Home / Browse projects / Solapur, Maharashtra / Harikrupa residency
Harikrupa residency
RG-MH-23067 · RERA P52600033486 · Last updated on MahaRERA portal: 27 May 2024
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations.
See what the report covers Free either way: or have every new Solapur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Harikrupa residency is a Residential / Group Housing project by Shri Samarth Construction in Solapur, Maharashtra, registered with MahaRERA as P52600033486 on 22 Feb 2022. The registration is recorded completed; possession was promised by 31 Dec 2025.
At a glance
Project
- NameHarikrupa residency
- TypeResidential / Group Housing
- Location
- pune pandharpur highway
- lokhande vasti
- Wakhari
- Pandharpur
- Solapur
- 413304
- Pincode413304
- RERA no.P52600033486
- ReraGenie IDRG-MH-23067
Builder
- NameShri Samarth Construction
- Entity typePartnership
- GSTIN27AELFS4726A1Z2
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- Partnersamit arvind shirgaonkar, shashikant jaysing sutar, sachin Uday Pandharpurkar
- Other registrations2 more →
- Completed2 of 3
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on22 Feb 2022
- Promised completion31 Dec 2025
- Revised completionNone
- Buildings35 building records
- Documents filed167 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Bunglow no 1 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 2 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 3 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 4 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 5 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 6 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 7 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 8 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 9 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 10 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 11 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 12 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 13 | NA | 1 | 0 | 0 | 0 | 0 |
| Bunglow no 14 | NA | 1 | 0 | 0 | 0 | 0 |
| Bunglow no 15 | NA | 1 | 0 | 0 | 0 | 0 |
| Bunglow no 16 | NA | 1 | 0 | 0 | 0 | 0 |
| Bunglow no 17 | NA | 1 | 0 | 0 | 0 | 0 |
| Bunglow no 18 | NA | 1 | 0 | 0 | 0 | 0 |
| Bunglow no 22 | NA | 1 | 0 | 0 | 0 | 0 |
| Bunglow no 19 | NA | 1 | 0 | 0 | 0 | 0 |
| Bunglow no 20 | NA | 1 | 0 | 0 | 0 | 0 |
| Bunglow no 21 | NA | 1 | 0 | 0 | 0 | 0 |
| Bunglow no 23 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 24 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 25 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 26 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 27 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 28 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 29 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 31 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 32 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 33 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 34 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 35 | NA | 2 | 0 | 0 | 0 | 0 |
| Bunglow no 36 | NA | 2 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 27 May 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 35 buildings; the table lists the first 20.
313 of 385 construction stages are filed complete across 35 buildings. The stage furthest along is Podiums (if any), at 0%.
Bunglow no 182%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Bunglow no 282%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Bunglow no 382%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Bunglow no 482%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Bunglow no 582%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Bunglow no 682%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Bunglow no 782%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Bunglow no 882%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Bunglow no 973%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Bunglow no 1082%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Bunglow no 1182%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Bunglow no 1282%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Bunglow no 1382%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Bunglow no 1482%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Bunglow no 1573%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Bunglow no 1682%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Bunglow no 1782%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Bunglow no 1882%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Bunglow no 2282%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Bunglow no 1982%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 27 May 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 60% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed35
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| Bunglow no 1 | 1 | 1 |
| Bunglow no 2 | 1 | 1 |
| Bunglow no 3 | 1 | 1 |
| Bunglow no 4 | 1 | 1 |
| Bunglow no 5 | 1 | 1 |
| Bunglow no 6 | 1 | 1 |
| Bunglow no 7 | 1 | 1 |
| Bunglow no 8 | 1 | 1 |
| Bunglow no 9 | 1 | 1 |
| Bunglow no 10 | 1 | 1 |
| Bunglow no 11 | 1 | 1 |
| Bunglow no 12 | 1 | 1 |
| Bunglow no 13 | 1 | 1 |
| Bunglow no 14 | 1 | 1 |
| Bunglow no 15 | 1 | 1 |
| Bunglow no 16 | 1 | 1 |
| Bunglow no 17 | 1 | 1 |
| Bunglow no 18 | 1 | 1 |
| Bunglow no 22 | 1 | 1 |
| Bunglow no 19 | 1 | 1 |
| Bunglow no 20 | 1 | 1 |
| Bunglow no 21 | 1 | 1 |
| Bunglow no 23 | 1 | 1 |
| Bunglow no 24 | 1 | 1 |
| Bunglow no 25 | 1 | 1 |
| Bunglow no 26 | 1 | 1 |
| Bunglow no 27 | 1 | 1 |
| Bunglow no 28 | 1 | 1 |
| Bunglow no 29 | 1 | 1 |
| Bunglow no 31 | 1 | 1 |
| Bunglow no 32 | 1 | 1 |
| Bunglow no 33 | 1 | 1 |
| Bunglow no 34 | 1 | 1 |
| Bunglow no 35 | 1 | 1 |
| Bunglow no 36 | 1 | 1 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Anuradha Balkrishna Warudkar | PANDHARPUR | Solapur |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Khamitkar & Associates |
| Engineer | Parvez Shabbir Shaikh |
| Engineer | SK Consultants & Engineers |
| Chartered Accountant | sanjeev s kothadiya & associates |
| Chartered Accountant | Rutuja Narsingh & Associates |
| Partner | Role in project |
|---|---|
| Shri Samarth Construction | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jan 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Dec 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Jul 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 13 May 2024
Documents filed167
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 167 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Final (2).pdf | 27 May 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Form 4 Final (2).pdf | 13 May 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 11zon_merged-PDF (2)_compressed.pdf | 13 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Final.pdf | 29 Apr 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: HARIKRUPA_01_merged_11zon.pdf | 29 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Harikrupa Residency as on 31st December 2023.pdf | 5 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Harikrupa Residency as on 31st December 2023.pdf | 4 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - Harikrupa Residency FY 21-22.pdf | 11 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Harikrupa Residency FY 22-23.pdf | 11 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Harikrupa Residency as on March 2022.pdf | 7 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Harikrupa Residency as on June 2022.pdf | 7 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Harikrupa Residency as on Sept 2022.pdf | 7 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Harikrupa Residency as on December 2022.pdf | 7 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Harikrupa Residency as on March 2023.pdf | 7 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Harikrupa Residency as on June 2023.pdf | 7 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Harikrupa Residency as on Sept 2023.pdf | 7 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Harikrupa Residency as on 31st March 2022.pdf | 7 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Harikrupa Residency as on 30th June 2022.pdf | 7 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Harikrupa Residency as on 30th September 2022.pdf | 7 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Harikrupa Residency as on 31st December 2022.pdf | 7 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Harikrupa Residency as on 31st March 2023.pdf | 7 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Harikrupa Residency as on 30th June 2023.pdf | 7 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Harikrupa Residency as on 30th Sept 2023.pdf | 7 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf | 25 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf | 25 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Harikrupa Residency as on June 2022.pdf | 24 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Harikrupa Residency as on September 2022.pdf | 24 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Harikrupa Residency as on December 2022.pdf | 24 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Harikrupa Residency as on March 2022.pdf | 24 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Harikrupa Residency as on March 2023.pdf | 24 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Harikrupa Residency as on June 2023.pdf | 24 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Harikrupa Residency as on September 2023.pdf | 24 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Shri Samrth Construction - Form - 5_compressed.pdf | 20 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Harikrupa Residency Form - 5.pdf | 20 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 20 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's certificate.pdf | 20 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: quality assurance certificate.pdf | 20 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: quality assurance 1.pdf | 9 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form no 5.pdf | 9 Oct 2022 |
| Building plan approvalFile: plan 3_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 4_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 5_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 6_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 7_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 8_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 9_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 10_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 12_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 13_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 14_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 15_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 16_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: cc 18_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 19_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 20_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 23_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 24_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 26_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 27_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 29_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 33_compressed.pdf | 6 Jul 2022 |
| Building plan approvalFile: plan 36_compressed.pdf | 6 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: plan 3_compressed.pdf | 6 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: plan 4_compressed.pdf | 6 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: plan 5_compressed.pdf | 6 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: plan 6_compressed.pdf | 6 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: plan 7_compressed.pdf | 6 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: plan 8_compressed.pdf | 6 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: plan 9_compressed.pdf | 6 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: plan 10_compressed.pdf | 6 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: plan 12_compressed.pdf | 6 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: plan 13_compressed.pdf | 6 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: plan 14_compressed.pdf | 6 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: plan 15_compressed.pdf | 6 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: plan 16_compressed.pdf | 6 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: cc 18_compressed.pdf | 6 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: plan 19_compressed.pdf | 6 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: plan 20_compressed.pdf | 6 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: plan 23_compressed.pdf | 6 Jul 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: plan 24_compressed.pdf | 6 Jul 2022 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Harikrupa HeightsP52600050906 | LOKHANDE WASTI, Solapur | 25 | May 2023 | Ongoing | Dec 2026 | Not due yet |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Solapur
Computed across the 550+ Solapur projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 167 filed documents as one ZIP, foldered, with a manifest
Keep Harikrupa residency on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near lokhande vasti550+ in Solapur
CHHORIYA TOWNSHIP WAKHARI PANDHARPUR PHASE 3
Chhoriya Properties And Development Compan
Chhoriya Township Wakhari Pandharpur Phase 2
Chhoriya Properties And Development Compan
Chhoriya Residency - Pandharpur
Dhariwal And Chhoriya Developers LLP
CENTER-PRIDE
AMOL DATTATRAY NAGTILAK
Aarambha Residency
Aarambha Residency
TIRUPATI PURAM
TIRUPATI CONSTRUCTION PRAMOTERS AND DEVELO
See every Solapur project, with the district possession charts
Builder: Shri Samarth Construction
Shri Samarth Construction has 3 registrations on MahaRERA, including Harikrupa residency and Harikrupa Heights. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Solapur district page.
Frequently asked questions
What are my rights if Harikrupa residency is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Harikrupa residency?
The registered promoter entity is Shri Samarth Construction, a partnership as per the filing. Its GSTIN 27AELFS4726A1Z2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Harikrupa residency?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Harikrupa residency?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Harikrupa residency?
The professionals named in the filing: Architect: Khamitkar & Associates; Engineer: Parvez Shabbir Shaikh; Engineer: SK Consultants & Engineers; Chartered Accountant: sanjeev s kothadiya & associates; Chartered Accountant: Rutuja Narsingh & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Harikrupa residency?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback