Home / Browse projects / Nashik, Maharashtra / HARI ANANDVAN

Registration lapsed No litigation declared Residential / Group Housing project

HARI ANANDVAN

By ISHAAN ENTERPRISES

RG-MH-36093 · RERA P51600015577 · Last updated on MahaRERA portal: 29 Apr 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 5 complaints at MahaRERA
  • Completion date moved by 48 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
35 of 88Construction stages doneacross 8 buildings; furthest along: Slabs of Super Structure, 75%
5Complaints at MahaRERAon this registration
Jump to the 88 documents Report an error

HARI ANANDVAN is a Residential / Group Housing project by ISHAAN ENTERPRISES in Nashik, Maharashtra, registered with MahaRERA as P51600015577 on 8 Mar 2018. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 48 months from the original filing. 5 complaints are on record with the regulator.

At a glance

Project

  • NameHARI ANANDVAN
  • TypeResidential / Group Housing
  • Location
    • Lam road
    • Deolali gaon
    • Belatgavhan
    • Nashik
    • 422401
  • Pincode422401
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600015577
  • ReraGenie IDRG-MH-36093

Builder

  • NameISHAAN ENTERPRISES
  • Entity typePartnership
  • PartnerNaresh Jagumal Karda

Key dates

10 months past promisethis monthRegisteredMar 2018First promiseDec 2021Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on8 Mar 2018
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Dec 2021)
  • Buildings8 building records
  • Documents filed88 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A TypeNA20000
B TypeNA50000
C TYpeNA50000
D TypeNA50000
E TypeNA50000
F TYpeNA50000
G TypeNA40000
H TypeNA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building8

As on 29 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

35 of 88 construction stages are filed complete across 8 buildings. The stage furthest along is Slabs of Super Structure, at 75%.

A Type57%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises25%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
B Type0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C TYpe91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
D Type89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%
E Type27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
F TYpe27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
G Type48%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
H Type9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes100%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes40%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes50%

Parking filed78

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots78
Closed/Covered32
Open Space46
BuildingClosed/CoveredOpen SpaceTotal
A Type01616
B Type6612
C TYpe6612
D Type6612
E Type6612
F TYpe6612
G Type101
H Type101

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,784 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3892.14
Proposed, not sanctioned3,868 sq m
Buildings approved8
Buildings sanctioned8

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDeolali Camp, Nashik-422401

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDHARAM PAPNEJA
PartnerRole in project
ISHAAN ENTERPRISES-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600013489Dec 2021 → Dec 2025

Reason as filed by the promoterConstruction work being delated due to unavoidable reason

EXT51600011267Dec 2021 → Dec 2022

Reason as filed by the promoterThere has been delay in construction activities due to some unavoidable reasons.

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC001000000010175LOUISA MARTIN BRITTO AND JOSEPHA MARIA BRITTONaresh Karda partner of Ishaan Enterprises08/03/2021
CC001000000020261NAVEEN MANOHAR NAGPALISHAAN ENTERPRISES04/05/2022
CC001000000030266NAVAL MANOHARLAL NAGPALISHAAN ENTERPRISES16/06/2022
CC001000000090416NAVEEN MANOHAR NAGPALISHAN ENTERPRISES05/12/2023
CC12503988POORAV DINESH ZAVERIISHAAN ENTERPRISES12/11/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Mar 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Feb 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 May 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Feb 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed88

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: HARI ANANDVAN.pdf29 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Aanandvan.pdf26 Apr 2024
Details of encumbrancesFile: Encumbrance certificate (1)_page-0001.pdf24 Feb 2024
Details of encumbrances concerned to FinanceFile: Encumbrance certificate finance_page-0001.pdf24 Feb 2024
Details of encumbrances concerned to LegalFile: Encumbrance certificate finance_page-0001.pdf24 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank acc details_page-0001.pdf24 Feb 2024
Deviation Report with respect to Allotment letterFile: Encumbrance certificate-model allotment letter_page-0001.pdf24 Feb 2024
Deviation Report with respect to model copy of AgreementFile: Encumbrance certificate-model agreement_page-0001.pdf24 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Anandvan.pdf17 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Anandvan.pdf17 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Anandvan.pdf17 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Anandvan.pdf17 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Anandvan.pdf17 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Anandvan.pdf17 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Hari Anandvan.pdf17 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Anandvan.pdf17 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Anandvan.pdf17 Feb 2024
Disclosure of sold/ booked inventoryFile: HARI ANANDVAN.pdf17 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Anandvan.pdf17 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Anandvan.pdf17 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Anandvan.pdf17 Feb 2024
Disclosure of sold/ booked inventoryFile: Hari Anandvan.pdf17 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: ANANDVAN3006 (2).pdf19 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: ANANDVAN3009 (2).pdf19 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Aanandvan3112.pdf19 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf16 Jan 2023
Disclosure of sold/ booked inventoryFile: anandvan3006.pdf12 Jan 2023
Disclosure of sold/ booked inventoryFile: anandvan3009.pdf12 Jan 2023
Disclosure of sold/ booked inventoryFile: anandvan3112.pdf12 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5- Rera Audit Ishan.pdf21 Dec 2022
Disclosure of sold/ booked inventoryFile: HARI ANANDVAN.pdf29 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: hari Anandvan.pdf6 Apr 2022
Disclosure of sold/ booked inventoryFile: Sold unsold -Anandvan.pdf26 Jan 2022
CERSAI detailsFile: CERSAI_Search_Report_200228817292_For_Asset_Based_Search_ANANDVAN.pdf26 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Anandvan 2A.pdf18 Jan 2022
Disclosure of sold/ booked inventoryFile: HARI ANANDVAN.pdf18 Jan 2022
Disclosure of sold/ booked inventoryFile: HARI ANANDVAN (1).pdf15 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Aanandvan.pdf13 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM-2A - 19-20-Aanandvan (1).pdf7 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM-2A - 20-21-Anandvan.pdf7 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Hari Anandvan.pdf7 Oct 2021
Disclosure of sold/ booked inventoryFile: ANANDVAN INFRA.pdf7 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5-Hari Anandvan-2020-21.pdf29 Sep 2021
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CERTIFICATE-Anandvan.pdf16 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5-Hari Anandvan-2019-20.pdf1 Oct 2020
Annual Audit Report of Statutory CA (Form 5)File: Form 5-Hari Anandvan-2019-20.pdf29 Sep 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5-Hari Anandvan-2018-19.pdf29 Sep 2020
Building plan approvalFile: ANANDVAN-1-FINAL.pdf16 May 2020
Building plan approvalFile: ANANDVAN-2-FINAL.pdf16 May 2020
Building Plan Approval (IOD)File: ANANDVAN-1-FINAL.pdf16 May 2020
Building Plan Approval (IOD)File: ANANDVAN-2-FINAL.pdf16 May 2020
Annual Audit Report of Statutory CA (Form 5)File: Form 5-Hari Anandvan.pdf30 Sep 2019
Annual Audit Report of Statutory CA (Form 5)File: Form 5-Hari Anandvan.pdf28 Sep 2019
Proforma of Allotment letterFile: Anand-Ishan-Draft agreement.pdf20 Feb 2019
Building plan approvalFile: 1 (7)-ilovepdf-compressed (1).pdf5 Oct 2018
Building plan approvalFile: 2 (3)-ilovepdf-compressed (1).pdf5 Oct 2018
Building plan approvalFile: 3-ilovepdf-compressed (4) (1).pdf5 Oct 2018
Building plan approvalFile: 4-ilovepdf-compressed (1).pdf5 Oct 2018
Building plan approvalFile: 5-ilovepdf-compressed (2) (1).pdf5 Oct 2018
Building plan approvalFile: 6-ilovepdf-compressed (1).pdf5 Oct 2018
Building plan approvalFile: 7-ilovepdf-compressed (1) (2).pdf5 Oct 2018
Building plan approvalFile: 8-ilovepdf-compressed (1).pdf5 Oct 2018
Building Plan Approval (IOD)File: 1 (7)-ilovepdf-compressed (1).pdf5 Oct 2018
Building Plan Approval (IOD)File: 2 (3)-ilovepdf-compressed (1).pdf5 Oct 2018
Building Plan Approval (IOD)File: 3-ilovepdf-compressed (4) (1).pdf5 Oct 2018
Building Plan Approval (IOD)File: 4-ilovepdf-compressed (1).pdf5 Oct 2018
Building Plan Approval (IOD)File: 5-ilovepdf-compressed (2) (1).pdf5 Oct 2018
Building Plan Approval (IOD)File: 6-ilovepdf-compressed (1).pdf5 Oct 2018
Building Plan Approval (IOD)File: 7-ilovepdf-compressed (1) (2).pdf5 Oct 2018
Building Plan Approval (IOD)File: 8-ilovepdf-compressed (1).pdf5 Oct 2018
Building plan approvalFile: 1.PDF3 Mar 2018
Building plan approvalFile: 2.PDF3 Mar 2018
Building plan approvalFile: iod-1.pdf3 Mar 2018
Building plan approvalFile: iod-2.pdf3 Mar 2018
Copy of the legal title reportFile: Anand-Ishan-Title report.pdf3 Mar 2018
Building Plan Approval (IOD)File: 1.PDF3 Mar 2018
Building Plan Approval (IOD)File: 2.PDF3 Mar 2018
Building Plan Approval (IOD)File: iod-1.pdf3 Mar 2018
Building Plan Approval (IOD)File: iod-2.pdf3 Mar 2018
Certificates of CA (Form 3)File: Anand-Ishan-CA Certificate.pdf3 Mar 2018

How this compares with Nashik

10%of Nashik projects moved their completion datethis one moved by 48 months
19%of Nashik registrations have lapsed or been cancelledthis one is among them

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep HARI ANANDVAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Deolali gaon4,100+ in Nashik

Builder: ISHAAN ENTERPRISES

ISHAAN ENTERPRISES has 1 registration on MahaRERA, including HARI ANANDVAN. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What does it mean that HARI ANANDVAN shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if HARI ANANDVAN is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of HARI ANANDVAN?

The registered promoter entity is ISHAAN ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in HARI ANANDVAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against HARI ANANDVAN?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for HARI ANANDVAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at HARI ANANDVAN?

The professionals named in the filing: Architect: DHARAM PAPNEJA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HARI ANANDVAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HARI ANANDVAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HARI ANANDVAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.