Home / Browse projects / Thane, Maharashtra / Hiraco Eminence Phase 2

Registration lapsed No litigation declared Residential / Group Housing project

Hiraco Eminence Phase 2

By KASHIMIRA CERAMIC PRODUCTS LLP

RG-MH-24365 · RERA P51800008104 · Last updated on MahaRERA portal: 7 Oct 2021

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 73 months past the filed date
  • 20 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Sep 2020Possession promised73 months past this date
9 of 33Construction stages doneacross 3 buildings; furthest along: Podiums (if any), 90%
20Complaints at MahaRERAon this registration
Jump to the 34 documents Report an error

Hiraco Eminence Phase 2 is a Residential / Group Housing project by KASHIMIRA CERAMIC PRODUCTS LLP in Thane, Maharashtra, registered with MahaRERA as P51800008104 on 18 Aug 2017. Possession was promised by 30 Sep 2020 and is now 73 months past that date. 20 complaints are on record with the regulator.

At a glance

Project

  • NameHiraco Eminence Phase 2
  • TypeResidential / Group Housing
  • Location
    • NH8
    • Kashimira
    • Mira-Bhayandar (M Corp.)
    • Thane
    • 401104
  • Pincode401104
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800008104
  • ReraGenie IDRG-MH-24365

Builder

  • NameKASHIMIRA CERAMIC PRODUCTS LLP
  • Entity typeOthers
  • PartnersDHAVAL KODARBHAI DARJI Kodarbhai Darji, DAHYA BHAI SUTARIA Govind Bhai Sutariya
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked

Key dates

73 months past promisethis monthRegisteredAug 2017PromisedSep 2020

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Aug 2017
  • Promised completion30 Sep 2020
  • Revised completionNone
  • Buildings3 building records
  • Documents filed34 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA140000
B WINGNA150000
C WINGNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 7 Oct 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 90%.

A WING84%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)90%
Plinth100%
Stilt Floor90%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises55%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
B WING84%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)90%
Plinth100%
Stilt Floor90%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises55%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
C WING84%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)90%
Plinth100%
Stilt Floor90%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises55%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 7 Oct 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed177

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots177
Closed/Covered127
Open Space50
BuildingClosed/CoveredOpen SpaceTotal
A WING431760
B WING431760
C WING411657

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,690 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI12384.0
Proposed, not sanctioned5,471 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKANDIVALI EAST

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr.DilipKumar Mevada
PartnerRole in project
KASHIMIRA CERAMIC PRODUCTS LLP-

Litigation declared1

CaseCourtStatus
123/2014/2014IN THE COURT JUDICIAL MAGISTRATE FIRST CLASS THANEDisposed Off

Complaints filed with MahaRERA20

Case no.ComplainantRespondentFiled
CC006000000000940ROHIT DAROLIAKASHIMIRA CERAMIC PRODUCTS LLP27/09/2017
CC006000000000845Arati PanditKashimira Ceramic Products LLP23/09/2017
CC006000000000725DHEERAJ KUMAR SINGHKASHIMIRA CERAMIC PRODUCTS LLP22/09/2017
CC006000000000718Asavari GandharwarKashmira Ceramics Products LLP22/09/2017
CC006000000000933Tyrone ShiraziKashimira ceramic products LLP03/10/2017
CC006000000000760Deepak KaulKashimira Ceramics Products LLP23/09/2017
CC006000000000817Neha Dharmesh PatelKashimira Ceramic Products LLP23/09/2017
CC006000000001606Adesh Narhari ShirkeKashimira Ceramic Products LLP31/10/2017
CC006000000000853NIRMAL S SHAHKASHIMIRA CERAMIC PRODUCTS LLP30/09/2017
CC006000000001002Bipin R GuptaKashimira Ceramic Products LLP01/10/2017
CC006000000001004Bhupat Maganbhai HadiyaKashimira Ceramic Product LLP01/10/2017
CC006000000001026NILESH PRAVIN THAKKARKashimira Ceramic Product LLP02/10/2017
CC006000000001652Tanvi Eminence Owners Welfare AssociationKashimira Ceramic Products LLP08/11/2017
CC006000000001654Tanvi Eminence Owners Welfare AssociationKashimira Ceramic Products LLP08/11/2017
CC006000000001657Tanvi Eminence Owners Welfare AssociationKashimira Ceramic Products LLP08/11/2017
CC006000000001659Tanvi Eminence Owners Welfare AssociationKashimira Ceramic Products LLP08/11/2017
CC006000000012066Swati Umesh ShettyKashimira Ceramic Products LLP21/11/2017
CC006000000120961Bijoy KumarKashimira Ceramic Products LLP08/11/2019
CC006000000231154Sharat Chandra DashKashimira Ceramic Products LLP12/05/2022
CC006000000428774Dhirendra JhaKashimira Ceramic Products LLP09/01/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Sep 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 Oct 2020

Documents filed34

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
OtherFile: fire NOC phase II.pdf7 Oct 2021
Proforma of Allotment letterFile: Agreement For Sale 1.pdf15 Jan 2021
OtherFile: PHASE 2 - ABC.pdf26 Oct 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PHASE 2 - ABC.pdf8 Oct 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PHASE I - A WING.pdf8 Oct 2020
OtherFile: IMG-20200907-WA0030-converted.pdf7 Sep 2020
Commencement Certificates / NA Order for plotted developmentFile: H2 FINAL CC.pdf26 Sep 2019
Proforma of Allotment letterFile: P-2 RERA UPLOAD.pdf29 May 2018
OtherFile: high court order 1 .PDF4 Jan 2018
Details of encumbrancesFile: No Encumbrance Certificate Phase II.pdf30 Jul 2017
Declaration in FORM BFile: Form B Phase II(2).pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certifcate phase II Compressed.pdf30 Jul 2017
Certificates of CA (Form 3)File: rera certificate p2-min.pdf30 Jul 2017
Certificates of CA (Form 3)File: sold p2.pdf30 Jul 2017
Certificates of CA (Form 3)File: unsold p2.pdf30 Jul 2017
Certificates of CA (Form 3)File: Phase II Flat Adjustments letter.pdf30 Jul 2017
Proforma of Allotment letterFile: Sales Agreement P2.pdf30 Jul 2017
OtherFile: Bhupatbhai authority letter.pdf30 Jul 2017
OtherFile: Vijaybhai authority letter.pdf30 Jul 2017
Building plan approvalFile: IOD P2.pdf27 Jul 2017
Layout approvalFile: P2 A wing (1).pdf27 Jul 2017
Layout approvalFile: P2 Master plan (1).pdf27 Jul 2017
Layout approvalFile: P2 B wing (1).pdf27 Jul 2017
Layout approvalFile: P2 C wing (1).pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: P2 Master plan (1).pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: P2 A wing (1).pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: P2 B wing (1).pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: P2 C wing (1).pdf27 Jul 2017
Building Plan Approval (IOD)File: IOD P2.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC P2.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA_AR_CERTIFICATE_PHASE 2_270717 compress.pdf27 Jul 2017
PAN CardFile: KCPLLP Pan.pdf26 Jul 2017
Copy of the legal title reportFile: Phase II title certificate.pdf26 Jul 2017
Proforma of Allotment letterFile: Allotment Letter P2.pdf26 Jul 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Hiraco Eminence Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kashimira7,600+ in Thane

2 kmHiraco Eminence Phase 2Completed 5Lapsed / revoked 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 8 registered projects within 2 km.

Builder: KASHIMIRA CERAMIC PRODUCTS LLP

KASHIMIRA CERAMIC PRODUCTS LLP has 3 registrations on MahaRERA, including Hiraco Eminence Phase 1 and Hiraco Eminence Phase 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Hiraco Eminence Phase 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Hiraco Eminence Phase 2 is delayed beyond 30 Sep 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Hiraco Eminence Phase 2?

The registered promoter entity is KASHIMIRA CERAMIC PRODUCTS LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Hiraco Eminence Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Hiraco Eminence Phase 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Hiraco Eminence Phase 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Hiraco Eminence Phase 2?

The professionals named in the filing: Architect: Ar.DilipKumar Mevada. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Hiraco Eminence Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Hiraco Eminence Phase 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Hiraco Eminence Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.