Home / Browse projects / Pune, Maharashtra / Happiness Hub - Varve

Completed No litigation declared Residential / Group Housing project

Happiness Hub - Varve

By PARANJAPE SCHEMES (CONSTRUCTION) LTD

RG-MH-02458 · RERA P52100000303 · Last updated on MahaRERA portal: 27 Feb 2025

Source: official MahaRERA filing

Red flags

  • 22 complaints at MahaRERA
  • Completion date moved by 60 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2025Possession promisedregistration recorded completed
94 of 143Construction stages doneacross 13 buildings; furthest along: External plumbing and external plaster, 99%
22Complaints at MahaRERAon this registration
Jump to the 60 documents Report an error

Happiness Hub - Varve is a Residential / Group Housing project by PARANJAPE SCHEMES (CONSTRUCTION) LTD in Pune, Maharashtra, registered with MahaRERA as P52100000303 on 15 Jul 2017. The registration is recorded completed; possession was promised by 28 Mar 2025. The completion date has moved by 60 months from the original filing. 22 complaints are on record with the regulator.

At a glance

Project

  • NameHappiness Hub - Varve
  • TypeResidential / Group Housing
  • Location
    • Mumbai Bangalore Highway
    • Varve
    • Varve Kh.
    • Bhor
    • Pune
    • 412206
  • Pincode412206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100000303
  • ReraGenie IDRG-MH-02458

Builder

  • NamePARANJAPE SCHEMES (CONSTRUCTION) LTD
  • Entity typeCompany
  • ChairpersonSHRIKANT PURUSHOTTAM PARANJAPE
  • Managing DirectorSHASHANK PURUSHOTTAM PARANJAPE
  • Other registrations28 more →
  • Completed15 of 29
  • No longer live7 lapsed, de-registered or revoked
  • Declared earlier projects17 →

Key dates

this monthRegisteredJul 2017First promiseMar 2020Revised toMar 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on15 Jul 2017
  • Promised completion28 Mar 2025
  • Revised completionRevised to 28 Mar 2025 (originally 31 Mar 2020)
  • Buildings13 building records
  • Documents filed60 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA130000
FNA130000
GNA130000
HNA130000
INA130000
JNA130000
KNA130000
LNA130000
MNA130000
ONA130000
PNA130000
QNA130000
RNA130000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building13

As on 27 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

94 of 143 construction stages are filed complete across 13 buildings. The stage furthest along is External plumbing and external plaster, at 99%.

A89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%
F89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises97%
Sanitary Fittings within the flats / premises97%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.97%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.97%
G90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises97%
Sanitary Fittings within the flats / premises97%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.97%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.97%
H90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises97%
Sanitary Fittings within the flats / premises97%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.97%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.97%
I91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%
J83%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%
K90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%
L86%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
M90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
O87%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
P91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Q90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
R90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 27 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes98%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes95%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes90%
Open ParkingYes100%
CLUB HOUSEYes100%

Parking filed324

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots324
Closed/Covered208
Open Space116
BuildingClosed/CoveredOpen SpaceTotal
A808
F202040
G161329
H121123
I12921
J12012
K12012
L12921
M24024
O201838
P201232
Q201232
R201232

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area49,929 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI49038.84
Proposed, not sanctioned49,039 sq m
Buildings approved13
Buildings sanctioned13

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHANDARKAR ROAD PUNE

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
PARANJAPE SCHEMES (CONSTRUCTION) LTD-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100005592Mar 2020 → Mar 2021

Reason as filed by the promoterThe Promoter has made different applications for plinth checking. Out of which, made on 16/01/2018, the Promoter obtained NOC on 01/10/2018 and thus the work for the project was delayed due to delayed receipt of plinth NOC from Competent Authority.

EXT52100011460Mar 2020 → Sep 2022

Reason as filed by the promoterSince two Covid lockdowns and migration of laborers work could not proceed .Promoter has availed loan from the Financial institution to enable to complete the project.

EXT52100027218Mar 2020 → Mar 2025

Reason as filed by the promoterAs per attachment

Complaints filed with MahaRERA22

Case no.ComplainantRespondentFiled
CC005000000064816Paranjape Schemes (Construction) Ltd.Mrs. Parveen Vikram Pattankude10/11/2020
CC005000000075178Anupa Nagnath kanakdharParanjape Schemes (Constructions) Ltd. Through its Managing Director Shashank Purushottam Paranjape07/02/2021
CC005000000198143RAJESHREE SUNIL KHAIREM/S PARANJAPE SCHEMES (CONSTRUCTION) LIMITED03/02/2023
CC005000000228404RAJENDRA MARTAND NAGAPURKARPARANJAPE SCHEMES CONSTRUCTION LTD.28/02/2023
CC005000000258997Paranjape Schemes Construction Limited Paranjape Schemes Construction LimitedSmita Mohan Jagdale15/06/2023
CC005000000259086Paranjape Schemes Construction LimitedParanjape Schemes Construction LimitedSAVITA ANIL KADAM30/06/2023
CC005000000259107Paranjape Schemes Construction Limited Paranjape Schemes Construction LimitedSagar Vilasrao Shilimkar04/07/2023
CC005000000259113Paranjape Schemes Construction Limited Paranjape Schemes Construction LimitedAnil Sudam Jadhav05/07/2023
CC005000000259202Paranjape Schemes Construction Limited Paranjape Schemes Construction LimitedCHAPALGAONKAR KALYANI SHAILENDRA27/07/2023
CC005000000269480Paranjape Schemes Construction Limited Paranjape Schemes Construction LimitedMOHINI HIMANSHU REDDY25/09/2023
CC005000000269493Paranjape Schemes Construction Limited Paranjape Schemes Construction LimitedSHRINIWASAN SHANMUGAM KOUNDER28/09/2023
CC005000000269495Paranjape Schemes Construction Limited Paranjape Schemes Construction LimitedISHITA SMITESH SHAH27/09/2023
CC005000000269496Paranjape Schemes Construction Limited Paranjape Schemes Construction LimitedUPENDRA RAMCHANDRA SHIRSIKAR27/09/2023
CC005000000290044Paranjape Schemes Construction Limited Paranjape Schemes Construction LimitedHARSHAVARDHAN BHANUDAS YADAV09/01/2024
CC005000000370949Paranjape Schemes Construction Limited Paranjape Schemes Construction LimitedANUJA NARENDRA SONAWANE16/05/2024
CC12502350PARANJAPE SCHEMES (CONSTRUCTION) LTDPOOJA SANJAY KOLSUMKAR11/07/2025
CC12502353PARANJAPE SCHEMES (CONSTRUCTION) LTDPOOJA SANJAY KOLSUMKAR11/07/2025
CC12502362PARANJAPE SCHEMES (CONSTRUCTION) LTDGHARGE HANUMANTRAO JAGANNATH11/07/2025
CC12502438PARANJAPE SCHEMES (CONSTRUCTION) LTDNITIN MADHUKAR PAWAR17/07/2025
CC12600698Marigold Co Operative Hsg Soc LtdPARANJAPE SCHEMES (CONSTRUCTION) LTD06/02/2026
CC12600705Tulip Co Operative Housing Society LimitedPARANJAPE SCHEMES (CONSTRUCTION) LTD07/02/2026
CC12600930Daffodils Co Operative Housing Society LimitedPARANJAPE SCHEMES (CONSTRUCTION) LTD19/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Apr 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jun 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 11 Jan 2025

Documents filed60

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 HH- DEC 24-uploaded-compressed.pdf27 Feb 2025
Declaration in FORM BFile: Form B Affidavit-HH-17Jan24.pdf18 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-Happiness Hub-31Dec2023.pdf18 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-Happiness Hub-30Mar2024.pdf18 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-Happiness Hub-29June2024.pdf18 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A-Fy 21-22-HH.pdf18 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A-FY 22-23-HH.pdf18 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A-FY 23-24-HH.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: Inventory Report-Happiness Hub-Dec'24-uploaded.pdf16 Jan 2025
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Certificate-Daffodils-Varve29-08-2024 FGM Bldg-uploaded.pdf11 Jan 2025
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Certificate-Rose-Varve-29-08-2024-A Bldg-uploaded.pdf11 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Society certificate Tulip-22-02-2024-HIJKL Varve HH-uploaded.pdf11 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure Inventory-Happiness Hub-Sept'24-uploaded.pdf17 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5-Happiness hub-FY' 23-24-uploaded.pdf7 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure-Happiness Hub -JUne'24-uploaded.pdf16 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3 Form 2- Happiness Hub-June'24-uploaded.pdf6 Jul 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Certificate-Marigold-HH-Varve-OPQR bldg-12Jan'24.pdf18 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2-Happiness Hub-Dec'23-uploaded.pdf5 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1-Happiness Hub-Sept23-uploaded.pdf19 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2-Happiness Hub-Sept'23-uploaded.pdf11 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5-Happiness Hub- Varve-Fy '22-23-uploaded11oct23.pdf11 Oct 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part Completion Certificate FGHI -HHVarve- 04Aug2023.pdf10 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-HHVarve-June'23-uploaded.pdf24 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2-Happiness Hub-June'23.pdf7 Jul 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Application for OC - HH-31May2023.pdf19 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3 Form 2 -Happiness Hub-Mar 2023-uploaded.pdf8 Apr 2023
Other - FinanceFile: FORM 4-Happiness Hub.pdf3 Mar 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Happiness Hub Society formation process.pdf28 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: HHubVarve-FORM 5-FY 21-22-uploaded 03Feb2023.pdf3 Feb 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: HH Completion certificate.pdf15 Nov 2022
Copy of the legal title reportFile: Title certificate 6 april 2022.pdf25 Apr 2022
Declaration about Commencement CertificateFile: Format D-Declaration of Commencement.pdf27 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A HH FY2021-22.pdf27 Jan 2022
CERSAI detailsFile: CERSAI_Report _Registration Of Security.pdf27 Jan 2022
CERSAI detailsFile: CERSAI_Report Registration Of Security_.pdf27 Jan 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf27 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Happiness Hub-min_compressed.pdf28 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 20 RERA Happiness Hub compressed.pdf1 Apr 2021
Certificates of CA (Form 5)File: Happiness HUb_Form 5_18-19.pdf7 Oct 2019
Certificates of CA (Form 5)File: Happiness Hub.pdf6 Oct 2018
Details of encumbrancesFile: Encumbrance Certificate_Corrected.pdf29 Aug 2017
Declaration in FORM BFile: Form B_Happiness Hub_Corrected.pdf29 Aug 2017
Proforma of Allotment letterFile: Allotment Ltr_Corrected_Happiness Hub.pdf29 Aug 2017
Building plan approvalFile: Happiness Hub -LAYOUT - part-1.pdf12 Jul 2017
Building plan approvalFile: Happiness Hub -LAYOUT - part-2.pdf12 Jul 2017
Layout approvalFile: Happiness Hub -LAYOUT - part-1.pdf12 Jul 2017
Layout approvalFile: Happiness Hub -LAYOUT - part-2.pdf12 Jul 2017
PAN CardFile: Directors List with PAN-Happiness Hub.pdf12 Jul 2017
Copy of Layout Approval (in case of layout)File: Happiness Hub -LAYOUT - part-1.pdf12 Jul 2017
Copy of Layout Approval (in case of layout)File: Happiness Hub -LAYOUT - part-2.pdf12 Jul 2017
Building Plan Approval (IOD)File: Happiness Hub -LAYOUT - part-1.pdf12 Jul 2017
Building Plan Approval (IOD)File: Happiness Hub -LAYOUT - part-2.pdf12 Jul 2017
Certificates of CA (Form 3)File: Happiness Hub-Form 3.pdf12 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 HAPPINESS HUB VARVE.pdf10 Jul 2017
Declaration in FORM BFile: Form B_Happiness Hub.pdf6 Jul 2017
Proforma of Allotment letterFile: Proforma_Allotment Ltr and Agreement_Happiness Hub.pdf6 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 engineer's certificate Happiness hub.pdf1 Jul 2017
Copy of the legal title reportFile: Title Report_10-03-2017 (3).pdf28 Jun 2017
Details of encumbrancesFile: Encumbrance Certificate_Happiness Hub_28-06-2017.pdf28 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: hpp cc.pdf27 Jun 2017

Promoter's earlier projects8

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

7 delivered on promise1 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
127 UPPER EASTP51800000454Andheri, Mumbai Suburban-Jul 2017CompletedJun 2024Registered original: Dec 2019Jan 1970
PRATHAM RESIDENTIAL727 SADASHIV PETH KUMTHEKAR ROAD PUNE 41103035-CompletedApr 2016Mar 2016
THE BUSINESS HUBSURVEY NO25 HISSA NO 29 HISSA NO 1 KOTHRUD PUNE 41102986-CompletedJan 2016Nov 2015
MADHUKOSH - IIISNo4 HISSA NO 2 SNO 16 AND 17 part Wadgaon khurd Tal Haveli Sinhgad road Pune258-CompletedAug 2015Aug 2015
PRATHAM COMMERCIAL727 SADASHIV PETH KUMTHEKAR ROAD PUNE 41103032-CompletedJun 2015Apr 2015
PUNARVASUPRABHAT ROAD ERANDWANE PUNE 41100410-CompletedDec 2014Late, Jun 2015
MADHUKOSH - IISNo4 HISSA NO 2 SNO 16 17 part Wadgaon khurd Tal Haveli Sinhgad road Pune150-CompletedDec 2013Oct 2013
MADHUKOSH - ISNo 4 HISSA NO 2 SNO 16 AND 17 part Wadgaon khurd Tal Haveli Sinhgad road Pune289-CompletedMar 2012Feb 2012

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 60 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Happiness Hub - Varve on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Varve13,700+ in Pune

Builder: PARANJAPE SCHEMES (CONSTRUCTION) LTD

PARANJAPE SCHEMES (CONSTRUCTION) LTD has 29 registrations on MahaRERA, including SWAPNASAMRAT and Blue Ridge Project C Land T18 and T19. Its filings disclose 17 earlier MahaRERA projects: declares 9 of 17 past projects completed on time. Litigation is declared on 6 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Happiness Hub - Varve is delayed beyond 28 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Happiness Hub - Varve?

The registered promoter entity is PARANJAPE SCHEMES (CONSTRUCTION) LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Happiness Hub - Varve?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Happiness Hub - Varve?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Happiness Hub - Varve?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in Happiness Hub - Varve?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Happiness Hub - Varve. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Happiness Hub - Varve to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.