Indira Landmark Phase 2
RG-MH-22568 · RERA P52100032996 · Last updated on MahaRERA portal: 12 Oct 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 60 months, 4 of them under MahaRERA's automatic 4-month extension
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Indira Landmark Phase 2 is a Residential / Group Housing project by Bhgyashri Vasant Bhide in Pune, Maharashtra, registered with MahaRERA as P52100032996 on 3 Feb 2022. Possession is promised by 30 Oct 2027. The completion date has moved by 60 months from the original filing, 4 of them under MahaRERA's automatic 4-month extension for the West Asia conflict. 10 of the 22 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete.
At a glance
Project
- NameIndira Landmark Phase 2
- TypeResidential / Group Housing
- Location
- Kushaba Ganpat Ovhal
- Sadashiv Peth Rajendranagar
- Pune (M Corp.)
- Pune City
- Pune
- 411030
- Pincode411030
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100032996
- ReraGenie IDRG-MH-22568
Builder
- NameBhgyashri Vasant Bhide
- Entity typeIndividual
- Other registrations1 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on3 Feb 2022
- Promised completion30 Oct 2027
- Revised completionRevised to 30 Oct 2027 (originally 31 Oct 2022)
- Buildings1 building record
- Documents filed67 files
Current status
Figures as on 12 Oct 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Indira Landmark | NA | 14 | 11 | 20 | 2 | 22 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 12 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
Indira Landmark: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 12 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Bhagyashri Constructions | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Indira Landmark | NA | Rs 6.44 cr | Rs 6.44 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Kanhekar Prakash |
| Engineer | Saummitra Joag |
| Chartered Accountant | neeren Randive & Associates |
| Chartered Accountant | Neeren Ravidra Ranadive |
| Partner | Role in project |
|---|---|
| Bhgyashri Vasant Bhide | - |
Extensions2
A revised date filed with the regulator does not change the possession date in your agreement for sale. Commentary on the order notes that a buyer's right to interest for delay under section 18 of RERA may still stand; that question has not been tested.
Granted by MahaRERA, not applied for by the promoterMahaRERA's order of 7 August 2026 extended the completion date of eligible registered projects by four months, treating the West Asia conflict as force majeure. Promoters did not have to apply for it.
Reason as filed by the promoterThe Construction of project is 100% complete , not a single pending work has left. But we are in the process of getting completion certificate from Pune Municipal Corpartion under their discount scheme for developmental charges we shall be taking completion flat wise one by one under the said scheme. So untill we reeive the completion and sell the flats we are seeking and requesting for this extension. We already are attaching the consent letter from allottees of sold flats for the same.
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 1167/2012 | Civil Court Sr Div pune | Evidence pending |
| 2693/2012 | Civil Court Sr Div pune | Evidence pending |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Dec 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Nov 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Nov 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Oct 2027
Documents filed67
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1_ Sep 26.pdf | 12 Oct 2026 |
| Withdrawal Update Form 2File: Form 2_Sep 26.pdf | 12 Oct 2026 |
| Withdrawal Update Form 3File: RERA Form 3 As on 30_09_2026-new.pdf | 12 Oct 2026 |
| Form 2A (FY 2024-2025)File: Form 2A-24_25.pdf | 12 Oct 2026 |
| Form 2A (FY 2025-2026)File: Form 2A_FY_25-26.pdf | 12 Oct 2026 |
| Form 5 (FY 2024-2025)File: Form 5.pdf | 12 Oct 2026 |
| Form 5 (FY 2025-2026)File: Form 5.pdf | 12 Oct 2026 |
| Withdrawal Update Form 1File: Form 1_June 25.pdf | 7 Oct 2026 |
| Withdrawal Update Form 1File: Form 1_Sep 25.pdf | 7 Oct 2026 |
| Withdrawal Update Form 1File: Form 1_Dec 25.pdf | 7 Oct 2026 |
| Withdrawal Update Form 1File: Form 1_March 26.pdf | 7 Oct 2026 |
| Withdrawal Update Form 1File: Form 1_June 26.pdf | 7 Oct 2026 |
| Withdrawal Update Form 2File: Form 2_June 25.pdf | 7 Oct 2026 |
| Withdrawal Update Form 2File: Form 2_Sep 25.pdf | 7 Oct 2026 |
| Withdrawal Update Form 2File: Form 2_Dec 25.pdf | 7 Oct 2026 |
| Withdrawal Update Form 2File: Form 2_March 26.pdf | 7 Oct 2026 |
| Withdrawal Update Form 2File: Form 2_March 26.pdf | 7 Oct 2026 |
| Withdrawal Update Form 3File: Form 3_June 25.pdf | 7 Oct 2026 |
| Withdrawal Update Form 3File: Form 3_Sep 25.pdf | 7 Oct 2026 |
| Withdrawal Update Form 3File: Form 3_Dec 25.pdf | 7 Oct 2026 |
| Withdrawal Update Form 3File: Form 3_March 26.pdf | 7 Oct 2026 |
| Withdrawal Update Form 3File: Form 3_June 26-new.pdf | 7 Oct 2026 |
| Form 1File: Form 1 MahaReRa.pdf | 14 Aug 2025 |
| Form 3File: MAHARERA Form 3 Bhagyashri Constructions CA Certficate.pdf | 14 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Declaration of Sold Unsold at Indira Landmark phase 2.pdf | 14 Aug 2025 |
| Self-declaration of Quarterly ProgressFile: RERA Self Declaration for Quarterly progress Phase 2.pdf | 14 Aug 2025 |
| Form 2File: Form 2 2022.pdf | 14 Aug 2025 |
| OthersFile: Form 4 MahaReRa.pdf | 14 Aug 2025 |
| Form 1File: Form 1 MahaReRa.pdf | 14 Aug 2025 |
| Form 2File: Form 2 2022.pdf | 14 Aug 2025 |
| Form 3File: MAHARERA Form 3 Bhagyashri Constructions CA Certficate.pdf | 14 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Declaration of Sold Unsold at Indira Landmark phase 2.pdf | 14 Aug 2025 |
| Self-declaration of Quarterly ProgressFile: RERA Self Declaration for Quarterly progress Phase 2.pdf | 14 Aug 2025 |
| OthersFile: Form 4 MahaReRa.pdf | 14 Aug 2025 |
| Form 1File: Form 1 MahaReRa.pdf | 14 Aug 2025 |
| Form 2File: Form 2 2022.pdf | 14 Aug 2025 |
| Form 3File: MAHARERA Form 3 Bhagyashri Constructions CA Certficate.pdf | 14 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Declaration of Sold Unsold at Indira Landmark phase 2.pdf | 14 Aug 2025 |
| Form 1File: Form 1 MahaReRa.pdf | 14 Aug 2025 |
| Form 2File: Form 2 2022.pdf | 14 Aug 2025 |
| Form 3File: MAHARERA Form 3 Bhagyashri Constructions CA Certficate.pdf | 14 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Declaration of Sold Unsold at Indira Landmark phase 2.pdf | 14 Aug 2025 |
| Self-declaration of Quarterly ProgressFile: RERA Self Declaration for Quarterly progress Phase 2.pdf | 14 Aug 2025 |
| OthersFile: Form 4 MahaReRa.pdf | 14 Aug 2025 |
| Form 2A (FY 2021-2022)File: Form 2A .pdf | 14 Aug 2025 |
| Form 2A (FY 2022-2023)File: Form 2A (1).pdf | 14 Aug 2025 |
| Declaration in FORM BFile: Affadavit Cum Declaration Form B.pdf | 31 Jan 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200228702431_For_Asset_Based_Search_25_01_2022_09_23_08_344.pdf | 25 Jan 2022 |
| Copy of the legal title reportFile: Title Search Report as per MahaRera Compressed.pdf | 14 Dec 2021 |
| Details of encumbrancesFile: Affadavit On Legal Encumbernces.pdf | 14 Dec 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate for Rera Phase 2.pdf | 30 Nov 2021 |
| CERSAI detailsFile: CERSAI Affadavit.pdf | 26 Nov 2021 |
| Proforma of Allotment letterFile: Draft Agreement to Sale Indira Landmark.pdf | 22 Nov 2021 |
| Declaration about Commencement CertificateFile: Declaration about commencement certificate (2).pdf | 10 Nov 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Declaration of Quality Assurance Certificate 31st Dec 2021.pdf | 10 Nov 2021 |
| Layout approvalFile: Indira Landmark Phase 2 santion Plan and layout.pdf | 6 Nov 2021 |
| Building plan approvalFile: Indira Landmark Phase 2 Building Plan Approval.pdf | 6 Nov 2021 |
| Copy of Layout Approval (in case of layout)File: Indira Landmark Phase 2 santion Plan and layout.pdf | 6 Nov 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Indira Landmark Phase 2 Building Plan Approval.pdf | 6 Nov 2021 |
| Declaration in FORM BFile: Affadavit Cum Declaration As Per Form B Of RERA.pdf | 6 Nov 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3 for year upto 31st March 2021.pdf | 6 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: CA Certificate Form 5 for year upto 2019.pdf | 6 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA Certificate Form 3 for year upto 2019.pdf | 6 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA Certificate Form 5 for year upto 31st March 2021.pdf | 6 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA Certificate Form 5 for year upto 31st March 2021.pdf | 6 Nov 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Indira Landmark.pdf | 30 Oct 2021 |
| PAN CardFile: Mrs Bhagyashri Bhide PAN.pdf | 29 Oct 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 14,000+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 67 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Indira Landmark Phase 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Sadashiv Peth Rajendranagar14,000+ in Pune
Filed coordinates, straight-line distance. 312 registered projects within 2 km.
NYATI EVANIA
NYATI CONSTRUCTION PRIVATE LIMITED
CENTRALVISTA
NAIKNAVARE DEVELOPERS PVT. LTD.
Guardian Cityscapes Phase-3
Guardian Homes Private Limited
SARASNAGAR
CITY ETHERNAL LLP
PROFITBAY
LAXMI SPACECON LLP
SUN GLORY
Jindal Mittal Graha Nirman Pvt. Ltd.
Builder: Bhgyashri Vasant Bhide
Bhgyashri Vasant Bhide has 2 registrations on MahaRERA, including INDIRA LANDMARK and Indira Landmark Phase 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Indira Landmark Phase 2 is delayed beyond 30 Oct 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Indira Landmark Phase 2?
The registered promoter entity is Bhgyashri Vasant Bhide, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Indira Landmark Phase 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Indira Landmark Phase 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Indira Landmark Phase 2?
The professionals named in the filing: Architect: Kanhekar Prakash; Engineer: Saummitra Joag; Chartered Accountant: neeren Randive & Associates; Chartered Accountant: Neeren Ravidra Ranadive. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Indira Landmark Phase 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback