PAN CARD.pdf18 Sep 2017
Declaration in FORM BFile: Declaration B.pdf18 Sep 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTI.pdf18 Sep 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 66 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep INDRAPRASTHANAGARI-PHASE 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near wadgaon13,700+ in Pune

2 kmINDRAPRASTHANAGARI-PHASECompleted 12Lapsed / revoked 11Other 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 26 registered projects within 2 km.

Builder: D.B.DEVELOPERS LTD

D.B.DEVELOPERS LTD has 1 registration on MahaRERA, including INDRAPRASTHANAGARI-PHASE 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that INDRAPRASTHANAGARI-PHASE 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if INDRAPRASTHANAGARI-PHASE 1 is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of INDRAPRASTHANAGARI-PHASE 1?

The registered promoter entity is D.B.DEVELOPERS LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in INDRAPRASTHANAGARI-PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against INDRAPRASTHANAGARI-PHASE 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for INDRAPRASTHANAGARI-PHASE 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at INDRAPRASTHANAGARI-PHASE 1?

The professionals named in the filing: Architect: MANISH KUTE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in INDRAPRASTHANAGARI-PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About INDRAPRASTHANAGARI-PHASE 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save INDRAPRASTHANAGARI-PHASE 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.