Home / Browse projects / Sindhudurg, Maharashtra / Horizon Grande Wing 02
Horizon Grande Wing 02
By Metric Homes Private Limited
RG-MH-53861 · RERA P52900048513 · Last updated on MahaRERA portal: 14 Apr 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 2 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Sindhudurg registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Horizon Grande Wing 02 is a Residential / Group Housing project by Metric Homes Private Limited in Sindhudurg, Maharashtra, registered with MahaRERA as P52900048513 on 3 Jan 2023. Possession was promised by 31 Dec 2025 and is now 10 months past that date.
At a glance
Project
- NameHorizon Grande Wing 02
- TypeResidential / Group Housing
- Location
- Waradkarwadi
- Near post Office wayari
- Wayari
- Malwan
- Sindhudurg
- 416606
- Pincode416606
- RERA no.P52900048513
- ReraGenie IDRG-MH-53861
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on3 Jan 2023
- Promised completion31 Dec 2025
- Revised completionNone
- Buildings1 building record
- Documents filed118 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Horizon Grande Wing 02 | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 14 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 0%.
Horizon Grande Wing 02: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 14 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 60% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed50
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Mr Siddhesh Pramod Hendre | Mumbai City | Mumbai City |
| Mrs Reshma Siddhesh Hendre | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Alternate Angle Architects Pvt Ltd |
| Engineer | Er Rajendra Suresh Vankudre |
| Chartered Accountant | Depen Kapadia |
| Partner | Role in project |
|---|---|
| Metric Homes Private Limited | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Nov 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Nov 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Nov 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 18 Oct 2024
Documents filed118
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 118 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Wing 02 Completion Arch cert.pdf | 14 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Arch cert wing 02 completion certifcate.pdf | 14 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Wing 02 Completion Arch cert.pdf | 14 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Wing 02 Completion Arch cert.pdf | 14 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Arch cert wing 02 completion certifcate.pdf | 14 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch cert wing 02 completion certifcate.pdf | 12 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Arch cert wing 02 completion certifcate.pdf | 12 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Arch cert wing 02 completion certifcate.pdf | 12 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Arch cert wing 02 completion certifcate.pdf | 12 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Wing 02 Completion Arch cert.pdf | 18 Oct 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Wing 02 Completion Arch cert.pdf | 18 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Wing 02 Completion Arch cert.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Wing 02 Completion Arch cert.pdf | 18 Oct 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Wing 02 Completion Arch cert.pdf | 18 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Wing 02 Completion Arch cert.pdf | 18 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Wing 02 Completion Arch cert.pdf | 18 Oct 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Wing 02 Completion Arch cert.pdf | 16 Oct 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Wing 02 Completion Arch cert.pdf | 16 Oct 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Wing 02 OC Copy.pdf | 16 Oct 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Wing 02 OC Copy.pdf | 16 Oct 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Wing 02 Completion Arch cert.pdf | 15 Oct 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Arch Cert.pdf | 14 Oct 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: AD.pdf | 14 Oct 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Copy.pdf | 14 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Wing 02 Inventory.pdf | 18 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng 02 letter.pdf | 17 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch cert wing 02.pdf | 16 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Cert 02.pdf | 16 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH APR 2024.pdf | 15 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG CERT APR 24.pdf | 15 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ENG QUALITY WING 02.pdf | 15 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERT APR 2024.pdf | 15 Apr 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: FRE (1)_11zon.pdf | 15 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD WING 02 APR 24.pdf | 12 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH WING 02.pdf | 10 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER WING 02.pdf | 10 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: WING 02 SOLD UNSOLD.pdf | 10 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA WING 02.pdf | 10 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JAN WING 02 ARCH CERT.pdf | 20 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERT WING 02 AMJ 2023_compressed.pdf | 20 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JAS ARCH CERT 2023 WING 02.pdf | 20 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Wing 02 Engineer Cert 10th April 2023.pdf | 20 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Wing 02 Engineer Cert 10th July 2023.pdf | 20 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: JAS ENG CERT 2023 WING 02.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Wing 02 self declaration 10th April 23.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: wing 02 self declaration 10th July 23.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JAS CA CERT 2023 WING 02.pdf | 20 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERT WING 02 AMJ 2023_compressed.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Wing 02.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Wing 02.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Wing 02.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Wing 02.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Wing 02.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Wing 02.pdf | 19 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1).pdf | 18 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Wing 02 Engineer Cert 10th April 2023.pdf | 18 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Wing 02 Engineer Cert 10th July 2023.pdf | 18 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assuance Wing 02.pdf | 18 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assuance Wing 02.pdf | 18 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assuance Wing 02.pdf | 18 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: wing 02 self declaration 10th April 23.pdf | 18 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: wing 02 self declaration 10th july 23.pdf | 18 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH WING 02.pdf | 11 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert wing 02 PDF.pdf | 11 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance wing 02 PDF.pdf | 11 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Wing 02 sold N unsold.pdf | 11 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Wing 02 self declaration.pdf | 11 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer’s Certificate 02.pdf | 22 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer’s Certificate 02.pdf | 22 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate - 02.pdf | 22 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate - 02.pdf | 22 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect - Wing 02.pdf | 24 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Wing 02.pdf | 24 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Wing-02 -Malvan Project.pdf | 21 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: Wing 2 Malvan Sold unsold.pdf | 6 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Final_11zon (3).pdf | 22 Dec 2022 |
| Layout approvalFile: Layout.pdf | 26 Nov 2022 |
| Building plan approvalFile: Plan 1_compressed.pdf | 26 Nov 2022 |
| Building plan approvalFile: Plan 2_compressed (1).pdf | 26 Nov 2022 |
| Building plan approvalFile: Plan 3_compressed.pdf | 26 Nov 2022 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Horizon Grande Wing 02p52900048513 | Survey No.29 Hissa No.5/1-5/29,5/31,5/32, Waradkarwadi, Near post Office wayari, Wayari, Malwan, Sindhudurg, 416606, MAHARASHTRA | Completed | Dec 2025 | Oct 2024 |
| Horizon Grande Wing 01p52900048514 | Survey No.29 Hissa No.5/1-5/29,5/31,5/32, Waradkarwadi, Near Post Office Wayari, Wayari, Malwan, Sindhudurg, 416606, MAHARASHTRA | Completed | Dec 2024 | Oct 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sindhudurg
Computed across the 530+ Sindhudurg projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 118 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Horizon Grande Wing 02 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Near post Office wayari530+ in Sindhudurg
ATHANG SAI HOMES on S No 32/8/2 and 34/1B of V
Chandrashekhar Suryakant Morvekar
Siddhivinayak Residency
Vastu Builder & Land Developer
SEA MERIDIAN
SKY INFRASTRUCTURE
ATHANG LAXMI
Chandrashekhar Suryakant Morvekar
SEA PEARL
HIRAYA CONSTRUCTIONS LLP
AYAANS AMBARY
Suman Developers
See every Sindhudurg project, with the district possession charts
Builder: Metric Homes Private Limited
Metric Homes Private Limited has 3 registrations on MahaRERA, including Horizon Grande Wing K and Horizon Grande Wing 02. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Sindhudurg district page.
Frequently asked questions
What does it mean that Horizon Grande Wing 02 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Horizon Grande Wing 02 is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Horizon Grande Wing 02?
The registered promoter entity is Metric Homes Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Horizon Grande Wing 02?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Horizon Grande Wing 02?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Horizon Grande Wing 02?
The professionals named in the filing: Architect: Alternate Angle Architects Pvt Ltd; Engineer: Er Rajendra Suresh Vankudre; Chartered Accountant: Depen Kapadia. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Horizon Grande Wing 02?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback