Home / Browse projects / Pune, Maharashtra / HERAMB PLAZA
HERAMB PLAZA
RG-MH-16455 · RERA P52100026196 · Last updated on MahaRERA portal: 3 Aug 2026
Source: official MahaRERA filing
Red flags
- Completion date moved by 25 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
HERAMB PLAZA is a Others project by BRICK NEST PROPERTIES LLP in Pune, Maharashtra, registered with MahaRERA as P52100026196 on 29 Aug 2020. The registration is recorded completed; possession was promised by 31 Dec 2026. The completion date has moved by 25 months from the original filing. 33 of the 53 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.
At a glance
Project
- NameHERAMB PLAZA
- TypeOthers
- Location
- 60/2
- SOMWAR PETH
- Pune (M Corp.)
- Pune City
- Pune
- 411011
- Pincode411011
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100026196
- ReraGenie IDRG-MH-16455
Builder
- NameBRICK NEST PROPERTIES LLP
- Entity typePartnership
- PartnersTARANG SATISH PANCHOLI, KARAN SANDEEP JANI, SACHIN SURESH TAUR, VIRAJ GAUTAM GELADA, RUPALI BAHIRAT, VIREN VIKRAMSINH TAUR, NAREDRA VITHAL BAHIRAT
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on29 Aug 2020
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Nov 2024)
- Buildings1 building record
- Documents filed120 files
Current status
Figures as on 3 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| HERAMB PLAZA | NA | 9 | 8 | 49 | 4 | 53 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 3 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
HERAMB PLAZA: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 3 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed69
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| HERAMB PLAZA | NA | Rs 3.89 cr | Rs 8.17 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RAJENDRA THITE |
| Engineer | TARANG SATISH PANCHOLI |
| Chartered Accountant | CA Sachin Mishra |
| Chartered Accountant | Pravin Pise and Associates |
| Partner | Role in project |
|---|---|
| BRICK NEST PROPERTIES LLP | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterBuilding work completed, Application for occupation certificate to be submit in PMC.
Reason as filed by the promoterThe project completion has been delayed due to circumstances beyond the control of the promoter. The project was adversely affected by delays in statutory approvals, disruption in availability of labor and construction materials, and interruptions caused by external factors. In addition, unforeseen administrative and operational challenges impacted the planned construction schedule. Despite these difficulties, the promoter has continued construction activities and remains fully committed to completing the project at the earliest. The extension is sought to ensure timely completion with require
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 4 Feb 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Jun 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed120
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 120 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: F1 - Architect Certificate Mar 26.pdf | 3 Aug 2026 |
| Withdrawal Update Form 2File: F2 - Engineer Certificate Mar 26.pdf | 3 Aug 2026 |
| Withdrawal Update Form 3File: F3-BRICKNEST.pdf | 3 Aug 2026 |
| Occupational CertificateFile: Full Occupancy Certificate.pdf | 3 Aug 2026 |
| Building plan approvalFile: Plan 01.pdf | 26 Jun 2026 |
| Building plan approvalFile: Plan 02.pdf | 26 Jun 2026 |
| Building plan approvalFile: Plan 03.pdf | 26 Jun 2026 |
| Building plan approvalFile: Plan 04.pdf | 26 Jun 2026 |
| Withdrawal Update Form 1File: Architect_Certificate_-_Sept 25.pdf | 26 Jun 2026 |
| Withdrawal Update Form 1File: Architect Certificate-Dec 25.pdf | 26 Jun 2026 |
| Withdrawal Update Form 1File: F1 - Architect Certificate Mar 26.pdf | 26 Jun 2026 |
| Withdrawal Update Form 2File: Engineer Certificate_ Sept25.pdf | 26 Jun 2026 |
| Withdrawal Update Form 2File: Engineer Certificate_ Dec25.pdf | 26 Jun 2026 |
| Withdrawal Update Form 2File: F2 - Engineer Certificate Mar 26.pdf | 26 Jun 2026 |
| Withdrawal Update Form 3File: F3-BRICKNEST-SEPT-25.pdf | 26 Jun 2026 |
| Withdrawal Update Form 3File: F3-BRICKNEST-Q3.pdf | 26 Jun 2026 |
| Withdrawal Update Form 3File: F3-BRICKNEST.pdf | 26 Jun 2026 |
| Form 2A (FY 2025-2026)File: Form 2A.pdf | 19 Jun 2026 |
| Withdrawal Update Form 1File: F1 - Architect Certificate Mar 26.pdf | 30 May 2026 |
| Withdrawal Update Form 2File: F2 - Engineer Certificate Mar 26.pdf | 30 May 2026 |
| Withdrawal Update Form 3File: F3-BRICKNEST.pdf | 30 May 2026 |
| Form 5 (FY 2023-2024)File: F5-FY 23-24(BRICKNEST).pdf | 14 Feb 2026 |
| Form 5 (FY 2024-2025)File: F5-FY 24-25(BRICKNEST).pdf | 14 Feb 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - Heramb Plaza - June 24.pdf | 28 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - Heramb Plaza - Sep 24.pdf | 28 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Bricknest_Jun-24.pdf | 28 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Bricknest_Sep-24.pdf | 28 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - Heramb Plaza - June 24.pdf | 28 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - Heramb Plaza - Sep 24.pdf | 28 Nov 2024 |
| Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Legal.pdf | 21 Jun 2024 |
| Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Finance.pdf | 21 Jun 2024 |
| Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Legal.pdf | 21 Jun 2024 |
| Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Finance.pdf | 21 Jun 2024 |
| Declaration about Commencement CertificateFile: fORM d_page-0001.pdf | 21 Jun 2024 |
| Declaration in FORM BFile: Developers Form B.pdf | 21 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-Dec 23.pdf | 21 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-June 23.pdf | 21 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-March 21.pdf | 21 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-March 22.pdf | 21 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-March 23.pdf | 21 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-March 24.pdf | 21 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-Sep 23.pdf | 21 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate-Dec 23.pdf | 21 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate-June 23.pdf | 21 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate-March 21.pdf | 21 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate-March 22.pdf | 21 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate-March 23.pdf | 21 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate-March 24.pdf | 21 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate-Sep 23.pdf | 21 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A-March-21.pdf | 21 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A-March-22.pdf | 21 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A-March-23.pdf | 21 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A-March-24.pdf | 21 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf | 21 Jun 2024 |
| CERSAI detailsFile: CERSAI Details (1).pdf | 21 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_20-21.pdf | 21 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_21-22.pdf | 21 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_22-23.pdf | 21 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_23-24-Q1.pdf | 21 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_23-24-Q2.pdf | 21 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_23-24-Q4.pdf | 21 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_23-24-Q3.pdf | 21 Jun 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations-Tarang (7 files merged).pdf | 21 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA Audit Report_20-21.pdf | 21 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA Audit Report_21-22.pdf | 21 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RERA Audit Report_22-23.pdf | 21 Jun 2024 |
| Proforma of Allotment letterFile: Allotment Letter_compressed.pdf | 21 Jun 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account Declaration.pdf | 21 Jun 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation of Allotment Letter.pdf | 21 Jun 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation for AFS.pdf | 21 Jun 2024 |
| Other - TechnicalFile: Annexure-A.pdf | 21 Jun 2024 |
| Building plan approvalFile: 20221020002.pdf | 2 Mar 2023 |
| Building plan approvalFile: 20221020003.pdf | 2 Mar 2023 |
| Building plan approvalFile: 20221020005.pdf | 2 Mar 2023 |
| Building plan approvalFile: 20221020006.pdf | 2 Mar 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 20221020002.pdf | 2 Mar 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 20221020003.pdf | 2 Mar 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 20221020005.pdf | 2 Mar 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 20221020006.pdf | 2 Mar 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: 20221020007.pdf | 2 Mar 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 120 filed documents as one ZIP, foldered, with a manifest
Keep HERAMB PLAZA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SOMWAR PETH13,700+ in Pune
Filed coordinates, straight-line distance. 268 registered projects within 2 km.
Wyng
Manasara Realty LLP
SARA KASTURI BUILDING C
JAGRUTSARA STRUCTURES LLP
ANTRIKSH TOWERS
AUM CITYSCAPES LLP
EVOLET TIARA
M/S EVOLET DEVELOPERS
B. T. SQUARE
AJAY JAYAWANT BHOSLE
GIRNAR
SHREE DATTA REALTORS
Builder: BRICK NEST PROPERTIES LLP
BRICK NEST PROPERTIES LLP has 1 registration on MahaRERA, including HERAMB PLAZA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if HERAMB PLAZA is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of HERAMB PLAZA?
The registered promoter entity is BRICK NEST PROPERTIES LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in HERAMB PLAZA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for HERAMB PLAZA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at HERAMB PLAZA?
The professionals named in the filing: Architect: RAJENDRA THITE; Engineer: TARANG SATISH PANCHOLI; Chartered Accountant: CA Sachin Mishra; Chartered Accountant: Pravin Pise and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in HERAMB PLAZA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback