Home / Browse projects / Mumbai Suburban, Maharashtra / HANS ELEGANCE
HANS ELEGANCE
RG-MH-26202 · RERA P51800003370 · Last updated on MahaRERA portal: 28 Jun 2022
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 3 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
HANS ELEGANCE is a Residential / Group Housing project by SHREE HANS REALTORS LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003370 on 5 Aug 2017. The registration is recorded completed; possession was promised by 30 Sep 2018.
At a glance
Project
- NameHANS ELEGANCE
- TypeResidential / Group Housing
- Location
- Andheri
- Mumbai Suburban
- 400057
- Pincode400057
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800003370
- ReraGenie IDRG-MH-26202
Builder
- NameSHREE HANS REALTORS LLP
- Entity typeOthers
- ChairpersonVALLABHBHAI VASHRAMBHAI ITALIA
- Managing DirectorsRAMESH VASHRAMBHAI ITALIA, RAJESH KANTILAL SHAH, SEJAL ROHAN SHAH, DHANJIBHAI RAMJIBHAI ITALIA, MAHESH DUNGARSHIBHAI ITALIA
- Named personVALLABHBHAI ITALIA
- Other registrations3 more →
- Completed2 of 4
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects3 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on5 Aug 2017
- Promised completion30 Sep 2018
- Revised completionNone
- Buildings1 building record
- Documents filed21 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| HANS ELEGANCE | NA | 9 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 28 Jun 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 80%.
HANS ELEGANCE: 56% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 80% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 28 Jun 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed29
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | IND ARCHITECTS |
| Engineer | HARESH PATEL |
| Partner | Role in project |
|---|---|
| SHREE HANS REALTORS LLP | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 28 Jun 2022
Documents filed21
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 1 Other.pdf | 28 Jun 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society cERTIFICATE.pdf | 28 Jun 2022 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 ARCHITECT.pdf | 31 Jul 2021 |
| OtherFile: FINAL OC.pdf | 25 Oct 2018 |
| Certificates of CA (Form 5)File: Shreehans RERA Audit.pdf | 30 Sep 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARC-1.pdf | 31 Oct 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eNG.pdf | 31 Oct 2017 |
| Certificates of CA (Form 3)File: CA -1.pdf | 31 Oct 2017 |
| Building plan approvalFile: IOD FINAL.PDF | 28 Jul 2017 |
| Layout approvalFile: LAYOUT F.pdf | 28 Jul 2017 |
| PAN CardFile: PAN.pdf | 28 Jul 2017 |
| Copy of the legal title reportFile: TITLE FINAL.pdf | 28 Jul 2017 |
| Details of encumbrancesFile: ENCUMBRABNCES.pdf | 28 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: LAYOUT F.pdf | 28 Jul 2017 |
| Building Plan Approval (IOD)File: IOD FINAL.PDF | 28 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: bOTH ccc final.pdf | 28 Jul 2017 |
| Declaration in FORM BFile: form b - FINAL.pdf | 28 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arc - final.pdf | 28 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG FINAL.pdf | 28 Jul 2017 |
| Certificates of CA (Form 3)File: ca final.pdf | 28 Jul 2017 |
| Proforma of Allotment letterFile: Agreement for Sale - RERA Draft.pdf | 28 Jul 2017 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| HANS VALLABH NIWASP51800034673 | VILE PARLE EAST, Mumbai Suburban | - | Apr 2022 | Certificate Signed | Mar 2024 | Dec 2023 |
| REDEVELOPMENT OF HANS TOP IN TOWNP51800016991 | MALAD EAST, Mumbai Suburban | - | Jun 2018 | Certificate Signed | May 2023 | Late, Aug 2023 |
| HANS AVENUE | PLOT NO 272 JAWAHAR NAGAR GOREGOAN WEST | 26 | - | Completed | Sep 2013 | Sep 2013 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 21 filed documents as one ZIP, foldered, with a manifest
Keep HANS ELEGANCE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Andheri6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 351 registered projects within 2 km.
Vijayraj Residency
Vijayraj Realtors
ZEE HAPPY VEENA
ZEE LIFESPACES
Romell Espalier
ROMELL REAL ESTATE PRIVATE LIMITED
ZEE SHAAN
TRISUL DEVELOPERS
SALE BUILDING 1 - CHAMUNDA CROWN AND SALE BUIL
Chamunda Builders & Developers
ARKADE PEARL 1
ARKADE DEVELOPERS LIMITED
See every Mumbai Suburban project, with the district possession charts
Builder: SHREE HANS REALTORS LLP
SHREE HANS REALTORS LLP has 4 registrations on MahaRERA, including HANS ELEGANCE and REDEVELOPMENT OF HANS TOP IN TOWN. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if HANS ELEGANCE is delayed beyond 30 Sep 2018?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of HANS ELEGANCE?
The registered promoter entity is SHREE HANS REALTORS LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in HANS ELEGANCE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for HANS ELEGANCE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at HANS ELEGANCE?
The professionals named in the filing: Architect: IND ARCHITECTS; Engineer: HARESH PATEL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in HANS ELEGANCE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback