ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / GURU PADMA KUTIR CO OPERATIVE HOUSING SOCIETY

Registered No litigation declared Residential / Group Housing project

GURU PADMA KUTIR CO OPERATIVE HOUSING SOCIETY

By URBAN DEVELOPERS

RG-MH-33075 · RERA P51700080547 · Last updated on MahaRERA portal: 18 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 3 other registrations.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedno revision filed
4 of 9Construction stages donefurthest along: Internal walls, 35%
11 of 19Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 39 documents Report an error

GURU PADMA KUTIR CO OPERATIVE HOUSING SOCIETY is a Residential / Group Housing project by URBAN DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700080547 on 16 Jun 2025. Possession is promised by 31 Mar 2027. 8 of the 19 units on this registration are recorded sold or booked, and 4 of 9 construction stages are filed complete.

At a glance

Project

  • NameGURU PADMA KUTIR CO OPERATIVE HOUSING SOCIETY
  • TypeResidential / Group Housing
  • Location
    • BADLAPUR
    • BADLAPUR GAON
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • RERA no.P51700080547
  • ReraGenie IDRG-MH-33075

Builder

  • NameURBAN DEVELOPERS
  • Entity typePartnership
  • Other registrations3 more →
  • Completed2 of 4

Key dates

this monthRegisteredJun 2025PromisedMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on16 Jun 2025
  • Promised completion31 Mar 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed39 files

Current status

42%8 of 19 units booked
54.1%Work done, per cost certificate

Figures as on 18 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GURU PADMA KUTIR CO OPERATIVE HOUSING SOCIETYNA8719019

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 9 construction stages are filed complete. The stage furthest along is Internal walls, at 35%.

GURU PADMA KUTIR CO OPERATIVE HOUSING SOCIETY: 50% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.15%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed27

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots27
Closed/Covered6
Open Space21

Land and ownership11

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area311 sq m
Land owned byThe promoter, with other names on the file
Named landowners11
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on26 Nov 2025
LandownerVillageDistrict
GURU PADMA KUTIR CO OPERATIVE HOUSING SOCIETYBadlapur (M Cl)Thane
DHONDIRAM SITARAM JORIBadlapur (M Cl)Thane
PRASAD BHAGWAN GAIKWADBadlapur (M Cl)Thane
RISHIKESH DASHRATH SABALEBadlapur (M Cl)Thane
DEEPALI GANESH PARWADIBadlapur (M Cl)Thane
GANESH RAJARAM PARVADIBadlapur (M Cl)Thane
ASHUL SHANTARAM VIPATBadlapur (M Cl)Thane
JYOTI PRAKASH GUJARBadlapur (M Cl)Thane
VAIBHAV PRAKASH GUJARBadlapur (M Cl)Thane
DIWAKAR BECHAR TRIBHUVANEBadlapur (M Cl)Thane
SAGAR DHONDIRAM JORIBadlapur (M Cl)Thane

Approvals and building plan

Sanctioning authorityKULGAON BADLAPUR MUNICIPAL COUNCIL
Permissible FSI804.3
Proposed, not sanctioned804 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch“BHASKARA”, SURVEY NO.20&26,YOG-VAIBHAV CO-OP HOUSING SOCIETY,KATRAP ROAD , BADLAPUR, THANE,MAHARASHTRA , PIN 421503
Estimated costRs 1.75 cr
Cost incurredRs 94.80 lakh
Work done54.07%
BuildingWingEstimatedIncurred
GURU PADMA KUTIR CO OPERATIVE HOUSING SOCIETYNARs 1.58 crRs 94.80 lakh
-NARs 17.31 lakh-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRaj Associates
EngineerAtul Kudtarkar and Associates Pvt Ltd
EngineerATUL VIJAY KUDTARKAR
Chartered AccountantVinesh Ahuja
Chartered AccountantRAVIRAJ B DANGE
Chartered AccountantSUPRIYA MILIND KALAMKAR
PartnerRole in project
URBAN DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Jun 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Apr 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Apr 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed39

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: form 2a -updated.pdf18 May 2026
Withdrawal Update Form 1File: FORM 1_11zon.pdf25 Apr 2026
Withdrawal Update Form 2File: FORM 2.pdf25 Apr 2026
Withdrawal Update Form 3File: FORM 3_11zon.pdf25 Apr 2026
Withdrawal Update Form 1File: FORM 1.pdf21 Jan 2026
Withdrawal Update Form 2File: FORM 2.pdf21 Jan 2026
Withdrawal Update Form 3File: FORM 3.pdf21 Jan 2026
Withdrawal Update Form 1File: Form 1.pdf28 Nov 2025
Withdrawal Update Form 1File: FORM 1.pdf28 Nov 2025
Withdrawal Update Form 2File: Form 2_11zon.pdf28 Nov 2025
Withdrawal Update Form 2File: FORM 2 Q2_11zon.pdf28 Nov 2025
Withdrawal Update Form 3File: Form 3.pdf28 Nov 2025
Withdrawal Update Form 3File: Form 3.pdf28 Nov 2025
Copy of the legal title reportFile: Title Report.pdf3 Jun 2025
Other - LegalFile: 1 Other - Legal (2) (1).pdf3 Jun 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Bank Declaration (2).pdf3 Jun 2025
Other - FinanceFile: 1 Other - Finance (1).pdf3 Jun 2025
Proforma of Agreement for saleFile: New Performa.pdf3 Jun 2025
Proforma of Allotment letterFile: new allotment.pdf13 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: new ca.pdf13 May 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: New Bank Letter.pdf13 May 2025
Declaration in FORM BFile: Fom B Part.pdf29 Apr 2025
CERSAI detailsFile: CERSAI_Search_Report_200351797921_For_Asset_Based_Search_29_04_2025_18_31_28_680.pdf29 Apr 2025
CERSAI detailsFile: Cersai.pdf29 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Interest Declaration.pdf29 Apr 2025
Layout approvalFile: Plan.PDF28 Apr 2025
Building plan approvalFile: Plan.PDF28 Apr 2025
PAN CardFile: Firm Pan.pdf28 Apr 2025
Details of encumbrances concerned to FinanceFile: Detail of Encumberance Finance-1.pdf28 Apr 2025
Copy of Layout Approval (in case of layout)File: Plan.PDF28 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf28 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf28 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Plan.PDF28 Apr 2025
Declaration about Commencement CertificateFile: commencement Declaration.pdf28 Apr 2025
Deviation Report with respect to Allotment letterFile: Deviation Allotment Letter.pdf28 Apr 2025
Details of encumbrances concerned to LegalFile: Detail of Encumberance Finance-1.pdf28 Apr 2025
Deviation Report with respect to model copy of AgreementFile: Devation Agreemnt for sale.pdf28 Apr 2025
Disclosure for secured/unsecured finance availed for the projectFile: Loan Declaration.pdf28 Apr 2025

How this compares with Thane

42%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GURU PADMA KUTIR CO OPERATIVE HOUSING SOCIET on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BADLAPUR GAON7,600+ in Thane

Builder: URBAN DEVELOPERS

Urban Developers has 4 registrations on MahaRERA, including Urban Park and SWAMI COMPLEX. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if GURU PADMA KUTIR CO OPERATIVE HOUSING SOCIETY is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GURU PADMA KUTIR CO OPERATIVE HOUSING SOCIETY?

The registered promoter entity is URBAN DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GURU PADMA KUTIR CO OPERATIVE HOUSING SOCIETY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GURU PADMA KUTIR CO OPERATIVE HOUSING SOCIETY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GURU PADMA KUTIR CO OPERATIVE HOUSING SOCIETY?

The professionals named in the filing: Architect: Raj Associates; Engineer: Atul Kudtarkar and Associates Pvt Ltd; Engineer: ATUL VIJAY KUDTARKAR; Chartered Accountant: Vinesh Ahuja; Chartered Accountant: RAVIRAJ B DANGE; Chartered Accountant: SUPRIYA MILIND KALAMKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GURU PADMA KUTIR CO OPERATIVE HOUSING SOCIETY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GURU PADMA KUTIR CO OPERATIVE HOUSING SOCIETY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GURU PADMA KUTIR CO OPERATIVE HOUSING SOCIET to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.