Home / Browse projects / Pune, Maharashtra / HAPPY MORNING

Completed No litigation declared Residential / Group Housing project

HAPPY MORNING

By SANDIP BALKRISHNA BANGAR

RG-MH-53717 · RERA P52100051758 · Last updated on MahaRERA portal: 10 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 11 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Feb 2026Possession promisedregistration recorded completed
54 of 88Construction stages doneacross 8 buildings; furthest along: Basement (if any), 0%
22 of 40Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 122 documents Report an error

HAPPY MORNING is a Residential / Group Housing project by SANDIP BALKRISHNA BANGAR in Pune, Maharashtra, registered with MahaRERA as P52100051758 on 27 Jun 2023. The registration is recorded completed; possession was promised by 21 Feb 2026. The completion date has moved by 11 months from the original filing. 18 of the 40 units on this registration are recorded sold or booked, and 54 of 88 construction stages are filed complete.

At a glance

Project

  • NameHAPPY MORNING
  • TypeResidential / Group Housing
  • Location
    • NARAYANGAON
    • Junnar
    • Pune
    • 410504
  • Pincode410504
  • RERA no.P52100051758
  • ReraGenie IDRG-MH-53717

Builder

  • NameSANDIP BALKRISHNA BANGAR
  • Entity typeIndividual

Key dates

this monthRegisteredJun 2023First promiseMar 2025Revised toFeb 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on27 Jun 2023
  • Promised completion21 Feb 2026
  • Revised completionRevised to 21 Feb 2026 (originally 22 Mar 2025)
  • Buildings8 building records
  • Documents filed122 files

Current status

45%18 of 40 units booked
75.0%Work done, per cost certificate

Figures as on 10 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A SERIES ROW HOUSENA22707
A PLUS SERIES ROW HOUSENA22606
B SERIES ROW HOUSENA22202
B PLUS SERIES ROW HOUSENA22505
C SERIES ROW HOUSENA22101
D SERIES ROW HOUSENA22303
BUILDING ANA6515015
BUNGLOWNA33101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building8

As on 10 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

54 of 88 construction stages are filed complete across 8 buildings. The stage furthest along is Basement (if any), at 0%.

A SERIES ROW HOUSE55%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A PLUS SERIES ROW HOUSE55%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B SERIES ROW HOUSE55%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B PLUS SERIES ROW HOUSE55%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C SERIES ROW HOUSE55%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
D SERIES ROW HOUSE55%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING A82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUNGLOW82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 10 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed108

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots108
Open Space108
BuildingOpen SpaceTotal
A SERIES ROW HOUSE1414
A PLUS SERIES ROW HOUSE1212
B SERIES ROW HOUSE44
B PLUS SERIES ROW HOUSE1010
C SERIES ROW HOUSE22
D SERIES ROW HOUSE66
BUILDING A5050
BUNGLOW1010

Land and ownership14

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area6,441 sq m
Land owned byThe promoter, with other names on the file
Named landowners14
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on24 Sep 2025
LandownerVillageDistrict
ABHISHEK KHANDU ERANDEKolharwadiPune
MANISHA KHANDU ERANDEKolharwadiPune
SWAPNIL DHONDIBHAU MATEBelhePune
AJAY DHOMDIBHAU MATEBelhePune
BALASAHEB KERUBHAU BHUJBALNarayangaonPune
SATISH JAYWANT PATENarayangaonPune
SAVITRI DASHRATH BHUJBALNarayangaonPune
SUDHIR DASHRATH BHUJBALNarayangaonPune
DEEPAK DASHRATH BHUJBALNarayangaonPune
ALKA GULAB MANDLIKNarayangaonPune
BABAN GANPAT BHUJBALNarayangaonPune
CHIMAJI GANPAT BHUJBALNarayangaonPune
BALASAHEB alias BHIMAJI VITTHAL BHUJBALNarayangaonPune
NARMADABAI VITTHAL BHUJBALNarayangaonPune

Approvals and building plan

Sanctioning authorityTOWN PLANING AND VALUATION DEPARTMENT PUNE
Permissible FSI6104.64
Proposed, not sanctioned4,413 sq m
Buildings approved8
Buildings sanctioned8

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSURVEY NO 657/B BHALG, NEAR REGISTER OFFICE, NARAYANGAON TAL JUNNAR DIST PUNE - 410504
Estimated costRs 7.80 cr
Cost incurredRs 5.85 cr
Work done75.0%
BuildingWingEstimatedIncurred
BUILDING ANARs 2.05 crRs 1.54 cr
A SERIES ROW HOUSENARs 1.44 crRs 1.08 cr
A PLUS SERIES ROW HOUSENARs 1.24 crRs 93.22 lakh
B PLUS SERIES ROW HOUSENARs 81.42 lakhRs 61.06 lakh
D SERIES ROW HOUSENARs 68.36 lakhRs 51.27 lakh
BUNGLOWNARs 65.21 lakhRs 48.90 lakh
-NARs 43.45 lakhRs 32.59 lakh
B SERIES ROW HOUSENARs 31.88 lakhRs 23.91 lakh
C SERIES ROW HOUSENARs 16.28 lakhRs 12.21 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKUNAL SUNIL CHORDIA
EngineerJANAK GANESH LOHOT
EngineerSURESH UTTAM GADGE
Chartered AccountantHBAA AND COMPANY
Chartered AccountantPRAVIN EKNATH PISE
PartnerRole in project
SANDIP BALKRISHNA BANGAR-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100027890Mar 2025 → Feb 2026

Reason as filed by the promoterFinancial constraints, Shortage of labour, etc. difficulties faced by the developer, hence project could not be completed within the stipulated time.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 May 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 May 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 May 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 May 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed122

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 122 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2023-2024)File: From 2A FY 23-24.pdf10 May 2026
Form 2A (FY 2024-2025)File: From 2A FY 24-25.pdf10 May 2026
Form 2A (FY 2025-2026)File: From 2A FY 25-26.pdf10 May 2026
Form 5 (FY 2025-2026)File: FORM 5 FY 2025-26.pdf5 May 2026
Withdrawal Update Form 1File: FORM 1 FY 25-26 QTR-1.pdf2 May 2026
Withdrawal Update Form 1File: FORM 1 FY 25-26 QTR-2.pdf2 May 2026
Withdrawal Update Form 1File: FORM 1 FY 25-26 QTR-3.pdf2 May 2026
Withdrawal Update Form 1File: FORM 1 FY 25-26 QTR-4.pdf2 May 2026
Withdrawal Update Form 2File: FORM 2 FY 25-26 QTR-1.pdf2 May 2026
Withdrawal Update Form 2File: FORM 2 FY25-26 QTR-2.pdf2 May 2026
Withdrawal Update Form 2File: FORM 2 FY 25-26 QTR-3.pdf2 May 2026
Withdrawal Update Form 2File: FORM 2 FY 25-26 QTR-4.pdf2 May 2026
Withdrawal Update Form 3File: FORM 3 FY 25-26 QTR-1.pdf2 May 2026
Withdrawal Update Form 3File: FORM 2 FY25-26 QTR-2.pdf2 May 2026
Withdrawal Update Form 3File: FORM 3 FY 25-26 QTR-3.pdf2 May 2026
Withdrawal Update Form 3File: FORM 3 FY 25-26 QTR-4.pdf2 May 2026
Occupational CertificateFile: Occupancy Certificate.pdf2 May 2026
Form 1File: FORM 1 FY 24-25 QTR-4.pdf15 Oct 2025
Form 2File: FORM 2 FY 24-25 QTR-4.pdf15 Oct 2025
Form 3File: FORM 3 FY 24-25 QTR-4.pdf15 Oct 2025
Disclosure of Sold and Booked InventoryFile: BOOKED SOLD UNSOLD DETAILS - FY 24-25 QTR-4.pdf15 Oct 2025
Form 5 (FY 2023-2024)File: FORM 5 FY 23-24.pdf30 Sep 2025
Form 5 (FY 2024-2025)File: FORM 5 FY 2024-25.pdf30 Sep 2025
Form 1File: FORM 1 - QTR-1.pdf24 Sep 2025
Form 2File: FORM 2 - QTR-1.pdf24 Sep 2025
Form 3File: FORM 3 - QTR-1.pdf24 Sep 2025
Disclosure of Sold and Booked InventoryFile: BOOKED SOLD UNSOLD DETAILS - QTR-1.pdf24 Sep 2025
Form 1File: FORM 1 - QTR-2.pdf24 Sep 2025
Form 2File: FORM 2 - QTR-2.pdf24 Sep 2025
Form 3File: FORM 3 - QTR-2 30-09-23.pdf24 Sep 2025
Disclosure of Sold and Booked InventoryFile: BOOKED SOLD UNSOLD DETAILS - QTR-2.pdf24 Sep 2025
Form 1File: FORM 1 QTR-3.pdf24 Sep 2025
Form 2File: FORM 2 QTR-3.pdf24 Sep 2025
Form 3File: FORM 3 QTR-3.pdf24 Sep 2025
Disclosure of Sold and Booked InventoryFile: BOOKED SOLD UNSOLD DETAILS - QTR-3.pdf24 Sep 2025
Form 1File: FORM 1 - QTR-4.pdf24 Sep 2025
Form 2File: FORM 2 - QTR-4.pdf24 Sep 2025
Form 3File: FORM 3 - QTR-4.pdf24 Sep 2025
Disclosure of Sold and Booked InventoryFile: BOOKED SOLD UNSOLD DETAILS - QTR-4.pdf24 Sep 2025
Form 1File: FORM 1 FY 24-25 QTR-1.pdf24 Sep 2025
Form 2File: FORM 2 FY 24-25 QTR-1.pdf24 Sep 2025
Form 3File: FORM 3 FY 24-25 QTR-1.pdf24 Sep 2025
Disclosure of Sold and Booked InventoryFile: BOOKED SOLD UNSOLD DETAILS - FY 24-25 QTR-1.pdf24 Sep 2025
Form 1File: FORM 1 - QTR-3 - 30-09-24.pdf24 Sep 2025
Form 2File: FORM 2 - QTR-3 - 30-09-24.pdf24 Sep 2025
Form 3File: FORM 3 - QTR-3 - 30-09-24.pdf24 Sep 2025
Disclosure of Sold and Booked InventoryFile: BOOKED SOLD UNSOLD DETAILS - FY 24-25 QTR-2.pdf24 Sep 2025
Form 1File: FORM 1 - 31-12-2024.pdf24 Sep 2025
Form 2File: FORM 2 - 31-12-2024.pdf24 Sep 2025
Form 3File: FORM 3 - 31-12-2024.pdf24 Sep 2025
Disclosure of Sold and Booked InventoryFile: BOOKED SOLD UNSOLD DETAILS - FY 24-25 QTR-3.pdf24 Sep 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 31-12-2024.pdf24 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - 31-12-2024_compressed.pdf24 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - 31-12-2024.pdf24 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - QTR-3.pdf31 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - QTR-3 - 30-09-23.pdf31 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - QTR-3 - 30-09-24.pdf31 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - QTR-3 30-09.pdf31 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf27 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - 31-12-23.pdf27 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 30-09-2023.pdf27 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 31-12-2023.pdf27 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 31-03-2024.pdf27 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 30-06-2024.pdf27 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 FY 23-24.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 2023- QTR-3 (JULY-SEP 2023).pdf12 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 2023- QTR-4 (OCT-DEC 2023).pdf12 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 2024- QTR-1 (JAN-MAR 2024).pdf12 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 2024- QTR-2 (APR-JUN 2024).pdf12 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 2023- QTR-3 (JULY-SEP 2023)_compressed.pdf12 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 2024- QTR-1 (JAN-MAR 2024).pdf12 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 2024- QTR-2 (APR-JUN 2024).pdf12 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 2023- QTR-3 (JULY-SEP 2023)_compressed.pdf12 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 2024- QTR-1 (JAN-MAR 2024)_compressed.pdf12 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 2024- QTR-2 (APR-JUN 2024).pdf12 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - QTR 1.pdf8 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - QTR-1.pdf8 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - QTR-1_compressed.pdf8 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - QTR-2.pdf6 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - QTR-4.pdf6 Jun 2024

How this compares with Pune

45%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 11 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep HAPPY MORNING on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NARAYANGAON13,700+ in Pune

Builder: SANDIP BALKRISHNA BANGAR

SANDIP BALKRISHNA BANGAR has 1 registration on MahaRERA, including HAPPY MORNING. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if HAPPY MORNING is delayed beyond 21 Feb 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of HAPPY MORNING?

The registered promoter entity is SANDIP BALKRISHNA BANGAR, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in HAPPY MORNING?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for HAPPY MORNING?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at HAPPY MORNING?

The professionals named in the filing: Architect: KUNAL SUNIL CHORDIA; Engineer: JANAK GANESH LOHOT; Engineer: SURESH UTTAM GADGE; Chartered Accountant: HBAA AND COMPANY; Chartered Accountant: PRAVIN EKNATH PISE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HAPPY MORNING?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HAPPY MORNING. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HAPPY MORNING to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.