Completed No litigation declared Residential / Group Housing project

Hi Life

By Rising welworth Enterprises LLP

RG-MH-81765 · RERA P52100016413 · Last updated on MahaRERA portal: 29 Aug 2025

Source: official MahaRERA filing

Red flags

  • 41 complaints at MahaRERA
  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2025Possession promisedregistration recorded completed
43 of 44Construction stages doneacross 4 buildings; furthest along: Podiums (if any), 0%
41Complaints at MahaRERAon this registration
Jump to the 139 documents Report an error

Hi Life is a Residential / Group Housing project by Rising welworth Enterprises LLP in Pune, Maharashtra, registered with MahaRERA as P52100016413 on 10 May 2018. The registration is recorded completed; possession was promised by 31 Mar 2025. The completion date has moved by 21 months from the original filing. 41 complaints are on record with the regulator.

At a glance

Project

  • NameHi Life
  • TypeResidential / Group Housing
  • Location
    • Aundh Ravet Road
    • Dange Chowk
    • Thergaon
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100016413
  • ReraGenie IDRG-MH-81765

Builder

  • NameRising welworth Enterprises LLP
  • Entity typePartnership
  • GSTIN27AAPFV1388P1Z4
  • PartnerNilesh Vilas Palresha
  • Other registrations3 more →
  • Completed3 of 4
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredMay 2018First promiseJun 2023Revised toMar 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on10 May 2018
  • Promised completion31 Mar 2025
  • Revised completionRevised to 31 Mar 2025 (originally 30 Jun 2023)
  • Buildings4 building records
  • Documents filed139 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
T1 BuildingNA230000
T2 BuildingNA230000
T3 BuildingNA230000
MhadaNA130000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 29 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

43 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Podiums (if any), at 0%.

T1 Building100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
T2 Building100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
T3 Building100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Mhada91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 29 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes75%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed398

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots398
Closed/Covered329
Open Space69
BuildingClosed/CoveredOpen SpaceTotal
T1 Building9621117
T2 Building9621117
T3 Building12727154
Mhada10010

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area11,012 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on28 Sep 2024
LandownerVillageDistrict
Siddharth Kantilal KhinvasaraBanerPune

Approvals and building plan

Sanctioning authorityPIMPARI CHINCHAVAD MUNICIPAL CORPORATION
Permissible FSI24250.19
Proposed, not sanctioned21,541 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKHARADI

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Reza Kabul
ArchitectVK Architect
ArchitectAr MInal Firake
EngineerJw Consultant
EngineerAvinash chavhan
Chartered AccountantSAC & CO LLP
Chartered AccountantCA Priyanka Chordiya
PartnerRole in project
Rising welworth Enterprises LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100017105Jun 2023 → Mar 2024

Reason as filed by the promoterThe work of MHADA building has been delayed for the reasons (1) The MAHADA building was P + 11 floors earlier, however due to implementation of Unified Development Control and Promotion Regulations (UDCPR) for Maharashtra State, the potential of the plot changed, hence accordingly the MAHADA building got revised by the authority Pimpri Chinchwad Municipal Corporation. However, Environment Clearance thereof was granted by State Environment Impact Assessment Authority (SEIAA) on 11.04.2023, therefore the construction schedule of the building got changed. The work of this building was stopped for

EXT52100025164Jun 2023 → Mar 2025

Reason as filed by the promoterWe state and declare that, the above-mentioned project has been duly completed and the concerned competent authority Pimpri Chinchwad Municipal Corporation has already issued occupancy certificate on 21.03.2023 for building no. T1, T2, T3. Further, the promoter has already applied to Pimpri Chinchwad Municipal Corporation for Occupancy Certificate of MHADA Building on 09.07.2024 through its online system application, copy whereof is annexed herewith. The project registration was valid up to 31.03.2024, hence to enable us to file Form 4 on receipt of occupancy certificate, we humbly request you

Complaints filed with MahaRERA41

Case no.ComplainantRespondentFiled
CC005000000022694Sagar GhateAbhijeet Kedar20/02/2019
CC005000000279831Vaibhav Vishnu KumbharRising Welworth Enterprises LLP11/12/2023
CC005000000279852HARIDAS KUNDALIK SALUNKHERising Welworth Enterprises LLP11/12/2023
CC005000000290249SAVITA RAJENDRA BHADRising Welworth Enterprises LLP30/01/2024
CC005000000290251NIKHIL BABAN KAKADERising Welworth Enterprises LLP30/01/2024
CC005000000290276BHAUSAHEB RAMKRUSHNA VIDHATERISING WELWORTH ENTERPRISES LLP31/01/2024
CC005000000310353PALLAVI RAJEBHAU MANERISING WELWORTH ENTERPRISES LLP09/02/2024
CC005000000370959RUPALI APURVA GIRIMs Rising Welworth Enterprises LLP22/05/2024
CC12400249Prakash Dattu AmbilkarRising welworth Enterprises LLP27/09/2024
CC12400279GANESH PRAKASH SHELKERising welworth Enterprises LLP30/09/2024
CC12400281SHIVAM RAVINDRA SURYAWANSHIRising welworth Enterprises LLP30/09/2024
CC12400319PRATIK BHARAT PANBUDERising welworth Enterprises LLP03/10/2024
CC12400348Gajanan Bhagwan ShiralRising welworth Enterprises LLP05/10/2024
CC12400506Chaitrali Bharat JogdandRising welworth Enterprises LLP21/10/2024
CC12400883JITENDRA BALIRAM SAVDEKARRising welworth Enterprises LLP25/11/2024
CC12401128ASHISH VILASRAO NANANDKARRising welworth Enterprises LLP14/12/2024
CC12401130DARPAN SANTOSH CHAUDHARIRising welworth Enterprises LLP14/12/2024
CC12401145GOVERDHAN DNYANESWAR SONWANERising welworth Enterprises LLP16/12/2024
CC12401226GANESH SUKHDEV MALIRising welworth Enterprises LLP24/12/2024
CC12401239NITIN SUNDARRAO TANDALERising welworth Enterprises LLP25/12/2024
CC12401245HANMANT SADASHIV GHODKERising welworth Enterprises LLP26/12/2024
CC12500447Avinash Sopan KumbharRising welworth Enterprises LLP10/02/2025
CC12500192Harshal Ranuji GhuleRising welworth Enterprises LLP20/01/2025
CC12500095NETAJI BABURAO RATHODRising welworth Enterprises LLP10/01/2025
CC12500105DIPTI SHAILENDRASINGH CHAUHANRising welworth Enterprises LLP11/01/2025
CC12500106ANITA JAYPAL MANDAVERising welworth Enterprises LLP11/01/2025
CC12500140DHANASHRI BALASAHEB PAWARRising welworth Enterprises LLP15/01/2025
CC12500147MANISHA SADASHIV NARKERising welworth Enterprises LLP16/01/2025
CC12500448Nikhil Tushar BagalRising welworth Enterprises LLP10/02/2025
CC12500217CHAITALI NANDKUMAR JADHAVRising welworth Enterprises LLP22/01/2025
CC12500218Arinjay Subhash KalantreRising welworth Enterprises LLP22/01/2025
CC12500894ANAND SURESH JOSHIRising welworth Enterprises LLP14/03/2025
CC12500453DIPALI PRASHANT SHINDERising welworth Enterprises LLP11/02/2025
CC12500860AMAR SHRIRANG KODITKARRising welworth Enterprises LLP12/03/2025
CC12500955UNMANI PRAMOD SONAWANERising welworth Enterprises LLP18/03/2025
CC12501103GITANJALEE PRADEEP SONAWANERising welworth Enterprises LLP02/04/2025
CC12501107NIKITA YASHWANT SHINGATERising welworth Enterprises LLP02/04/2025
CC12501122MAYA MAHADEO UIKERising welworth Enterprises LLP03/04/2025
CC12501634RAMKRUSHNA SAMBHAJI SHINDERising welworth Enterprises LLP20/05/2025
CC12602942Rising welworth Enterprises LLPMr DYANDEO BHASKAR WANDHEKAR19/05/2026
CC12602944Rising welworth Enterprises LLPMs KRITIKA JINDAL19/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 May 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Feb 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 May 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Feb 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 9 Jul 2025

Documents filed139

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 139 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: FORM 5 HI LIFE.pdf29 Aug 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC VERIFICATION MAIL- HI LIFE AND HI LIFE PHASE 3.pdf9 Jul 2025
Other - TechnicalFile: OC VERIFICATION MAIL- HI LIFE AND HI LIFE PHASE 3.pdf9 Jul 2025
Certificates of CA (Form 3)File: Form 3 Hi life.pdf21 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Hi life.pdf21 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 HI LIFE.pdf9 Apr 2025
Other - LegalFile: FORM 4 HI LIFE.pdf9 Apr 2025
Disclosure of sold/ booked inventoryFile: HI LIFE PHASE 1 31032025.pdf5 Apr 2025
Status of Formation of Legal Entity (Society/Co Op etc.)File: Registration Cert-VTP HILIFE.pdf4 Apr 2025
Status of Formation of Legal Entity (Society/Co Op etc.)File: Registration Cert-VTP HILIFE MHADA.pdf4 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 5.pdf4 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 HI LIFE 30092024.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 HI LIFE 31122024.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 HI LIFE 30092024.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 HI LIFE 31122024.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 HI LIFE 30092024.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 HI LIFE 31122024.pdf16 Jan 2025
Certificates of CA (Form 3)File: FORM 3 HILIFE 31122024.pdf14 Jan 2025
Certificates of CA (Form 3)File: FORM 3 HILIFE 31122024.pdf14 Jan 2025
Certificates of CA (Form 3)File: FORM 3 HILIFE 31122024.pdf14 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 HI LIFE PHASE 3 31122024.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 HI LIFE 31122024.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PH-1 FORM 2 3QTR FINAL.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 HI LIFE PHASE 3 31122024.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 HI LIFE 31122024.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PH-1 FORM 2 3QTR FINAL.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PH-1 FORM 2 3QTR FINAL.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 HI LIFE PHASE 3 31122024.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 HI LIFE 31122024.pdf13 Jan 2025
Certificates of CA (Form 3)File: HI LIFE FORM3 31032022.pdf7 Dec 2024
Certificates of CA (Form 3)File: HI LIFE FORM3 31032022.pdf7 Dec 2024
Certificates of CA (Form 3)File: HI LIFE FORM3 31032022.pdf7 Dec 2024
Disclosure of sold/ booked inventoryFile: HI LIFE PH1 30092024.pdf25 Nov 2024
Declaration in FORM BFile: FORM B.pdf25 Nov 2024
Details of encumbrancesFile: ENCM TO FIN- HI LIFE.pdf25 Nov 2024
Disclosure of sold/ booked inventoryFile: HI LIFE PH1 30092024.pdf25 Nov 2024
Declaration in FORM BFile: FORM B.pdf25 Nov 2024
Details of encumbrancesFile: ENCM TO FIN- HI LIFE.pdf25 Nov 2024
Details of encumbrancesFile: ENCM TO FIN- HI LIFE.pdf25 Nov 2024
Declaration in FORM BFile: FORM B.pdf25 Nov 2024
Disclosure of sold/ booked inventoryFile: HI LIFE PH1 30092024.pdf25 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 HI LIFE 18072024.pdf13 Nov 2024
Certificates of CA (Form 3)File: FORM 3 HI LIFE PHASE 3.pdf13 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 HI LIFE 18072024.pdf13 Nov 2024
Certificates of CA (Form 3)File: FORM 3 HI LIFE PHASE 3.pdf13 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 HI LIFE 18072024.pdf13 Nov 2024
Certificates of CA (Form 3)File: FORM 3 HI LIFE PHASE 3.pdf13 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Hilife PH 1.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Hilife PH 1.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Hilife PH 1.pdf18 Oct 2024
Certificates of CA (Form 3)File: HI LIFE PH-1 FORM-3 FINAL 2QTR.pdf17 Oct 2024
Certificates of CA (Form 3)File: HI LIFE PH-1 FORM-3 FINAL 2QTR.pdf17 Oct 2024
Certificates of CA (Form 3)File: HI LIFE PH-1 FORM-3 FINAL 2QTR.pdf17 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 Hi Life 31-03-2024_compressed.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 Hi Life 31-03-2024_compressed.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 Hi Life 31-03-2024_compressed.pdf7 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Hilife Phase 1 30062024.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: HI LIFE 1 30062024.pdf9 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A HI LIFE PHASE 1 2 3 31032024.pdf16 May 2024
Disclosure of sold/ booked inventoryFile: INVENTORY HI LIFE PHASE 1 31122023.pdf9 May 2024
Disclosure of sold/ booked inventoryFile: INVENTORY HI LIFE PHASE 1 31032024.pdf9 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 HI LIFE PHASE 1 31032024.pdf26 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 HI LIFE PHASE 1 31032024.pdf26 Apr 2024
Certificates of CA (Form 3)File: FORM 3 HILIFE PH-1 SIGN 4QTR.pdf26 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 Hi life phase 31-12-2023.pdf3 Feb 2024
Certificates of CA (Form 3)File: Form 3 31122023 Highlife phase1-Mhada-both sign- compressed.pdf3 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 HI LIFE PHASE 1 31122023.pdf13 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A HI LIFE PHASE 1 31032020.pdf9 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 HI LIFE 30092023.pdf28 Oct 2023
Certificates of CA (Form 3)File: FORM 3 HI LIFE 30092023.pdf28 Oct 2023
Disclosure of sold/ booked inventoryFile: INVENTORY HI LIFE 1 30092023.pdf19 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 HI LIFE PHASE 1 30092023.pdf16 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RISING WELWORTH - PHASE 1 FY 22-23 FORM 5.pdf13 Oct 2023
Disclosure of sold/ booked inventoryFile: HI LIFE MHADA 30062023.pdf28 Aug 2023
Disclosure of sold/ booked inventoryFile: INVENTORY HI LIFE MHADA 30062023.pdf24 Aug 2023
Disclosure of sold/ booked inventoryFile: HI LIFE PHASE 1 31122021.pdf24 Aug 2023
Disclosure of sold/ booked inventoryFile: HI LIFE PHASE 1 30062022.pdf24 Aug 2023
Disclosure of sold/ booked inventoryFile: HI LIFE PHASE 1 30092022.pdf24 Aug 2023
Disclosure of sold/ booked inventoryFile: HI LIFE PHASE 1 31122022.pdf24 Aug 2023
Disclosure of sold/ booked inventoryFile: HI LIFE PHASE 1 30062023.pdf24 Aug 2023

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 21 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Hi Life on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dange Chowk13,700+ in Pune

2 kmHi LifeCompleted 107Lapsed / revoked 45Other 58Dot size: filed unitsN

Filed coordinates, straight-line distance. 210 registered projects within 2 km.

Builder: Rising welworth Enterprises LLP

Rising welworth Enterprises LLP has 4 registrations on MahaRERA, including Hi Life and Hi Life phase 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Hi Life is delayed beyond 31 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Hi Life?

The registered promoter entity is Rising welworth Enterprises LLP, a partnership as per the filing. Its GSTIN 27AAPFV1388P1Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Hi Life?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Hi Life?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Hi Life?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Hi Life?

The professionals named in the filing: Architect: Ar Reza Kabul; Architect: VK Architect; Architect: Ar MInal Firake; Engineer: Jw Consultant; Engineer: Avinash chavhan; Chartered Accountant: SAC & CO LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Hi Life?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Hi Life. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Hi Life to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.