Home / Browse projects / Mumbai Suburban, Maharashtra / Hari Om CHS Proposed

Registration lapsed No litigation declared Others project

Hari Om CHS Proposed

By Hari Om Developers

RG-MH-94060 · RERA P51800010174 · Last updated on MahaRERA portal: 3 Sep 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 15 months past the filed date
  • 6 complaints at MahaRERA
  • Completion date moved by 42 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jul 2025Possession promised15 months past this date
3 of 11Construction stages donefurthest along: Excavation, 90%
6Complaints at MahaRERAon this registration
Jump to the 31 documents Report an error

Hari Om CHS Proposed is a Others project by Hari Om Developers in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800010174 on 24 Aug 2017. Possession was promised by 31 Jul 2025 and is now 15 months past that date. The completion date has moved by 42 months from the original filing. 6 complaints are on record with the regulator.

At a glance

Project

  • NameHari Om CHS Proposed
  • TypeOthers
  • Location
    • Magra
    • Andheri East
    • Andheri
    • Mumbai Suburban
    • 400069
  • Pincode400069
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800010174
  • ReraGenie IDRG-MH-94060

Builder

  • NameHari Om Developers
  • Entity typePartnership
  • PartnersHansraj Arjan Patel, Dilipkumar Hansraj Patel, Hiralal H Patel, Hiten Devshi Patel, Mahendra Hiralal Patel, Ramesh Hansrajbhai Patel, Devshi Arjan Patel, Ramkumar Kadedin Gupta, Dineshkumar Kadedin Gupta, Santradevi Sangamlal Gupta
  • Other registrations9 more →
  • Completed6 of 10
  • No longer live1 lapsed, de-registered or revoked

Key dates

15 months past promisethis monthRegisteredAug 2017First promiseJan 2022Revised toJul 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Aug 2017
  • Promised completion31 Jul 2025
  • Revised completionRevised to 31 Jul 2025 (originally 30 Jan 2022)
  • Buildings1 building record
  • Documents filed31 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Hari Dham IINA130000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Sep 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 90%.

Hari Dham II: 61% average across the applicable activities

ActivityProgress
Excavation90%
Basement (if any)100%
Podiums (if any)50%
Plinth100%
Stilt Floor100%
Slabs of Super Structure60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 3 Sep 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed33

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots33
Open Space33

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,420 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI13548.95
Proposed, not sanctioned13,549 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBorivali East Mumbai

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVivek Bhole Architects Pvt Ltd
EngineerChakor Raul
Chartered AccountantHaresh Dhaduk & Associates
PartnerRole in project
Hari Om Developers-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800012196Jan 2022 → Jul 2025

Reason as filed by the promoterDetail reason for delay of the project is uploaded in other documents.

Litigation declared1

CaseCourtStatus
2272/2014City Civil CourtAdd Intrim Relief

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC006000000000973Ashok Kumar PasiHari Om Developers04/10/2017
CC006000000078308ASGARI GINWALAHARI OM DEVELOPERS01/03/2019
CC006000000197199Asgari F GinwalaHari Om Developers08/06/2021
CC006000000198113ABBAS YAKUB BALUWALAHARIOM DEVELOPERS26/08/2021
CC006000000198114ABBAS YAKUB BALUWALAHARIOM DEVELOPERS26/08/2021
CC006000000209370ALI AKBAR MANTRIHARIOM DEVELOPERS11/12/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed31

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CERSAI detailsFile: CERSAI Search Report.pdf3 Sep 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format 'A'.pdf3 Sep 2022
Deviation Report with respect to Allotment letterFile: Draft Allottment Letter.pdf3 Sep 2022
Declaration about Commencement CertificateFile: Declaration about CC.pdf14 Aug 2022
Disclosure of sold/ booked inventoryFile: Disclosed flat.pdf14 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form-5.pdf14 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: Amended CC.pdf1 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 A Quality Assurace Certificate_0001.pdf24 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 A Quality Assurace Certificate_0001.pdf24 Jun 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Flat Inventory.pdf14 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5-2018-19.pdf14 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5-2019-20.pdf14 Aug 2021
Certificates of CA (Form 5)File: Form 5 Hari Om-min.pdf18 Apr 2019
OtherFile: LC SUIT NO 2272 OF 2014.pdf19 Dec 2017
Building plan approvalFile: IOD Building No 6.pdf4 Aug 2017
Building plan approvalFile: Sale Bldg No 6 Amend.pdf4 Aug 2017
Building plan approvalFile: Sale Bldg No 6 Plan.pdf4 Aug 2017
Layout approvalFile: Layout Approval.pdf4 Aug 2017
PAN CardFile: Pan Card.pdf4 Aug 2017
Copy of the legal title reportFile: Title Report.pdf4 Aug 2017
Details of encumbrancesFile: No encumbrances Letter.pdf4 Aug 2017
Copy of Layout Approval (in case of layout)File: Layout Approval.pdf4 Aug 2017
Building Plan Approval (IOD)File: IOD Building No 6.pdf4 Aug 2017
Building Plan Approval (IOD)File: Sale Bldg No 6 Amend.pdf4 Aug 2017
Building Plan Approval (IOD)File: Sale Bldg No 6 Plan.pdf4 Aug 2017
Commencement Certificates / NA Order for plotted developmentFile: CC Building No 6.pdf4 Aug 2017
Declaration in FORM BFile: Form B Declaration.pdf4 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf4 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf4 Aug 2017
Certificates of CA (Form 3)File: CA Certificate.pdf4 Aug 2017
Proforma of Allotment letterFile: Sale Agreement draft.pdf4 Aug 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 42 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Hari Om CHS Proposed on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Andheri East6,700+ in Mumbai Suburban

2 kmHari Om CHS ProposedCompleted 112Lapsed / revoked 58Other 77Dot size: filed unitsN

Filed coordinates, straight-line distance. 247 registered projects within 2 km.

Builder: Hari Om Developers

HARI OM DEVELOPERS has 10 registrations on MahaRERA, including KULSWAMINI HEIGHTS and Hari Om CHS Proposed. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Hari Om CHS Proposed shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Hari Om CHS Proposed is delayed beyond 31 Jul 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Hari Om CHS Proposed?

The registered promoter entity is Hari Om Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Hari Om CHS Proposed?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Hari Om CHS Proposed?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Hari Om CHS Proposed?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Hari Om CHS Proposed?

The professionals named in the filing: Architect: Vivek Bhole Architects Pvt Ltd; Engineer: Chakor Raul; Chartered Accountant: Haresh Dhaduk & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Hari Om CHS Proposed?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Hari Om CHS Proposed. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Hari Om CHS Proposed to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.