Registration lapsed No litigation declared Others project

IMPERIAL HEIGHTS S1 S2

By KAMRAN LIVESTOCK & REAL ESTATE PVT LTD

RG-MH-12402 · RERA P51700001164 · Last updated on MahaRERA portal: 27 Jun 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 52 months past the filed date
  • 10 complaints at MahaRERA
  • Completion date moved by 30 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2022Possession promised52 months past this date
22 of 22Construction stages doneacross 2 buildings; every applicable stage filed complete
10Complaints at MahaRERAon this registration
Jump to the 173 documents Report an error

IMPERIAL HEIGHTS S1 S2 is a Others project by KAMRAN LIVESTOCK & REAL ESTATE PVT LTD in Thane, Maharashtra, registered with MahaRERA as P51700001164 on 26 Jul 2017. Possession was promised by 30 Jun 2022 and is now 52 months past that date. The completion date has moved by 30 months from the original filing. 10 complaints are on record with the regulator.

At a glance

Project

  • NameIMPERIAL HEIGHTS S1 S2
  • TypeOthers
  • Location
    • Khartan Road
    • Chendani
    • Thane (M Corp.)
    • Thane
    • 400601
  • Pincode400601
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700001164
  • ReraGenie IDRG-MH-12402

Builder

  • NameKAMRAN LIVESTOCK & REAL ESTATE PVT LTD
  • Entity typeCompany
  • Managing DirectorMUSTAK SAIFAN SHAIKH
  • ChairpersonNAJMA MUSTAK SHAIKH
  • Declared earlier projects2 →

Key dates

52 months past promisethis monthRegisteredJul 2017First promiseDec 2019Revised toJun 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on26 Jul 2017
  • Promised completion30 Jun 2022
  • Revised completionRevised to 30 Jun 2022 (originally 31 Dec 2019)
  • Buildings2 building records
  • Documents filed173 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
IMPERIAL HEIGHTS BUILDING NO S1NA190000
IMPERIAL HEIGHTS BUILDING NO S2NA240000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 27 Jun 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 22 construction stages are filed complete across 2 buildings.

IMPERIAL HEIGHTS BUILDING NO S1100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
IMPERIAL HEIGHTS BUILDING NO S2100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 27 Jun 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes10%
Open ParkingYes50%
Club house and GymnasiumYes100%

Parking filed6

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots6
Closed/Covered2
Open Space4
BuildingClosed/CoveredOpen SpaceTotal
IMPERIAL HEIGHTS BUILDING NO S1112
IMPERIAL HEIGHTS BUILDING NO S2134

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,233 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI29415.82
Proposed, not sanctioned25,896 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNANDANVAN INDUSTRIAL ESTATE GROUND FLOOR GALA NO AB/B2 IBS MARG ETERNITY MALL THANE 400 604

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNEXTSTEP CONSTRUCTION PRIVATE LIMITED NILESH D SAWANT
EngineerAJAY MAHALE
PartnerRole in project
KAMRAN LIVESTOCK & REAL ESTATE PVT LTD-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700011403Dec 2019 → Jun 2022

Reason as filed by the promoterProject work is completed and our Architect shall be filing application for completion certificate and occupancy certificate in due course. Kindly grant us extension till 30th June 2022. The necessary consent from allottee as per circular is annexed herewith.

EXT51700003921Dec 2019 → Dec 2020

Reason as filed by the promoterBuilding No. S1 is completed.We need extension for Building No. S2 since delayed Fire NOC dated 16th July 2018 and Commencement Certificate dated 21st September 2018

Complaints filed with MahaRERA10

Case no.ComplainantRespondentFiled
CC006000000022815AJIT KESHAV BAPARDEKARKAMRAN LIVE STOCK & REAL ESTATE PVT LTD23/04/2018
CC006000000023176santosh sakharam kalekamran live stock & real estate pvt.ltd01/02/2018
CC006000000056585Vijaya PatilM/s Kamran Livestock and real estate pvt.ltd22/10/2018
CC006000000057001Mr. Rajaram V. Joshi and Mrs. Sunanda R. JoshiKAMRAN LIVESTOCK & REAL ESTATE PVT. LTD.27/11/2018
CC006000000057002MR. RAJAN A. THAKUR & MRS. SEEMA R. THAKURKAMRAN LIVESTOCK & REAL ESTATE PVT. LTD.27/11/2018
CC006000000396200Rajeev Kashinath PaiMushtaq Sheikh20/06/2023
CC006000000194948MEHUL D NAIKM/S KAMRAN LIVE STOCKS & REAL ESTATE PVT LTD19/11/2020
CC006000000292581Eknath ShirkeKamran Livestock & Real Estate Pvt. Ltd.08/09/2022
CC006000000374842Digambar Gajanan RaneM/s. Kamran Livestock & Real Estate Pvt Ltd.18/03/2023
CC006000000374979Digambar Gajanan RaneM/s. Kamran Livestock & Real Estate Pvt. Ltd28/04/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Nov 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 9 Jun 2023

Documents filed173

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 173 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of ConveyanceFile: conveyamnce kamran.pdf27 Jun 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Formation.pdf23 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: full oc kamran.pdf9 Jun 2023
Building plan approvalFile: scan _compressed (1).pdf2 Jun 2023
Building plan approvalFile: scan 002_compressed.pdf2 Jun 2023
Building plan approvalFile: scan 003_compressed.pdf2 Jun 2023
Building plan approvalFile: scan 004_compressed.pdf2 Jun 2023
Building plan approvalFile: scan 005_compressed.pdf2 Jun 2023
Building plan approvalFile: scan 006_compressed.pdf2 Jun 2023
Building plan approvalFile: scan 007_compressed.pdf2 Jun 2023
Building Plan Approval (IOD)File: scan _compressed (1).pdf2 Jun 2023
Building Plan Approval (IOD)File: scan 002_compressed.pdf2 Jun 2023
Building Plan Approval (IOD)File: scan 003_compressed.pdf2 Jun 2023
Building Plan Approval (IOD)File: scan 004_compressed.pdf2 Jun 2023
Building Plan Approval (IOD)File: scan 005_compressed.pdf2 Jun 2023
Building Plan Approval (IOD)File: scan 006_compressed.pdf2 Jun 2023
Building Plan Approval (IOD)File: scan 007_compressed.pdf2 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 latest.pdf18 May 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Kamran Declaration for OC.pdf18 May 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Form 1 latest.pdf18 May 2023
Details of encumbrances concerned to FinanceFile: Declaration of No Emcumbrances - Legal.pdf17 Feb 2023
Details of encumbrances concerned to LegalFile: Declaration of No Emcumbrances - Legal.pdf17 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Separate Bank Account for Real Estate Projects.pdf17 Feb 2023
Deviation Report with respect to Allotment letterFile: No Deviation Report for Allotment Letter.pdf17 Feb 2023
Deviation Report with respect to model copy of AgreementFile: No Deviation Report for Agreement for Sale.pdf17 Feb 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate S1 S2.pdf16 Feb 2023
Proforma of Agreement for saleFile: AFS.pdf14 Jan 2023
Building plan approvalFile: MYSCAN_20220604_0002.PDF5 Jun 2022
Building plan approvalFile: MYSCAN_20220604_0004.PDF5 Jun 2022
Building plan approvalFile: MYSCAN_20220604_0005.PDF5 Jun 2022
Building plan approvalFile: MYSCAN_20220604_0007.PDF5 Jun 2022
Building plan approvalFile: MYSCAN_20220604_0008.PDF5 Jun 2022
Building plan approvalFile: MYSCAN_20220604_0009.PDF5 Jun 2022
Building plan approvalFile: MYSCAN_20220604_0010.PDF5 Jun 2022
Building plan approvalFile: MYSCAN_20220604_0011.PDF5 Jun 2022
Building plan approvalFile: MYSCAN_20220604_0012.PDF5 Jun 2022
Building plan approvalFile: MYSCAN_20220604_0012.PDF5 Jun 2022
Building plan approvalFile: MYSCAN_20220604_0014.PDF5 Jun 2022
Building plan approvalFile: MYSCAN_20220604_0015.PDF5 Jun 2022
Building plan approvalFile: MYSCAN_20220604_0016.PDF5 Jun 2022
Building Plan Approval (IOD)File: MYSCAN_20220604_0002.PDF5 Jun 2022
Building Plan Approval (IOD)File: MYSCAN_20220604_0004.PDF5 Jun 2022
Building Plan Approval (IOD)File: MYSCAN_20220604_0005.PDF5 Jun 2022
Building Plan Approval (IOD)File: MYSCAN_20220604_0007.PDF5 Jun 2022
Building Plan Approval (IOD)File: MYSCAN_20220604_0008.PDF5 Jun 2022
Building Plan Approval (IOD)File: MYSCAN_20220604_0009.PDF5 Jun 2022
Building Plan Approval (IOD)File: MYSCAN_20220604_0010.PDF5 Jun 2022
Building Plan Approval (IOD)File: MYSCAN_20220604_0011.PDF5 Jun 2022
Building Plan Approval (IOD)File: MYSCAN_20220604_0012.PDF5 Jun 2022
Building Plan Approval (IOD)File: MYSCAN_20220604_0012.PDF5 Jun 2022
Building Plan Approval (IOD)File: MYSCAN_20220604_0014.PDF5 Jun 2022
Building Plan Approval (IOD)File: MYSCAN_20220604_0015.PDF5 Jun 2022
Building Plan Approval (IOD)File: MYSCAN_20220604_0016.PDF5 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Kamran 2A 19-20.pdf4 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: KAMRAN 2A 20-21.pdf4 Feb 2022
CERSAI detailsFile: KAMRAN CERSAI.pdf21 Dec 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Kamran Society Formation.pdf21 Dec 2021
Status of ConveyanceFile: Kamran Conveyance.pdf21 Dec 2021
Declaration about Commencement CertificateFile: CC Declaration Kamran.pdf8 Nov 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_compressed.pdf8 Nov 2021
Disclosure of sold/ booked inventoryFile: Kamran Sold unsold_compressed.pdf8 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5-KLRPL-2019-20.pdf2 Nov 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: KAMRANS1S2_FORM 5_2018-19_Scan.pdf8 Nov 2019
OtherFile: LOI1.pdf21 Jan 2019
OtherFile: LOI2.pdf21 Jan 2019
OtherFile: LOI3.pdf21 Jan 2019
Commencement Certificates / NA Order for plotted developmentFile: KamranCC.pdf1 Nov 2018
Certificates of CA (Form 5)File: Kamran Live Stock.pdf29 Sep 2018
OtherFile: Environment clearance.pdf11 Jun 2018
OtherFile: court order.pdf3 May 2018
OtherFile: meeting agenda.pdf3 May 2018
Building plan approvalFile: S1.pdf21 Jul 2017
Building plan approvalFile: S2.pdf21 Jul 2017
Layout approvalFile: Layout.pdf21 Jul 2017
Building plan approvalFile: Kamran.pdf21 Jul 2017
PAN CardFile: KAMRAN.pdf21 Jul 2017
Copy of the legal title reportFile: 01.pdf21 Jul 2017
Copy of the legal title reportFile: 02.pdf21 Jul 2017
Copy of the legal title reportFile: 03.pdf21 Jul 2017
Details of encumbrancesFile: Kamran.pdf21 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
IMPERIAL HEIGHTS BUILDING NO S3OPP D K STADIUM CREEK ROAD CHENDANI THANE WEST 400 60153CompletedJun 2012Late, Dec 2012
OM SHREE SWAMI SAMARTH CHS LTDOPP D K STADIUM CREEK ROAD CHENDANI THANE WEST 400 601315CompletedDec 2011Late, Oct 2012

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 30 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep IMPERIAL HEIGHTS S1 S2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chendani7,600+ in Thane

2 kmIMPERIAL HEIGHTS S1 S2Completed 97Lapsed / revoked 63Other 127Dot size: filed unitsN

Filed coordinates, straight-line distance. 287 registered projects within 2 km.

Builder: KAMRAN LIVESTOCK & REAL ESTATE PVT LTD

KAMRAN LIVESTOCK & REAL ESTATE PVT LTD has 1 registration on MahaRERA, including IMPERIAL HEIGHTS S1 S2. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that IMPERIAL HEIGHTS S1 S2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if IMPERIAL HEIGHTS S1 S2 is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of IMPERIAL HEIGHTS S1 S2?

The registered promoter entity is KAMRAN LIVESTOCK & REAL ESTATE PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in IMPERIAL HEIGHTS S1 S2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against IMPERIAL HEIGHTS S1 S2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for IMPERIAL HEIGHTS S1 S2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at IMPERIAL HEIGHTS S1 S2?

The professionals named in the filing: Architect: NEXTSTEP CONSTRUCTION PRIVATE LIMITED NILESH D SAWANT; Engineer: AJAY MAHALE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in IMPERIAL HEIGHTS S1 S2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About IMPERIAL HEIGHTS S1 S2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save IMPERIAL HEIGHTS S1 S2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.