Red flags
- Registration lapsed
- Possession 22 months past the filed date
- 1 complaint at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Hubtown Harmony A Wing is a Residential / Group Housing project by Heet Builders Private Limited in Mumbai City, Maharashtra, registered with MahaRERA as P51900017558 on 28 Aug 2018. Possession was promised by 30 Dec 2024 and is now 22 months past that date. 1 complaint is on record with the regulator.
At a glance
Project
- NameHubtown Harmony A Wing
- TypeResidential / Group Housing
- Location
- Bhaudaji Marg
- Matunga East
- Mumbai City
- 400019
- Pincode400019
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900017558
- ReraGenie IDRG-MH-81817
Builder
- NameHeet Builders Private Limited
- Entity typeCompany
- DirectorSunil Chandrakant Shah
- Other registrations3 more →
- Completed1 of 4
- No longer live3 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on28 Aug 2018
- Promised completion30 Dec 2024
- Revised completionNone
- Buildings1 building record
- Documents filed93 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Hubtown Harmony A Wing | NA | 18 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 20 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
Hubtown Harmony A Wing: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities16
As on 20 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
| Gym | Yes | 0% |
Parking filed99
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Naren Kuwadekar & Associates |
| Architect | S.D. Arch |
| Engineer | Rajivan Paramban |
| Partner | Role in project |
|---|---|
| Heet Builders Private Limited | - |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000396625 | HEET BUILDERS PRIVATE LIMITED | Mrs. Bhharati Kondaji Kanade | 08/07/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Aug 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Nov 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 23 Aug 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 Aug 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 10 Oct 2024
Documents filed93
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 93 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Harmony Wing A (2).pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate - Harmony - Sep 24 - A wing.pdf | 8 Nov 2024 |
| Certificates of CA (Form 3)File: Form III_HARMONY - A wing.pdf | 6 Nov 2024 |
| Certificates of CA (Form 3)File: Form III_HARMONY - A WING_Sep 24.pdf | 6 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate A wing jun 24.pdf | 6 Nov 2024 |
| Layout approvalFile: BIT SITE LAYOUT _ IOA DATED 29-07-2020.pdf | 5 Nov 2024 |
| Copy of Layout Approval (in case of layout)File: BIT SITE LAYOUT _ IOA DATED 29-07-2020.pdf | 5 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Harmony Wing A.pdf | 5 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Harmony Wing A.pdf | 4 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: P51900017558 - Harmony - Wing -A.pdf | 22 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: HARMONY A WING.pdf | 17 Oct 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - Wing A Hubtown Harmony.pdf | 10 Oct 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 01-HARMONY FULL OC WING A AND PART OC WING B 12TH-AUG-2024 LETTER.pdf | 10 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: P51900017588 - Harmony - Wing -A ( Bit Sale building).pdf | 15 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QA Certificate_Harmony A wing_FY 23-24.pdf | 8 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form III_Mar 24_HARMONY - A WING.pdf | 20 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: HEET BUILDERS CERTIFICATE A wing.pdf | 20 Apr 2024 |
| Certificates of CA (Form 3)File: Form III_Mar 24_HARMONY - A WING.pdf | 20 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: P51900017558 - BIT -A WING.pdf | 15 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5-Harmony A wing_22-23.pdf | 4 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate - A wing - Harmony - Dec 23.pdf | 22 Jan 2024 |
| Certificates of CA (Form 3)File: Form III_HARMONY A WING.pdf | 22 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: P51900017558 - BIT -A WING (1).pdf | 17 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate - Wing A - Sep 23 (1).pdf | 26 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: harmony A wing Form 2A.pdf | 23 Nov 2023 |
| Certificates of CA (Form 3)File: Form III_HARMONY -A WING_Sep 23.pdf | 23 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: P51900017558 - BIT -A WING.pdf | 16 Oct 2023 |
| Building plan approvalFile: BIT SALE BLDG DRAWING-29-07-2020-1.pdf | 23 Aug 2023 |
| Building plan approvalFile: BIT SALE BLDG DRAWING-29-07-2020-2.pdf | 23 Aug 2023 |
| Building plan approvalFile: BIT SALE BLDG DRAWING-29-07-2020-3.pdf | 23 Aug 2023 |
| Building plan approvalFile: BIT SALE BLDG DRAWING-29-07-2020-4.pdf | 23 Aug 2023 |
| Building plan approvalFile: BIT SALE BLDG DRAWING-29-07-2020-5.pdf | 23 Aug 2023 |
| Building plan approvalFile: BIT SALE BLDG DRAWING-29-07-2020-6.pdf | 23 Aug 2023 |
| Building plan approvalFile: BIT SALE BLDG DRAWING-29-07-2020-7.pdf | 23 Aug 2023 |
| Building plan approvalFile: BIT SALE BLDG DRAWING-29-07-2020-8.pdf | 23 Aug 2023 |
| Building Plan Approval (IOD)File: BIT SALE BLDG DRAWING-29-07-2020-1.pdf | 23 Aug 2023 |
| Building Plan Approval (IOD)File: BIT SALE BLDG DRAWING-29-07-2020-2.pdf | 23 Aug 2023 |
| Building Plan Approval (IOD)File: BIT SALE BLDG DRAWING-29-07-2020-3.pdf | 23 Aug 2023 |
| Building Plan Approval (IOD)File: BIT SALE BLDG DRAWING-29-07-2020-4.pdf | 23 Aug 2023 |
| Building Plan Approval (IOD)File: BIT SALE BLDG DRAWING-29-07-2020-5.pdf | 23 Aug 2023 |
| Building Plan Approval (IOD)File: BIT SALE BLDG DRAWING-29-07-2020-6.pdf | 23 Aug 2023 |
| Building Plan Approval (IOD)File: BIT SALE BLDG DRAWING-29-07-2020-7.pdf | 23 Aug 2023 |
| Building Plan Approval (IOD)File: BIT SALE BLDG DRAWING-29-07-2020-8.pdf | 23 Aug 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: 08-CC revalidation 06-01-2024.pdf | 23 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Harmony A wing - June 23.pdf | 14 Aug 2023 |
| Certificates of CA (Form 3)File: FORM III A WING.pdf | 14 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERING CERTIFICATE - A wing - March 23 (1).pdf | 19 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: P51900017558 - BIT -A WING.pdf | 12 Jul 2023 |
| Certificates of CA (Form 3)File: Form III_Harmony A WIING March 23.pdf | 12 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: P51900017558 - BIT -A WING.pdf | 10 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 A WING_Harmony.pdf | 21 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate_Harmony A Wing_Dec 22.pdf | 9 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enginners Certificate Wing A Dec 22 - Harmony.pdf | 9 Jan 2023 |
| Certificates of CA (Form 3)File: FORM III - HARMONY A WING_Dec 22.pdf | 9 Jan 2023 |
| Certificates of CA (Form 3)File: FORM III - HARMONY A WING_Sept 22.pdf | 4 Jan 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 01-HARMONY PART OC FOR WING A AND WING B FOR SHOP LETTER-14TH-NOV-2022.pdf | 14 Nov 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate - harmony A wing - june 22_compressed.pdf | 2 Sep 2022 |
| Certificates of CA (Form 3)File: Harmony A wing CA Form 3_June 22_compressed.pdf | 30 Aug 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate_Harmony A wing_June 22.pdf | 12 Jul 2022 |
| Declaration about Commencement CertificateFile: RERA Form D Harmony A Wing.pdf | 15 Jun 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate - A wing_compressed.pdf | 15 Jun 2022 |
| Certificates of CA (Form 3)File: HARMONY_FORM-III (A WING)_compressed-compressed.pdf | 14 Jun 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate_Harmony A wing_Mar 22.pdf | 15 Apr 2022 |
| Certificates of CA (Form 3)File: Harmony A Wing_Form III_Dec 21_compressed.pdf | 8 Jan 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Heet Mar 21 - Harmony A Wing.pdf | 2 Dec 2021 |
| Certificates of CA (Form 3)File: Form_III_HARMONY A Wing_March 21_compressed.pdf | 16 Aug 2021 |
| Certificates of CA (Form 3)File: Harmony A _Form III_June 21_compressed.pdf | 16 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 02 BIT Harmony architect certificate-Phase II-31122020 Vishal 010221.pdf | 2 Feb 2021 |
| Details of encumbrancesFile: Heet Encumbrance Certificate 09012021.pdf | 11 Jan 2021 |
| Certificates of CA (Form 3)File: Heet Builders Form III March 20 Harmony A Wing Part1.pdf | 8 Jan 2021 |
| Certificates of CA (Form 3)File: Heet Builders Form III March 20 Harmony A Wing Part2.pdf | 8 Jan 2021 |
| Certificates of CA (Form 3)File: Heet Builders Form III March 20 Harmony A Wing Part3.pdf | 8 Jan 2021 |
| Certificates of CA (Form 3)File: Heet Builders Form III March 20 Harmony A Wing Part4.pdf | 8 Jan 2021 |
| Certificates of CA (Form 3)File: Heet Builders Form III March 20 Harmony A Wing Part5.pdf | 8 Jan 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Harmony A Wing Form 5 Mar 20.pdf | 8 Jan 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BIT HARMONY PHASE II WING A 31 MARCH 2020.pdf | 30 Nov 2020 |
| Details of Restarting of Construction work post lockdownFile: HarmonyA.pdf | 31 Oct 2020 |
| Building plan approvalFile: Approval Letter 29072020.pdf | 16 Sep 2020 |
| Building Plan Approval (IOD)File: Approval Letter 29072020.pdf | 16 Sep 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: FCC 30JUL2020.pdf | 16 Sep 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai City
Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 93 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Hubtown Harmony A Wing on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Matunga East780+ in Mumbai City
Filed coordinates, straight-line distance. 212 registered projects within 2 km.
CODENAME MATUNGA ORIGINS
J. P. INFRA (MUMBAI) PRIVATE LIMITED
SHANTI HEIGHTS
Vipul Shantilal Nagda HUF
Balkrishna Hills
Oriental Contractors Private Limited
VERVE MANSION
SHANTI SIDDHI INFRA LLP
PRINCECARE AMARAA
PRINCECARE AMARAA LLP
Godrej Five Gardens
Godrej Projects Development Ltd.
See every Mumbai City project, with the district possession charts
Builder: Heet Builders Private Limited
Heet Builders Private Limited has 4 registrations on MahaRERA, including Heavan C Wing and Hubtown Harmony A Wing. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.
Frequently asked questions
What does it mean that Hubtown Harmony A Wing shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Hubtown Harmony A Wing is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Hubtown Harmony A Wing?
The registered promoter entity is Heet Builders Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Hubtown Harmony A Wing?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Hubtown Harmony A Wing?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Hubtown Harmony A Wing?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Hubtown Harmony A Wing?
The professionals named in the filing: Architect: Naren Kuwadekar & Associates; Architect: S.D. Arch; Engineer: Rajivan Paramban. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Hubtown Harmony A Wing?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback