ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Hubtown Sunmist A 6th to Above Floor

Completed No litigation declared Residential / Group Housing project

Hubtown Sunmist A 6th to Above Floor

By Hubtown Limited

RG-MH-11579 · RERA P51800001202 · Last updated on MahaRERA portal: 17 Nov 2021

Source: official MahaRERA filing

Red flags

  • 8 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2019Possession promisedregistration recorded completed
8 of 11Construction stages donefurthest along: Installation of Lifts, 93%
8Complaints at MahaRERAon this registration
Jump to the 23 documents Report an error

Hubtown Sunmist A 6th to Above Floor is a Residential / Group Housing project by Hubtown Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800001202 on 27 Jul 2017. The registration is recorded completed; possession was promised by 31 Dec 2019. 8 complaints are on record with the regulator.

At a glance

Project

  • NameHubtown Sunmist A 6th to Above Floor
  • TypeResidential / Group Housing
  • Location
    • Off. Teli Gali
    • On Andheri Juhu Link Road
    • Opp.Hubtown Solaris
    • Andheri East
    • Andheri
    • Mumbai Suburban
    • 400069
  • Pincode400069
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800001202
  • ReraGenie IDRG-MH-11579

Builder

  • NameHubtown Limited
  • Entity typeCompany
  • DirectorHemant Shah
  • Other registrations19 more →
  • Completed11 of 20
  • No longer live3 lapsed, de-registered or revoked
  • Past their filed date2
  • Declared earlier projects2 →

Key dates

this monthRegisteredJul 2017PromisedDec 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on27 Jul 2017
  • Promised completion31 Dec 2019
  • Revised completionNone
  • Buildings1 building record
  • Documents filed23 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Hubtown Sunmist A 6th to Above FloorNA150000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Nov 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 93%.

Hubtown Sunmist A 6th to Above Floor: 81% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.93%

Progress on shared amenities15

As on 17 Nov 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes50%
Street LightingYes95%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed123

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots123
Closed/Covered123

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,149 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6301.0
Proposed, not sanctioned6,301 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMIDC Andheri E Mumbai

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCity gold Management Services (Maya Vaidya)
EngineerRajeevan Paramban
Chartered AccountantMH Dalal & Association
Chartered AccountantKMVR & Company
PartnerRole in project
Hubtown Limited-

Litigation declared1

CaseCourtStatus
Suit No 56 of 2016/2016Bombay High CourtPending

Complaints filed with MahaRERA8

Case no.ComplainantRespondentFiled
CC006000000023060Harshad BhanushaliHubtown Limited25/01/2018
CC006000000023562Vijay S SaokarHubtown Limited19/03/2018
CC006000000023766Samir KadamHubtown Limited17/03/2018
CC006000000055636RAJ BRIJMOHAN PODDARHubtown Limited03/08/2018
CC006000000055638RAJ BRIJMOHAN PODDARHubtown Limited03/08/2018
CC006000000055682MRS. PRISCILLA RODRIGUESM/S. HUBTOWN LIMITED17/09/2018
CC006000000198299Uday Kashinath PatilHubtown Limited09/09/2021
CC006000000344195Hubtown LimitedUday Kashinath Patil02/02/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 17 Nov 2021

Documents filed23

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Full OC 06092018.pdf17 Nov 2021
Certificates of CA (Form 3)File: Sunmist.pdf7 Jan 2019
Certificates of CA (Form 5)File: Sunmist RERA.pdf7 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Form I (Final).pdf11 Sep 2018
Certificates of Architect (Form 4)File: Arch Cert Form IV.pdf11 Sep 2018
OtherFile: Full OC 06092018.pdf11 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form I.pdf21 Jun 2018
OtherFile: Sunmist part OCC 19062018.pdf21 Jun 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Sunmist A wing.pdf26 Mar 2018
OtherFile: Agreement.pdf6 Nov 2017
Details of encumbrancesFile: Encumbrance sunmist-A Wing 6 th floor.pdf21 Jul 2017
Building plan approvalFile: IOD Sunmist.pdf20 Jul 2017
Copy of the legal title reportFile: Title Report Sunmist.pdf20 Jul 2017
Building Plan Approval (IOD)File: IOD Sunmist.pdf20 Jul 2017
Declaration in FORM BFile: Form B Sunmist A wing above 6th floor.pdf20 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate Sunmist.pdf20 Jul 2017
Certificates of CA (Form 3)File: CA Certificate Sunmist.pdf20 Jul 2017
Proforma of Allotment letterFile: Allotment and Agreement Sunmist A wing above 6th floor.pdf20 Jul 2017
Layout approvalFile: Layout Sunmist.pdf18 Jul 2017
PAN CardFile: PAN Card Hubtown.pdf18 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Sunmist.pdf18 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC Sunmist.pdf18 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf18 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Hubtown Sunmist B wingAndheri East61CompletedDec 2012Late, Sep 2014

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Hubtown Sunmist A 6th to Above Floor on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near On Andheri Juhu Link Road, Opp.Hubtown Solaris, Andheri East6,700+ in Mumbai Suburban

2 kmHubtown Sunmist A 6th toCompleted 144Lapsed / revoked 79Other 168Dot size: filed unitsN

Filed coordinates, straight-line distance. 391 registered projects within 2 km.

Builder: Hubtown Limited

Hubtown Limited has 20 registrations on MahaRERA, including Hubtown Greenwoods A wing and Hubtown Greenwoods D Wing. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Hubtown Sunmist A 6th to Above Floor is delayed beyond 31 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Hubtown Sunmist A 6th to Above Floor?

The registered promoter entity is Hubtown Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Hubtown Sunmist A 6th to Above Floor?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Hubtown Sunmist A 6th to Above Floor?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Hubtown Sunmist A 6th to Above Floor?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Hubtown Sunmist A 6th to Above Floor?

The professionals named in the filing: Architect: City gold Management Services (Maya Vaidya); Engineer: Rajeevan Paramban; Chartered Accountant: MH Dalal & Association; Chartered Accountant: KMVR & Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Hubtown Sunmist A 6th to Above Floor?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Hubtown Sunmist A 6th to Above Floor. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Hubtown Sunmist A 6th to Above Floor to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.