Home / Browse projects / Dadra & Nagar Haveli / HARMONY PHASE 2

Registration lapsed No litigation declared Residential / Group Housing project

HARMONY PHASE 2

By PRAMUKH REALTY

RG-MH-00964 · RERA P49600000124 · Last updated on MahaRERA portal: 20 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Dadra & Nagar Haveli registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
188 of 253Construction stages doneacross 23 buildings; furthest along: Staircases, 70%
10 of 27Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 121 documents Report an error

HARMONY PHASE 2 is a Residential / Group Housing project by PRAMUKH REALTY in Dadra & Nagar Haveli, registered with MahaRERA as P49600000124 on 4 Jan 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date. 17 of the 27 units on this registration are recorded sold or booked, and 188 of 253 construction stages are filed complete.

At a glance

Project

  • NameHARMONY PHASE 2
  • TypeResidential / Group Housing
  • Location
    • AYAPPA TEMPLE ROAD
    • NEXT TO FLORA
    • KAMLI FALIYA
    • Dadra & Nagar Haveli
    • 396230
  • Pincode396230
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P49600000124
  • ReraGenie IDRG-MH-00964

Builder

  • NamePRAMUKH REALTY
  • Entity typePartnership
  • PartnersAJIT HARDAS KHODBHAYA, TAPAN DEVSHI BHATU
  • Other registrations13 more →
  • Completed7 of 14
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

10 months past promisethis monthRegisteredJan 2022PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on4 Jan 2022
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings23 building records
  • Documents filed121 files

Current status

63%17 of 27 units booked
122.2%Work done, per cost certificate

Figures as on 20 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
07NA33101
08NA30101
09NA30101
10NA30101
11A and 11BNA30202
12NA30101
13NA30101
14NA30101
15NA30101
16NA30101
17NA30101
18A and 18BNA30202
19NA30101
20NA30101
21A and 21BNA30202
23NA30101
22A and 22BNA30202
1NA30101
2NA30101
3NA30101
4NA30101
5NA30101
6NA30101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 20 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 23 buildings; the table lists the first 20.

188 of 253 construction stages are filed complete across 23 buildings. The stage furthest along is Staircases, at 70%.

0782%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
080%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
0979%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
1082%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
11A and 11B82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
1282%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
135%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
1482%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
1582%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
1682%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
1782%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
18A and 18B82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
1982%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
2082%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
21A and 21B82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
2382%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
22A and 22B82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
182%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
282%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
382%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed26

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots26
Open Space26
BuildingOpen SpaceTotal
0711
0811
0911
1011
11A and 11B11
1211
1311
1411
1511
1611
1711
18A and 18B22
1911
2011
21A and 21B22
2311
22A and 22B22
111
211
311
411
511
611

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area6,777 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on28 Jun 2025

Approvals and building plan

Sanctioning authoritySilvassa Municipal Councial
Permissible FSI7018.0
Proposed, not sanctioned4,573 sq m
Buildings approved23
Buildings sanctioned23

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHDFC BANK LTD JAYPEE HOUSE OPP PATEL PETROL PUMP VAPI SILVASSA ROAD SILVASSA DNH DD 396230
Estimated costRs 24.95 cr
Cost incurredRs 30.49 cr
Work done122.21%
BuildingWingEstimatedIncurred
-NARs 5.91 crRs 5.32 cr
11A and 11BNARs 1.21 crRs 1.63 cr
18A and 18BNARs 1.19 crRs 1.61 cr
21A and 21BNARs 1.19 crRs 1.61 cr
22A and 22BNARs 1.19 crRs 1.61 cr
07NARs 75.05 lakhRs 1.02 cr
08NARs 75.05 lakh-
09NARs 75.05 lakhRs 1.19 cr
10NARs 75.05 lakhRs 1.19 cr
12NARs 75.05 lakhRs 1.02 cr
13NARs 75.05 lakh-
14NARs 75.05 lakhRs 1.02 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Imran Mohammad Abbas Shaikh
ArchitectISHWARLAL M GEHI
EngineerAbhishek Golcha
EngineerMr Aqueelur Rahman Mohammed Haneef
Chartered AccountantD.K. LAKHANI & CO
PartnerRole in project
PRAMUKH REALTY-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Dec 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Dec 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed121

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 121 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 Harmony PH 2.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2 Harmony PH 2.pdf20 Jan 2026
Withdrawal Update Form 3File: HARMONY PH 2 FORM 3_SIGNATURE (1).pdf20 Jan 2026
Withdrawal Update Form 1File: FORM 1 HARMONY PH 2 - OK.pdf18 Oct 2025
Withdrawal Update Form 1File: FORM 1 HARMONY PH 2 - OK.pdf18 Oct 2025
Withdrawal Update Form 2File: Form 2 HAR- PH 2 OK.pdf18 Oct 2025
Withdrawal Update Form 2File: Form 2 HAR- PH 2 OK.pdf18 Oct 2025
Withdrawal Update Form 3File: Pramuk Reality Harmony Phase 2.pdf18 Oct 2025
Withdrawal Update Form 3File: Pramuk Reality Harmony Phase 2.pdf18 Oct 2025
Form 5 (FY 2024-2025)File: Signed Harmony PH2 Form 5.pdf14 Oct 2025
Form 1File: HAR PH 2 FORM 1.pdf20 Aug 2025
Form 2File: HAR PH 2 FORM 2.pdf20 Aug 2025
Form 3File: HAR PH 2 FORM 3.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: HAR PH 2 FORM 3.pdf20 Aug 2025
Form 1File: Form 1 HAR 2.pdf20 Aug 2025
Form 2File: Form 2 HAR2.pdf20 Aug 2025
Form 3File: FORM 3 HAR 2.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: FORM 3 HAR 2.pdf20 Aug 2025
Form 1File: Harmony Phase-2 Form 1.pdf20 Aug 2025
Form 2File: Harmony Phase 2 Form 2.pdf20 Aug 2025
Form 3File: Harmony Phase 2 Form 3.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: Harmony Phase 2 Form 3.pdf20 Aug 2025
Form 1File: Harmony 2 Form 1.pdf20 Aug 2025
Form 2File: Harmony 2 Form 2.pdf20 Aug 2025
Form 3File: Harmony 2 Form 3.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: Harmony 2 Form 3.pdf20 Aug 2025
Form 1File: FORM 1 HARMONY 2 DEC 2023.pdf20 Aug 2025
Form 2File: FORM 2 HARMONY 2 DEC 2023.pdf20 Aug 2025
Form 3File: FORM 3 HARMONY 2 DEC 2023.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: FORM 3 HARMONY 2 DEC 2023.pdf20 Aug 2025
Form 1File: Form 1 Harmony 2 Sep 23.pdf20 Aug 2025
Form 2File: Form 2 Harmony 2 Sep 23.pdf20 Aug 2025
Form 3File: Form 3 PR Harmony Phase 2 Sep 23.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: Form 3 PR Harmony Phase 2 Sep 23.pdf20 Aug 2025
Withdrawal Update Form 1File: Form 1 Harmony Phase 2 Sing.pdf20 Aug 2025
Withdrawal Update Form 2File: FORM 2 HARMONY PH -2 Sing.pdf20 Aug 2025
Withdrawal Update Form 3File: FORM 3 PRAMUKH REALTY HARMONY PH 2 _signature.pdf20 Aug 2025
Form 1File: FORM 1 HAR-PH-2.pdf12 Jul 2025
Form 2File: FORM 2 HAR-PH-2.pdf12 Jul 2025
Form 3File: FORM 3 HAR-PH-2.pdf12 Jul 2025
Disclosure of Sold and Booked InventoryFile: FORM 3 HAR-PH-2.pdf12 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: FORM 1 HAR-PH-2.pdf24 Apr 2025
Certificates of CA (Form 3) (UT)File: FORM 3 HAR-PH-2.pdf24 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: FORM 2 HAR-PH-2.pdf24 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A HAR-PH-2.pdf24 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: HAR PH 2 FORM 1.pdf25 Jan 2025
Certificates of CA (Form 3) (UT)File: HAR PH 2 FORM 3.pdf25 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: HAR PH 2 FORM 2.pdf25 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A)File: HAR PH 2 FORM 2A.pdf25 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: Form 1 HAR 2.pdf18 Oct 2024
Certificates of CA (Form 3) (UT)File: FORM 3 HAR 2.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: Form 2 HAR2.pdf18 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A HAR 2.pdf18 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Harmony Ph 2 Form 5.pdf10 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: Harmony Phase-2 Form 1.pdf19 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: Harmony Phase 2 Form 2.pdf19 Jul 2024
Certificates of CA (Form 3) (UT)File: Harmony Phase 2 Form 3.pdf19 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A)File: Harmony Phase 2 2A.pdf19 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: Harmony 2 Form 1.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: Harmony 2 Form 2.pdf20 Apr 2024
Certificates of CA (Form 3) (UT)File: Harmony 2 Form 3.pdf20 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A)File: Harmony Phase 2 form 2A.pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: FORM 1 HARMONY 2 DEC 2023.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: FORM 2 HARMONY 2 DEC 2023.pdf19 Jan 2024
Certificates of CA (Form 3) (UT)File: FORM 3 HARMONY 2 DEC 2023_compressed.pdf19 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A)File: 2AHarmony P2.pdf19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: Form 1 Harmony 2 Sep 23.pdf25 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: Form 2 Harmony 2 Sep 23.pdf25 Nov 2023
Certificates of CA (Form 3) (UT)File: Form 3 PR Harmony Phase 2 Sep 23.pdf25 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A Harmony 2 Sep 23.pdf25 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Harmony PH-2 Project F Y -2022-23.pdf26 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: HARMONY PH 2 FORM 2.pdf28 Jul 2023
Certificates of CA (Form 3) (UT)File: HARMONY PH 2 Form 3.pdf28 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A)File: Harmony ph2 2A.pdf28 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: HARMONY phase 2 - form 1.pdf12 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: HARMONY phase 2 - form 2.pdf12 Apr 2023
Certificates of CA (Form 3) (UT)File: HARMONY phase 2 - form 3.pdf12 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 21 22.pdf15 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A)File: HARMONY PH2 2ND 2223.pdf8 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A)File: HARMONY PH2 1ST 2223.pdf20 Jul 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
PRAMUKH SNEHSAMARVANI253CompletedDec 2018Sep 2018

How this compares with Dadra & Nagar Haveli

63%of this project is bookeddistrict median 30%
10%of Dadra & Nagar Haveli projects moved their completion datethis one has not
28%of Dadra & Nagar Haveli registrations have lapsed or been cancelledthis one is among them

Computed across the 210+ Dadra & Nagar Haveli projects on ReraGenie, from their own filings.

Keep HARMONY PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KAMLI FALIYA210+ in Dadra & Nagar Haveli

2 kmHARMONY PHASE 2Completed 20Lapsed / revoked 7Other 32Dot size: filed unitsN

Filed coordinates, straight-line distance. 59 registered projects within 2 km.

Builder: PRAMUKH REALTY

Pramukh Realty has 14 registrations on MahaRERA, including Pramukh Sneh Phase 2 and Nakshatra A-B. Its filings disclose 5 earlier MahaRERA projects: declares 5 of 5 past projects completed on time. Read the full track record. See more projects on the Dadra & Nagar Haveli district page.

Frequently asked questions

What does it mean that HARMONY PHASE 2 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if HARMONY PHASE 2 is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of HARMONY PHASE 2?

The registered promoter entity is PRAMUKH REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in HARMONY PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for HARMONY PHASE 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at HARMONY PHASE 2?

The professionals named in the filing: Architect: Mr Imran Mohammad Abbas Shaikh; Architect: ISHWARLAL M GEHI; Engineer: Abhishek Golcha; Engineer: Mr Aqueelur Rahman Mohammed Haneef; Chartered Accountant: D.K. LAKHANI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HARMONY PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HARMONY PHASE 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HARMONY PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.