AARYA GREEN COUNTY

By NIRMITEE DEVELOPRERS

RG-MH-15993 · RERA P52100024538 · Last updated on MahaRERA portal: 25 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 60 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 60 months from the original
2 of 22Construction stages doneacross 2 buildings; furthest along: Plinth, 90%
47 of 64Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 117 documents Report an error

AARYA GREEN COUNTY is a Others project by NIRMITEE DEVELOPRERS in Pune, Maharashtra, registered with MahaRERA as P52100024538 on 18 Feb 2020. Possession is promised by 31 Dec 2027. The completion date has moved by 60 months from the original filing. 17 of the 64 units on this registration are recorded sold or booked, and 2 of 22 construction stages are filed complete.

At a glance

Project

  • NameAARYA GREEN COUNTY
  • TypeOthers
  • Location
    • 235
    • BHORESHWAR NAGAR
    • BHOR
    • Bhor (M Cl)
    • Pune
    • 412206
  • Pincode412206
  • RERA no.P52100024538
  • ReraGenie IDRG-MH-15993

Builder

  • NameNIRMITEE DEVELOPRERS
  • Entity typePartnership
  • PartnersSANDEEP NEWASE, NILESH TOSHNIWAL

Key dates

this monthRegisteredFeb 2020First promiseDec 2022Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Feb 2020
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Dec 2022)
  • Buildings2 building records
  • Documents filed117 files

Current status

27%17 of 64 units booked
61.1%Work done, per cost certificate

Figures as on 25 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BNA6656056
ANA61808

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 25 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Plinth, at 90%.

B55%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth90%
Stilt Floor90%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A6%
ActivityProgress
Excavation70%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 25 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
B11
A11

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,231 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Nilesh ToshniwalPune (M Corp.)Pune
Sandeep NewaseVenvadiPune

Approvals and building plan

Sanctioning authorityBHOR MUNCIPAL CORPORATION
Permissible FSI4923.87
Proposed, not sanctioned3,146 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICC TRAD CENTER SHOP NO 5 GROUND FLOOR SENAPATI BAPAT ROAD PUNE 411016
Estimated costRs 9.00 cr
Cost incurredRs 5.50 cr
Work done61.11%
BuildingWingEstimatedIncurred
BNARs 6.75 crRs 5.50 cr
ANARs 2.25 cr-

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShripad Padhye
EngineerAjit Gijare
EngineerPRASHANT CHANDRASHEKHAR BOLKOTE
Chartered AccountantDheeraj Dharmavat
Chartered AccountantS.G MUNDADA &CO
Chartered AccountantROHAN LADDHA
Chartered AccountantVINOD S SABU
PartnerRole in project
NIRMITEE DEVELOPERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100013140Dec 2022 → Jun 2025

Reason as filed by the promoterDUE TO COVID 19 SITUATION AND LACK OF DEMANDS FOR FLATS . ALSO FINANCIAL ISSUE.

EA05082502308Dec 2022 → Dec 2027

Reason as filed by the promoterThe delay in the project is primarily due to the lack of bookings and insufficient funds. From the beginning until June 2025, we have received only 11 bookings. The overall pace of booking has been very slow, resulting in inadequate cash flow, which is the main reason for the delay in project progress.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Feb 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Dec 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Dec 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed117

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 117 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: ARCH CERT Q4.pdf25 Jul 2026
Withdrawal Update Form 2File: ENG CERT Q4.pdf25 Jul 2026
Withdrawal Update Form 3File: FORM3 CERT Q4.pdf25 Jul 2026
Form 2A (FY 2024-2025)File: form2a_Quality Assurance-1 (1).pdf16 Feb 2026
Form 2A (FY 2024-2025)File: Form2a_Quality Assurance.pdf13 Feb 2026
Form 5 (FY 2024-2025)File: (Form 5)(FY 2024-25)New_Format.pdf13 Feb 2026
Withdrawal Update Form 1File: ARCH CERTF Q3.pdf9 Feb 2026
Withdrawal Update Form 2File: ENG CERT Q3.pdf9 Feb 2026
Withdrawal Update Form 3File: FORM 3 CERT Q3.pdf9 Feb 2026
Form 1File: ARC CERTFQ2 25-26.pdf6 Dec 2025
Form 2File: ENG CERT Q2 2025-26.pdf6 Dec 2025
Form 3File: FORM 30Q2 2025-26.pdf6 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory_Qtr_2.pdf6 Dec 2025
Withdrawal Update Form 1File: ARC CERTFQ2 25-26.pdf2 Dec 2025
Withdrawal Update Form 2File: ENG CERT Q2 2025-26.pdf2 Dec 2025
Withdrawal Update Form 3File: FORM 30Q2 2025-26.pdf2 Dec 2025
Withdrawal Update Form 1File: ARC CERTFQ2 25-26.pdf27 Nov 2025
Withdrawal Update Form 2File: ENG CERT Q2 2025-26.pdf27 Nov 2025
Withdrawal Update Form 3File: FORM 30Q2 2025-26.pdf27 Nov 2025
Form 1File: form 1.pdf23 Jul 2025
Form 2File: form 2.pdf23 Jul 2025
Form 3File: form 3.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory Qtr 1.pdf23 Jul 2025
Self-declaration of Quarterly ProgressFile: Self Declaration.pdf23 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3_22-23_Q3.pdf16 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3_22-23_Q4.pdf16 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3_23-24_Q1.pdf16 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3_23-24_Q2.pdf16 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3_23-24_Q3.pdf16 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3_23-24_Q4.pdf16 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3_24-25_Q1.pdf16 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3_24-25_Q2.pdf16 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3_22-23_Q1.pdf16 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3_22-23_Q2.pdf16 May 2025
Disclosure of sold/ booked inventoryFile: Inventory_24-25_Q4.pdf16 May 2025
Disclosure of sold/ booked inventoryFile: Inventory_24-25_Q3.pdf16 May 2025
Disclosure of sold/ booked inventoryFile: Inventory_24-25_Q2.pdf16 May 2025
Disclosure of sold/ booked inventoryFile: Inventory_24-25_Q1.pdf16 May 2025
Disclosure of sold/ booked inventoryFile: Inventory_23-24_Q4.pdf16 May 2025
Disclosure of sold/ booked inventoryFile: Inventory_23-24_Q3.pdf16 May 2025
Disclosure of sold/ booked inventoryFile: Inventory_23-24_Q2.pdf16 May 2025
Disclosure of sold/ booked inventoryFile: Inventory_23-24_Q1.pdf16 May 2025
Disclosure of sold/ booked inventoryFile: Inventory_22-23_Q4.pdf16 May 2025
Disclosure of sold/ booked inventoryFile: Inventory_22-23_Q3.pdf16 May 2025
Disclosure of sold/ booked inventoryFile: Inventory_22-23_Q2.pdf16 May 2025
Disclosure of sold/ booked inventoryFile: Inventory_22-23_Q1.pdf16 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC_Q1_23-24.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC_Q1_24-25.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC_Q2_23-24.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC_Q3_22-23.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC_Q4_22-23.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC_Q4_23-24.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC_21-22.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_Q4_23-24.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_Q4_22-23.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_Q4_22-23.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_Q3_24-25.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_Q3_23-24.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_Q3_22-23.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_Q2_24-25.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_Q2_23-24.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_Q2_22-23.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_Q1_24-25.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_Q1_23-24.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_Q1_22-23.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_Q1_22-23.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC _21-22.pdf18 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: (Form 5)(FY 2022-23_compressed.pdf9 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate.pdf25 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate 2020.pdf17 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate 2021.pdf17 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold.pdf17 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: DOC183.PDF10 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate.pdf10 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate.pdf10 Jan 2023
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf10 Jan 2023
Layout approvalFile: scan27816.pdf10 Dec 2022
Building plan approvalFile: DOC183.PDF10 Dec 2022
Building plan approvalFile: scan27815.pdf10 Dec 2022
Building plan approvalFile: scan27817.pdf10 Dec 2022

How this compares with Pune

27%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 60 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AARYA GREEN COUNTY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BHOR13,700+ in Pune

Builder: NIRMITEE DEVELOPRERS

NIRMITEE DEVELOPRERS has 1 registration on MahaRERA, including AARYA GREEN COUNTY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if AARYA GREEN COUNTY is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AARYA GREEN COUNTY?

The registered promoter entity is NIRMITEE DEVELOPRERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AARYA GREEN COUNTY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AARYA GREEN COUNTY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AARYA GREEN COUNTY?

The professionals named in the filing: Architect: Shripad Padhye; Engineer: Ajit Gijare; Engineer: PRASHANT CHANDRASHEKHAR BOLKOTE; Chartered Accountant: Dheeraj Dharmavat; Chartered Accountant: S.G MUNDADA &CO; Chartered Accountant: ROHAN LADDHA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AARYA GREEN COUNTY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AARYA GREEN COUNTY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AARYA GREEN COUNTY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.