ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Homedale

Completed No litigation declared Residential / Group Housing project

Homedale

By M/s. Om Shiv Sai Promoters & Developers

RG-MH-37197 · RERA P52100016481 · Last updated on MahaRERA portal: 24 Jul 2024

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedregistration recorded completed
22 of 22Construction stages doneacross 2 buildings; every applicable stage filed complete
1Complaints at MahaRERAon this registration
Jump to the 48 documents Report an error

Homedale is a Residential / Group Housing project by M/s. Om Shiv Sai Promoters & Developers in Pune, Maharashtra, registered with MahaRERA as P52100016481 on 18 May 2018. The registration is recorded completed; possession was promised by 30 Dec 2026. 1 complaint is on record with the regulator.

At a glance

Project

  • NameHomedale
  • TypeResidential / Group Housing
  • Location
    • DIAT Road
    • Khadakwasla Bypass Road
    • Khadakwasala
    • Haveli
    • Pune
    • 411041
  • Pincode411041
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100016481
  • ReraGenie IDRG-MH-37197

Builder

  • NameM/s. Om Shiv Sai Promoters & Developers
  • Entity typePartnership
  • PartnersPravin Shevkar, Jankiram Kanade, Vinod Badhe
  • Other registrations2 more →
  • Completed2 of 3
  • Declared earlier projects1 →

Key dates

this monthRegisteredMay 2018PromisedDec 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on18 May 2018
  • Promised completion30 Dec 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed48 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building ANA140000
Building BNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 24 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 22 construction stages are filed complete across 2 buildings.

Building A100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building B100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 24 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed99

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots99
Closed/Covered99
BuildingClosed/CoveredTotal
Building A4848
Building B5151

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,983 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
Miracle AssociatesPune (M Corp.)Pune
Kaluram Mate & othersPune (M Corp.)Pune
Shri Swami Samartha Co operative SocietyKhadakwasalaPune

Approvals and building plan

Permissible FSI11644.89
Proposed, not sanctioned11,645 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFergusson College Road Branch, Near Lalit Mahal

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCrystal Arch
EngineerStructure Vision
Chartered AccountantTANAJI CHORGE
PartnerRole in project
M/s. Om Shiv Sai Promoters & Developers-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000238722Shivaji TalekarOM SHIVSAI PROMOTERS AND DEVELOPERS19/04/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Jul 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 May 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 May 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 May 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 11 Aug 2022

Documents filed48

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of ConveyanceFile: Conveyance Deed INDEX2.pdf24 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: homedale phase 1 form 5.pdf23 Feb 2023
Architect’s Certificate on Completion of Project (Form 4)File: Architects Certificate.pdf10 Feb 2023
Other - FinanceFile: Release Deed Hero Fin Corp.pdf4 Feb 2023
Details of encumbrances concerned to FinanceFile: LEGAL ADVOCATE CERTIFICATE.pdf3 Feb 2023
Details of encumbrances concerned to LegalFile: LEGAL ADVOCATE CERTIFICATE.pdf3 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure_compressed.pdf3 Feb 2023
Proforma of Allotment letterFile: Allotment letter phase 1.pdf3 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Adobe Scan 3 Feb 2023.pdf3 Feb 2023
Deviation Report with respect to Allotment letterFile: Allotment letter deviation phase 1.pdf3 Feb 2023
Deviation Report with respect to model copy of AgreementFile: Homedaledeviation report_compressed.pdf3 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Phase 1.pdf30 Jan 2023
Proforma of Agreement for saleFile: HOMEDALE A And B Building Master Draft.pdf27 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: SOCIETY REGISTRATION CERTIFICATE.pdf27 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: annual report homedale phase I form 5.pdf29 Dec 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate_FOR RERA_.pdf11 Aug 2022
Copy of the legal title reportFile: Title Search Report 2022.pdf7 Jul 2022
Declaration about Commencement CertificateFile: Declaration about commencement certificate - Phase I.pdf7 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Phase.pdf7 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Phase I.pdf7 Jul 2022
CERSAI detailsFile: CERSAI_Search_Report.pdf7 Jul 2022
Disclosure of sold/ booked inventoryFile: Disclosure Phase I.pdf7 Jul 2022
Certificates of CA (Form 3)File: Form 3 Phase I.pdf7 Jul 2022
PAN CardFile: Om Shiv Sai Pan Card.pdf2 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: C A Certificate1.pdf2 Mar 2022
Certificates of CA (Form 3)File: Certificate of cost incurred Certificate_compressed.pdf15 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect work progress report.pdf27 May 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Certificate of cost incurred_Final (1).pdf27 May 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineers Certificate on Quality Assurance 27052021.pdf27 May 2021
Disclosure of sold/ booked inventoryFile: maharera certifcate A and B Building-min (1).pdf27 May 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Certificate of cost incurred_Final (1).pdf27 May 2021
Proforma of Allotment letterFile: MasterDraft.pdf29 Oct 2020
Details of encumbrancesFile: ENCUMBRANCES_OSS 15082020 2125.pdf15 Aug 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: form 2a.pdf13 Feb 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 - Phase I reduced.pdf18 Jan 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - Phase I reduced.pdf18 Jan 2020
Certificates of CA (Form 3)File: CA Certificate.pdf5 Aug 2019
Building plan approvalFile: Sanctioned plan.pdf10 May 2018
Layout approvalFile: Sanctioned plan.pdf10 May 2018
Copy of the legal title reportFile: Title search 1.pdf10 May 2018
Copy of the legal title reportFile: Title search 2.pdf10 May 2018
Details of encumbrancesFile: Encumbrance Certificate.pdf10 May 2018
Copy of Layout Approval (in case of layout)File: Sanctioned plan.pdf10 May 2018
Building Plan Approval (IOD)File: Sanctioned plan.pdf10 May 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement reduced.pdf10 May 2018
Declaration in FORM BFile: Form_B_OSS.pdf10 May 2018
Proforma of Allotment letterFile: Booking Letter_OSS.pdf10 May 2018
Proforma of Allotment letterFile: Agreement draft copy.pdf10 May 2018

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
GrasslandS.No. 15 P and others Kolhewadi Khadakwasla Pune 411041228CompletedMar 2018Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Homedale on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Khadakwasla Bypass Road13,700+ in Pune

2 kmHomedaleCompleted 17Lapsed / revoked 8Other 10Dot size: filed unitsN

Filed coordinates, straight-line distance. 35 registered projects within 2 km.

Builder: M/s. Om Shiv Sai Promoters & Developers

M/s. Om Shiv Sai Promoters & Developers has 3 registrations on MahaRERA, including Homedale and HOMEDALE PHASE 2. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Homedale is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Homedale?

The registered promoter entity is M/s. Om Shiv Sai Promoters & Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Homedale?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Homedale?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Homedale?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Homedale?

The professionals named in the filing: Architect: Crystal Arch; Engineer: Structure Vision; Chartered Accountant: TANAJI CHORGE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Homedale?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Homedale. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Homedale to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.