ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Indira Landmark Phase 2

Registered No litigation declared Residential / Group Housing project

Indira Landmark Phase 2

By Bhgyashri Vasant Bhide

RG-MH-22568 · RERA P52100032996 · Last updated on MahaRERA portal: 12 Oct 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 60 months, 4 of them under MahaRERA's automatic 4-month extension
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Oct 2027Possession promisedmoved 60 months from the original
11 of 11Construction stages doneevery applicable stage filed complete
12 of 22Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 67 documents Report an error

Indira Landmark Phase 2 is a Residential / Group Housing project by Bhgyashri Vasant Bhide in Pune, Maharashtra, registered with MahaRERA as P52100032996 on 3 Feb 2022. Possession is promised by 30 Oct 2027. The completion date has moved by 60 months from the original filing, 4 of them under MahaRERA's automatic 4-month extension for the West Asia conflict. 10 of the 22 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete.

At a glance

Project

  • NameIndira Landmark Phase 2
  • TypeResidential / Group Housing
  • Location
    • Kushaba Ganpat Ovhal
    • Sadashiv Peth Rajendranagar
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411030
  • Pincode411030
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100032996
  • ReraGenie IDRG-MH-22568

Builder

  • NameBhgyashri Vasant Bhide
  • Entity typeIndividual
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredFeb 2022First promiseOct 2022Revised toOct 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 Feb 2022
  • Promised completion30 Oct 2027
  • Revised completionRevised to 30 Oct 2027 (originally 31 Oct 2022)
  • Buildings1 building record
  • Documents filed67 files

Current status

45%10 of 22 units booked
100.0%Work done, per cost certificate

Figures as on 12 Oct 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Indira LandmarkNA141120222

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

Indira Landmark: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 12 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,023 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Bhagyashri ConstructionsPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI6398.0
Proposed, not sanctioned4,146 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch1732 Sadashiv Peth Near Grahak Peth Pune 411030
Estimated costRs 6.44 cr
Cost incurredRs 6.44 cr
Work done100.0%
BuildingWingEstimatedIncurred
Indira LandmarkNARs 6.44 crRs 6.44 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKanhekar Prakash
EngineerSaummitra Joag
Chartered Accountantneeren Randive & Associates
Chartered AccountantNeeren Ravidra Ranadive
PartnerRole in project
Bhgyashri Vasant Bhide-

Extensions2

A revised date filed with the regulator does not change the possession date in your agreement for sale. Commentary on the order notes that a buyer's right to interest for delay under section 18 of RERA may still stand; that question has not been tested.

MahaRERA order of 7 Aug 2026Jun 2027 → Oct 2027

Granted by MahaRERA, not applied for by the promoterMahaRERA's order of 7 August 2026 extended the completion date of eligible registered projects by four months, treating the West Asia conflict as force majeure. Promoters did not have to apply for it.

EA26082502446Oct 2022 → Jun 2027

Reason as filed by the promoterThe Construction of project is 100% complete , not a single pending work has left. But we are in the process of getting completion certificate from Pune Municipal Corpartion under their discount scheme for developmental charges we shall be taking completion flat wise one by one under the said scheme. So untill we reeive the completion and sell the flats we are seeking and requesting for this extension. We already are attaching the consent letter from allottees of sold flats for the same.

Litigation declared2

CaseCourtStatus
1167/2012Civil Court Sr Div puneEvidence pending
2693/2012Civil Court Sr Div puneEvidence pending

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Dec 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Nov 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Nov 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Oct 2027

Documents filed67

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1_ Sep 26.pdf12 Oct 2026
Withdrawal Update Form 2File: Form 2_Sep 26.pdf12 Oct 2026
Withdrawal Update Form 3File: RERA Form 3 As on 30_09_2026-new.pdf12 Oct 2026
Form 2A (FY 2024-2025)File: Form 2A-24_25.pdf12 Oct 2026
Form 2A (FY 2025-2026)File: Form 2A_FY_25-26.pdf12 Oct 2026
Form 5 (FY 2024-2025)File: Form 5.pdf12 Oct 2026
Form 5 (FY 2025-2026)File: Form 5.pdf12 Oct 2026
Withdrawal Update Form 1File: Form 1_June 25.pdf7 Oct 2026
Withdrawal Update Form 1File: Form 1_Sep 25.pdf7 Oct 2026
Withdrawal Update Form 1File: Form 1_Dec 25.pdf7 Oct 2026
Withdrawal Update Form 1File: Form 1_March 26.pdf7 Oct 2026
Withdrawal Update Form 1File: Form 1_June 26.pdf7 Oct 2026
Withdrawal Update Form 2File: Form 2_June 25.pdf7 Oct 2026
Withdrawal Update Form 2File: Form 2_Sep 25.pdf7 Oct 2026
Withdrawal Update Form 2File: Form 2_Dec 25.pdf7 Oct 2026
Withdrawal Update Form 2File: Form 2_March 26.pdf7 Oct 2026
Withdrawal Update Form 2File: Form 2_March 26.pdf7 Oct 2026
Withdrawal Update Form 3File: Form 3_June 25.pdf7 Oct 2026
Withdrawal Update Form 3File: Form 3_Sep 25.pdf7 Oct 2026
Withdrawal Update Form 3File: Form 3_Dec 25.pdf7 Oct 2026
Withdrawal Update Form 3File: Form 3_March 26.pdf7 Oct 2026
Withdrawal Update Form 3File: Form 3_June 26-new.pdf7 Oct 2026
Form 1File: Form 1 MahaReRa.pdf14 Aug 2025
Form 3File: MAHARERA Form 3 Bhagyashri Constructions CA Certficate.pdf14 Aug 2025
Disclosure of Sold and Booked InventoryFile: Declaration of Sold Unsold at Indira Landmark phase 2.pdf14 Aug 2025
Self-declaration of Quarterly ProgressFile: RERA Self Declaration for Quarterly progress Phase 2.pdf14 Aug 2025
Form 2File: Form 2 2022.pdf14 Aug 2025
OthersFile: Form 4 MahaReRa.pdf14 Aug 2025
Form 1File: Form 1 MahaReRa.pdf14 Aug 2025
Form 2File: Form 2 2022.pdf14 Aug 2025
Form 3File: MAHARERA Form 3 Bhagyashri Constructions CA Certficate.pdf14 Aug 2025
Disclosure of Sold and Booked InventoryFile: Declaration of Sold Unsold at Indira Landmark phase 2.pdf14 Aug 2025
Self-declaration of Quarterly ProgressFile: RERA Self Declaration for Quarterly progress Phase 2.pdf14 Aug 2025
OthersFile: Form 4 MahaReRa.pdf14 Aug 2025
Form 1File: Form 1 MahaReRa.pdf14 Aug 2025
Form 2File: Form 2 2022.pdf14 Aug 2025
Form 3File: MAHARERA Form 3 Bhagyashri Constructions CA Certficate.pdf14 Aug 2025
Disclosure of Sold and Booked InventoryFile: Declaration of Sold Unsold at Indira Landmark phase 2.pdf14 Aug 2025
Form 1File: Form 1 MahaReRa.pdf14 Aug 2025
Form 2File: Form 2 2022.pdf14 Aug 2025
Form 3File: MAHARERA Form 3 Bhagyashri Constructions CA Certficate.pdf14 Aug 2025
Disclosure of Sold and Booked InventoryFile: Declaration of Sold Unsold at Indira Landmark phase 2.pdf14 Aug 2025
Self-declaration of Quarterly ProgressFile: RERA Self Declaration for Quarterly progress Phase 2.pdf14 Aug 2025
OthersFile: Form 4 MahaReRa.pdf14 Aug 2025
Form 2A (FY 2021-2022)File: Form 2A .pdf14 Aug 2025
Form 2A (FY 2022-2023)File: Form 2A (1).pdf14 Aug 2025
Declaration in FORM BFile: Affadavit Cum Declaration Form B.pdf31 Jan 2022
CERSAI detailsFile: CERSAI_Search_Report_200228702431_For_Asset_Based_Search_25_01_2022_09_23_08_344.pdf25 Jan 2022
Copy of the legal title reportFile: Title Search Report as per MahaRera Compressed.pdf14 Dec 2021
Details of encumbrancesFile: Affadavit On Legal Encumbernces.pdf14 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate for Rera Phase 2.pdf30 Nov 2021
CERSAI detailsFile: CERSAI Affadavit.pdf26 Nov 2021
Proforma of Allotment letterFile: Draft Agreement to Sale Indira Landmark.pdf22 Nov 2021
Declaration about Commencement CertificateFile: Declaration about commencement certificate (2).pdf10 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Declaration of Quality Assurance Certificate 31st Dec 2021.pdf10 Nov 2021
Layout approvalFile: Indira Landmark Phase 2 santion Plan and layout.pdf6 Nov 2021
Building plan approvalFile: Indira Landmark Phase 2 Building Plan Approval.pdf6 Nov 2021
Copy of Layout Approval (in case of layout)File: Indira Landmark Phase 2 santion Plan and layout.pdf6 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: Indira Landmark Phase 2 Building Plan Approval.pdf6 Nov 2021
Declaration in FORM BFile: Affadavit Cum Declaration As Per Form B Of RERA.pdf6 Nov 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3 for year upto 31st March 2021.pdf6 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: CA Certificate Form 5 for year upto 2019.pdf6 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA Certificate Form 3 for year upto 2019.pdf6 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA Certificate Form 5 for year upto 31st March 2021.pdf6 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA Certificate Form 5 for year upto 31st March 2021.pdf6 Nov 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Indira Landmark.pdf30 Oct 2021
PAN CardFile: Mrs Bhagyashri Bhide PAN.pdf29 Oct 2021

How this compares with Pune

45%of this project is bookeddistrict median 29%
28%of Pune projects moved their completion datethis one moved by 60 months
25%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 14,000+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Indira Landmark Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Sadashiv Peth Rajendranagar14,000+ in Pune

2 kmIndira Landmark Phase 2Completed 82Lapsed / revoked 48Other 182Dot size: filed unitsN

Filed coordinates, straight-line distance. 312 registered projects within 2 km.

Builder: Bhgyashri Vasant Bhide

Bhgyashri Vasant Bhide has 2 registrations on MahaRERA, including INDIRA LANDMARK and Indira Landmark Phase 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Indira Landmark Phase 2 is delayed beyond 30 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Indira Landmark Phase 2?

The registered promoter entity is Bhgyashri Vasant Bhide, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Indira Landmark Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Indira Landmark Phase 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Indira Landmark Phase 2?

The professionals named in the filing: Architect: Kanhekar Prakash; Engineer: Saummitra Joag; Chartered Accountant: neeren Randive & Associates; Chartered Accountant: Neeren Ravidra Ranadive. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Indira Landmark Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Indira Landmark Phase 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Indira Landmark Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.