Home / Browse projects / Ratnagiri, Maharashtra / HAJI ABDUL GAFUR COMPLEX

Registered No litigation declared Others project

HAJI ABDUL GAFUR COMPLEX

By ISMAIL GAFUR KASU

RG-MH-26543 · RERA P52800004390 · Last updated on MahaRERA portal: 20 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 86 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 86 months from the original
5 of 11Construction stages donefurthest along: Staircases, 97%
26 of 50Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 67 documents Report an error

HAJI ABDUL GAFUR COMPLEX is a Others project by ISMAIL GAFUR KASU in Ratnagiri, Maharashtra, registered with MahaRERA as P52800004390 on 9 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 86 months from the original filing. 24 of the 50 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameHAJI ABDUL GAFUR COMPLEX
  • TypeOthers
  • Location
    • Lanja
    • Lanja (CT)
    • Ratnagiri
    • 416701
  • Pincode416701
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52800004390
  • ReraGenie IDRG-MH-26543

Builder

  • NameISMAIL GAFUR KASU
  • Entity typeIndividual

Key dates

this monthRegisteredAug 2017First promiseOct 2020Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Aug 2017
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Oct 2020)
  • Buildings1 building record
  • Documents filed67 files

Current status

48%24 of 50 units booked
80.5%Work done, per cost certificate

Figures as on 20 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
HAJI ABDUL GAFUR COMPLEXNA55321850

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 97%.

HAJI ABDUL GAFUR COMPLEX: 78% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises83%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks97%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.69%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.25%

Progress on shared amenities15

As on 20 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes85%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes50%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes85%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed24

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots24
Closed/Covered9
Open Space15

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,800 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityLanja Nagar Panchayat
Permissible FSI2389.0
Proposed, not sanctioned2,380 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSAITARA COMPLEX MUMBAI GOA HAIGHWAY LANJA RATNAGIRI 416701
Estimated costRs 5.90 cr
Cost incurredRs 4.75 cr
Work done80.48%
BuildingWingEstimatedIncurred
HAJI ABDUL GAFUR COMPLEXNARs 5.90 crRs 4.75 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShirish Ghorpade
EngineerManoj Joshi
Chartered AccountantAkshay C Shetye
Chartered AccountantVarad Pandit
PartnerRole in project
ISMAIL GAFUR KASU-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52800006076Oct 2020 → Oct 2021

Reason as filed by the promoterRevised approval from authority.

EXT52800011895Oct 2020 → Apr 2025

Reason as filed by the promoterBuilding Extention

EXT52800028363Oct 2020 → Dec 2027

Reason as filed by the promoterProject is almost on the verge of completion

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 May 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 May 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed67

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf20 Jun 2026
Withdrawal Update Form 2File: Form 2.pdf20 Jun 2026
Withdrawal Update Form 3File: Form 3.pdf20 Jun 2026
Withdrawal Update Form 1File: Form 1.pdf15 Mar 2026
Withdrawal Update Form 1File: Form 1.pdf15 Mar 2026
Withdrawal Update Form 1File: form 1.pdf15 Mar 2026
Withdrawal Update Form 2File: Form 2.pdf15 Mar 2026
Withdrawal Update Form 2File: form 2.pdf15 Mar 2026
Withdrawal Update Form 2File: Form 2.pdf15 Mar 2026
Withdrawal Update Form 3File: Form 3.pdf15 Mar 2026
Withdrawal Update Form 3File: Form 3.pdf15 Mar 2026
Withdrawal Update Form 3File: form 3.pdf15 Mar 2026
Form 5 (FY 2024-2025)File: Form 5 24-25.pdf15 Mar 2026
Declaration in FORM BFile: Form B.pdf23 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf23 Jul 2025
Certificates of CA (Form 3)File: Form 3.pdf23 Jul 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf23 Jul 2025
Disclosure of sold/ booked inventoryFile: Sold Booked.pdf23 Jul 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Bank Format.pdf23 Jul 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclouser of interest.pdf23 Jul 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2024.pdf23 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf16 Dec 2024
Certificates of CA (Form 3)File: FORM 3 - converted.pdf6 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf6 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 24.pdf6 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 22-23.pdf2 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 2021-22.pdf27 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf16 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf16 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2a.pdf16 Mar 2023
Certificates of CA (Form 3)File: FORM 3.pdf16 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf18 May 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf18 May 2022
CERSAI detailsFile: CERSAI_Search_Report.pdf18 May 2022
CERSAI detailsFile: Cersai Encumbrance.pdf18 May 2022
Certificates of CA (Form 3)File: FORM 3.pdf18 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 19-20.pdf18 May 2022
Declaration about Commencement CertificateFile: Declaration.pdf25 Nov 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf25 Nov 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf25 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 20.pdf25 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 21.pdf25 Nov 2021
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf25 Nov 2021
Certificates of CA (Form 3)File: Form 3.pdf25 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 21.pdf25 Nov 2021
Layout approvalFile: Plan.pdf12 May 2020
Layout approvalFile: Plan 1.pdf12 May 2020
Copy of Layout Approval (in case of layout)File: Plan.pdf12 May 2020
Copy of Layout Approval (in case of layout)File: Plan 1.pdf12 May 2020
Commencement Certificates / NA Order for plotted developmentFile: permission.pdf12 May 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf12 May 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5.pdf12 May 2020
Certificates of CA (Form 5)File: Signed Form 5 - Kasu Builders.pdf2 Oct 2018
Building plan approvalFile: 13 Order nagarpanchayat.pdf29 Jul 2017
Layout approvalFile: 4 Plan.pdf29 Jul 2017
PAN CardFile: 1 Kasu Pancard.pdf29 Jul 2017
Copy of the legal title reportFile: 2 Kasu search.pdf29 Jul 2017
Details of encumbrancesFile: 3 Kasu self declaration.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 4 Plan.pdf29 Jul 2017
Building Plan Approval (IOD)File: 13 Order nagarpanchayat.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: 14 NA order.pdf29 Jul 2017
Declaration in FORM BFile: 6 Kasu B form.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 7 Kasu Form 1.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 11 Kasu Form 2.pdf29 Jul 2017
Certificates of CA (Form 3)File: 9 Kasu Form 3.pdf29 Jul 2017
Proforma of Allotment letterFile: 5a Allotment form.pdf29 Jul 2017
Proforma of Allotment letterFile: 5b Kasu agreement.pdf29 Jul 2017

How this compares with Ratnagiri

48%of this project is bookeddistrict median 23%
15%of Ratnagiri projects moved their completion datethis one moved by 86 months
30%of Ratnagiri registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.

Keep HAJI ABDUL GAFUR COMPLEX on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Lanja1,100+ in Ratnagiri

2 kmHAJI ABDUL GAFUR COMPLEXCompleted 5Lapsed / revoked 6Other 7Dot size: filed unitsN

Filed coordinates, straight-line distance. 18 registered projects within 2 km.

Builder: ISMAIL GAFUR KASU

ISMAIL GAFUR KASU has 1 registration on MahaRERA, including HAJI ABDUL GAFUR COMPLEX. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Ratnagiri district page.

Frequently asked questions

What are my rights if HAJI ABDUL GAFUR COMPLEX is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of HAJI ABDUL GAFUR COMPLEX?

The registered promoter entity is ISMAIL GAFUR KASU, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in HAJI ABDUL GAFUR COMPLEX?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for HAJI ABDUL GAFUR COMPLEX?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at HAJI ABDUL GAFUR COMPLEX?

The professionals named in the filing: Architect: Shirish Ghorpade; Engineer: Manoj Joshi; Chartered Accountant: Akshay C Shetye; Chartered Accountant: Varad Pandit. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HAJI ABDUL GAFUR COMPLEX?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HAJI ABDUL GAFUR COMPLEX. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HAJI ABDUL GAFUR COMPLEX to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.