Home / Browse projects / Mumbai Suburban, Maharashtra / GURU ASHISH

Registered No litigation declared Residential / Group Housing project

GURU ASHISH

By SHIVCORP INFRA (OPC) PRIVATE LIMITED

RG-MH-06357 · RERA P51800053415 · Last updated on MahaRERA portal: 8 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 12 months from the original
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 92%
23 of 29Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 57 documents Report an error

GURU ASHISH is a Residential / Group Housing project by SHIVCORP INFRA (OPC) PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800053415 on 31 Oct 2023. Possession is promised by 31 Mar 2027. The completion date has moved by 12 months from the original filing. 6 of the 29 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameGURU ASHISH
  • TypeResidential / Group Housing
  • Location
    • Gawanpada Mulnd East
    • Mumbai
    • Mulund east
    • Greater Mumbai (M Corp.) (Part) (802794)
    • Mumbai
    • Mumbai Suburban
    • 400081
  • Pincode400081
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800053415
  • ReraGenie IDRG-MH-06357

Builder

  • NameSHIVCORP INFRA (OPC) PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorShyamlal Hiro Thakur

Key dates

this monthRegisteredOct 2023First promiseMar 2026Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Oct 2023
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Mar 2026)
  • Buildings1 building record
  • Documents filed57 files

Current status

21%6 of 29 units booked
38.6%Work done, per cost certificate

Figures as on 8 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GURU ASHISHNA141429029

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 92%.

GURU ASHISH: 57% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure92%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises42%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 8 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed33

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots33
Closed/Covered33

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area615 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Declared on14 May 2025
LandownerVillageDistrict
GURU ASHISHGreater Mumbai (M Corp.) (Part) (802794)Mumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI2401.71
Proposed, not sanctioned606 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMULUND WEST
Estimated costRs 11.19 cr
Cost incurredRs 4.31 cr
Work done38.56%
BuildingWingEstimatedIncurred
GURU ASHISHNARs 9.46 crRs 4.31 cr
-NARs 1.73 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectR P Asundaria
EngineerMr. KIRTIKUMAR HIMATLAL SHAH
EngineerABHIJIT ARUN NIKAM
Chartered AccountantCA Heena Momaya & Co
Chartered AccountantANJU PALAN & CO
PartnerRole in project
SHIVCORP INFRA OPC PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA04042620559Mar 2026 → Mar 2027

Reason as filed by the promoterConstruction works did not progress as expected and around 60% work of the project is completed so far and for the completion of the construction of the building, it will take around 9-10 months. Thereafter, the procedure for issue of Occupancy Certificate by BMC will also take about 2-3 months.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Jul 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Jul 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 May 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Mar 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed57

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2023-2024)File: Form 2A_FY2023-24.pdf8 Jun 2026
Form 2A (FY 2024-2025)File: Form 2A_FY2024-25.pdf8 Jun 2026
Form 2A (FY 2025-2026)File: Form 2A_FY2025-26.pdf8 Jun 2026
Form 5 (FY 2023-2024)File: FORM 5 _2023-24.pdf6 Jun 2026
Form 5 (FY 2024-2025)File: FORM 5 _2024-25.pdf6 Jun 2026
Form 5 (FY 2025-2026)File: FORM 5 _2025-26.pdf6 Jun 2026
Building plan approvalFile: plan (1)_compressed.pdf29 May 2026
Withdrawal Update Form 1File: Form 1_310326.pdf29 May 2026
Withdrawal Update Form 2File: Form 2_310326.pdf29 May 2026
Withdrawal Update Form 3File: FORM 3.pdf29 May 2026
Commencement certificateFile: DOC-20260306-WA0006..pdf21 Mar 2026
Withdrawal Update Form 1File: Architect Certificate.pdf21 Mar 2026
Withdrawal Update Form 1File: FORM 1_31122025.pdf21 Mar 2026
Withdrawal Update Form 2File: Engineer Certificate.pdf21 Mar 2026
Withdrawal Update Form 2File: FORM 2_31122025.pdf21 Mar 2026
Withdrawal Update Form 3File: CA certificate.pdf21 Mar 2026
Withdrawal Update Form 3File: FROM 3_31122025.pdf21 Mar 2026
Withdrawal Update Form 1File: Architect Certificate.pdf4 Mar 2026
Withdrawal Update Form 2File: Engineer Certificate.pdf4 Mar 2026
Withdrawal Update Form 3File: CA Certificate.pdf4 Mar 2026
Building plan approvalFile: Building plan_compressed.pdf6 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_310325.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf28 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf28 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf28 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: 2428000_FurtherCC_signed.pdf29 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineer Certificate.pdf9 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1_Architect Certificate 160424.pdf3 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_CA Certificate.pdf3 May 2024
Declaration about Commencement CertificateFile: Format - D.pdf18 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf18 Sep 2023
Proforma of Agreement for saleFile: Agreement for sale_11zon (1).pdf18 Sep 2023
Other - LegalFile: DECLARATION for cost detail.pdf9 Sep 2023
Details of encumbrances concerned to FinanceFile: DECLARATION FOR NO FINANCIAL ENCUMBRANCES.pdf21 Aug 2023
Details of encumbrances concerned to FinanceFile: DECLARATION FOR NO LEGAL ENCUMBRANCES.pdf21 Aug 2023
Details of encumbrances concerned to LegalFile: DECLARATION FOR NO FINANCIAL ENCUMBRANCES.pdf21 Aug 2023
Details of encumbrances concerned to LegalFile: DECLARATION FOR NO LEGAL ENCUMBRANCES.pdf21 Aug 2023
Other - FinanceFile: Declaration for flats as per CC.pdf21 Aug 2023
Other - LegalFile: Self Declaration for DIN No with enclo.pdf18 Aug 2023
CERSAI detailsFile: DECLARATION FOR NO CERSAI.pdf17 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Disclosure of Interest in Other Real Estate Organizations.pdf17 Aug 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account.pdf17 Aug 2023
Deviation Report with respect to model copy of AgreementFile: DECLARATION FOR REPORT ON DEVATION IN RESPECT OF SALE DEED_compressed.pdf17 Aug 2023
Other - FinanceFile: declaration.pdf17 Aug 2023
Layout approvalFile: LAYOUT.pdf21 Jul 2023
Building plan approvalFile: Plan IOD approved.pdf21 Jul 2023
PAN CardFile: PAN_SHIV CORP.pdf21 Jul 2023
Copy of the legal title reportFile: Legal Title Report.pdf21 Jul 2023
Details of encumbrances concerned to FinanceFile: DECLARATION FOR NO LEGAL ENCUMBRANCES.pdf21 Jul 2023
Details of encumbrances concerned to LegalFile: DECLARATION FOR NO LEGAL ENCUMBRANCES.pdf21 Jul 2023
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf21 Jul 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan IOD approved.pdf21 Jul 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate.pdf21 Jul 2023
Declaration in FORM BFile: Form B- Promoter.pdf21 Jul 2023
CERSAI detailsFile: CERSAI_Search_Report_200275086168_For_Asset_Based_Search_21_07_2023_13_57_40_043.pdf21 Jul 2023
Proforma of Allotment letterFile: Allotment Letter -.pdf21 Jul 2023
Deviation Report with respect to Allotment letterFile: DECLARATION FOR REPORT ON DEVATION IN RESPECT OF LETTER OF ALLOTMENT.pdf21 Jul 2023

How this compares with Mumbai Suburban

21%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GURU ASHISH on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mulund east6,700+ in Mumbai Suburban

2 kmGURU ASHISHCompleted 93Lapsed / revoked 82Other 120Dot size: filed unitsN

Filed coordinates, straight-line distance. 295 registered projects within 2 km.

Builder: SHIVCORP INFRA (OPC) PRIVATE LIMITED

SHIVCORP INFRA (OPC) PRIVATE LIMITED has 1 registration on MahaRERA, including GURU ASHISH. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if GURU ASHISH is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GURU ASHISH?

The registered promoter entity is SHIVCORP INFRA (OPC) PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GURU ASHISH?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GURU ASHISH?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GURU ASHISH?

The professionals named in the filing: Architect: R P Asundaria; Engineer: Mr. KIRTIKUMAR HIMATLAL SHAH; Engineer: ABHIJIT ARUN NIKAM; Chartered Accountant: CA Heena Momaya & Co; Chartered Accountant: ANJU PALAN & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GURU ASHISH?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GURU ASHISH. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GURU ASHISH to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.