ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / GUNJAI DARSHAN

Registered No litigation declared Residential / Group Housing project

GUNJAI DARSHAN

By LAXMI DEVELOPERS

RG-MH-06929 · RERA P51700053973 · Last updated on MahaRERA portal: 3 Jun 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2030Possession promisedno revision filed
6 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 65%
67 of 129Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 74 documents Report an error

GUNJAI DARSHAN is a Residential / Group Housing project by LAXMI DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700053973 on 18 Dec 2023. Possession is promised by 31 Dec 2030. 62 of the 129 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameGUNJAI DARSHAN
  • TypeResidential / Group Housing
  • Location
    • KALYAN
    • KALAYN
    • KATEMANEVALI
    • Thane
    • 421306
  • Pincode421306
  • RERA no.P51700053973
  • ReraGenie IDRG-MH-06929

Builder

  • NameLAXMI DEVELOPERS
  • Entity typePartnership
  • PartnersRAJESH MAVJI CHHEDA, ASHWIN MAVJI CHHEDA, DIWAKAR MANOJ RAI
  • Other registrations13 more →
  • Completed5 of 14
  • No longer live6 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredDec 2023PromisedDec 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Dec 2023
  • Promised completion31 Dec 2030
  • Revised completionNone
  • Buildings1 building record
  • Documents filed74 files

Current status

48%62 of 129 units booked
72.3%Work done, per cost certificate

Figures as on 3 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 2 WING BNA24231290129

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 65%.

BUILDING NO 2 WING B: 75% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.45%

Progress on shared amenities15

As on 3 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed141

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots141
Open Space141

Land and ownership9

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,130 sq m
Land owned byThe promoter, with other names on the file
Named landowners9
LandownerVillageDistrict
DUNDU KALU PAWSHEKATEMANEVALIThane
EKNATH KALU PAWSHEKATEMANEVALIThane
BALARAM KALU PAWSHEKATEMANEVALIThane
BABAN KALU PAWSHEKATEMANEVALIThane
ARJUN KALU PAWSHEKATEMANEVALIThane
GULAB PANDHRINATH PATILKATEMANEVALIThane
VASANTI SUBHASH PAWSHEKATEMANEVALIThane
BIPIN SUBHASH PAWSHEKATEMANEVALIThane
ASHMITA SUBHASH PAWSHEKATEMANEVALIThane

Approvals and building plan

Sanctioning authorityADTP, KALYAN DOMBIVALI MUNICIPAL CORPORATION, KALYAN
Permissible FSI7411.07
Proposed, not sanctioned2,411 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNH83, SUCHAK CHAMBERS, NEAR MAHAVEER SHOPPING CENTER AGRA ROAD KALYAN WEST
Estimated costRs 22.47 cr
Cost incurredRs 16.25 cr
Work done72.33%
BuildingWingEstimatedIncurred
BUILDING NO 2 WING BNARs 22.31 crRs 16.25 cr
-NARs 15.75 lakh-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDILIP TAMBDAY & ASSOCIATES
ArchitectDILIP TAMDAV & ASSOCIATES
EngineerAARNA STRUCTURAL CONSULATANT
Engineeraarna structural consultants
Chartered AccountantMAYUR K JAIN & CO
Chartered AccountantANKIT PARAS JAIN & CO
PartnerRole in project
LAXMI DEVELOPERS-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
SM12600020Bhakti AchrekarLAXMI DEVELOPERS07/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Oct 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2030

Documents filed74

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: QTR 4 FORM 1 MAR 26 GUNJAI DARSHAN.pdf3 Jun 2026
Withdrawal Update Form 2File: QTR 4 FORM 2 MAR 26 GUNJAI DARSHAN.pdf3 Jun 2026
Withdrawal Update Form 3File: final form 3 31-3-2026.pdf3 Jun 2026
Form 1File: QTR 3 FORM 1 DEC 25 GUNJAI DARSHAN.pdf27 Feb 2026
Form 2File: QTR 3 FORM 2 GUNJAI DARSHAN.pdf27 Feb 2026
Form 3File: QTR 3 FORM 3 DEC 2025 GUNJAI DARSHAN.pdf27 Feb 2026
Disclosure of Sold and Booked InventoryFile: QTR-3 SOLD UNSOLD DEC 2025 GUNJAI DARSHAN.pdf27 Feb 2026
Form 1File: Form 1 Architects certificate 30092025.pdf28 Nov 2025
Form 2File: QTR 2 FORM 2 SEPT 2025 GUNJAI.pdf28 Nov 2025
Form 3File: QTR 2 FORM 3 SEPT 2025 GUNJAI DARSHAN-Signed by both.pdf28 Nov 2025
Disclosure of Sold and Booked InventoryFile: QTR 2 SOLD UNSOLD SEPT 2025 GUNJAI.pdf28 Nov 2025
Form 5 (FY 2024-2025)File: FORM 5 GUNJAI 2024-25 SIgned.pdf30 Sep 2025
Form 1File: Form 1 Q1 LD.pdf2 Sep 2025
Form 2File: Form 2 Q1 LD.pdf2 Sep 2025
Form 3File: Form 3 Q1 LD.pdf2 Sep 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD Q1 LD.pdf2 Sep 2025
CERSAI detailsFile: QTR 4 SOLD UNSOLD MAR 25 GUNJAI.pdf15 Jul 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A GUNJAI DARSHAN 23-241.pdf15 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 31-03-2025.pdf13 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Laxmi Develoers 31-03-2025 Sign.pdf13 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 31-03-2025.pdf13 May 2025
Layout approvalFile: Plan 1 Copy 03-10-2024.pdf5 Mar 2025
Layout approvalFile: Plan 2 Copy 03-10-2024.pdf5 Mar 2025
Building plan approvalFile: Plan 1 Copy 03-10-2024.pdf5 Mar 2025
Copy of Layout Approval (in case of layout)File: Plan 1 Copy 03-10-2024.pdf5 Mar 2025
Copy of Layout Approval (in case of layout)File: Plan 2 Copy 03-10-2024.pdf5 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Plan 1 Copy 03-10-2024.pdf5 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: Revised CC COPY Dt 03-10-2024.pdf4 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: QTR 3 FORM 1 DEC 24 GUNJAI.pdf8 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: QTR 3 FORM 3 DEC 24 GUNJAI WITH SIGN.pdf8 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: QTR 3 FORM 2 DEC 24 GUNJAI.pdf8 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold List 31-12-2024.pdf8 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 30-09-2024.pdf28 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 30-06-2024 Sign.pdf28 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 30-09-2024 Sign.pdf28 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 30-09-2024.pdf28 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold List 30-06-2024.pdf28 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold List 30-09-2024.pdf28 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Gunjai 23-24.pdf11 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: QTR-4 ANNX A FORM 1 MARCH 24.pdf5 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: QTR-1 ANNX A FORM 1 JUNE 24.pdf5 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 QTR 4 MARCH 2024.pdf5 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 QTR 1 JUNE 2024.pdf5 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 31-03-2024.pdf5 Aug 2024
Other - TechnicalFile: 1 Copy of Layout Approval Final_compressed.pdf11 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Laxmi Developers Form 3_0001 revised.pdf24 Nov 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A Laxmi Developers Revised.pdf24 Nov 2023
Layout approvalFile: MYSCAN_20230901_0001 Revised1.pdf20 Nov 2023
Copy of Layout Approval (in case of layout)File: MYSCAN_20230901_0001 Revised1.pdf20 Nov 2023
Copy of the legal title reportFile: GetUserDocumentFileContent.pdf27 Oct 2023
Copy of the legal title reportFile: Laxmi Developers Legal Of Report_0001.pdf27 Oct 2023
Copy of the legal title reportFile: Laxmi Developers Flow Of Title_0001_compressed.pdf27 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_compressed.pdf27 Oct 2023
Declaration about Commencement CertificateFile: Laxmi Developers Form D_0001.pdf27 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_0001.pdf27 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ref_77_115_000_ R-0_2023_RAI GUNJAI DARSAN NF_(18-05-2023).pdf27 Oct 2023
CERSAI detailsFile: CERSAI_Search_Report_200284836527_For_Asset_Based_Search_27_10_2023_12_15_55_096.pdf27 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Laxmi Developers Annexure A Ashwin Chedda.pdf27 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Laxmi Developers Annexure A Rajesh Chheda.pdf27 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Laxmi Developers Annexure A Diwakar Chedda.pdf27 Oct 2023
Proforma of Agreement for saleFile: RERA Agreement Laxmi Developers.pdf27 Oct 2023
Deviation Report with respect to model copy of AgreementFile: Laxmi Developers Deviation With Respected To Agreement For Sale And Allotment Letter_0001.27 Oct 2023
Other - LegalFile: mou.pdf27 Oct 2023
Building plan approvalFile: MYSCAN_20230901_0001 (1)_compressed-compressed.pdf19 Oct 2023
PAN CardFile: PAN CARD LAXMI DEVELOPERS.pdf19 Oct 2023
Details of encumbrances concerned to FinanceFile: Scan_0001.pdf19 Oct 2023
Details of encumbrances concerned to FinanceFile: Scan_0001.pdf19 Oct 2023
Details of encumbrances concerned to LegalFile: Scan_0001.pdf19 Oct 2023
Details of encumbrances concerned to LegalFile: Scan_0001.pdf19 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20230901_0001 (1)_compressed-compressed.pdf19 Oct 2023
Declaration in FORM BFile: Form B Developers_compressed.pdf19 Oct 2023
CERSAI detailsFile: Scan_0001.pdf19 Oct 2023
Proforma of Allotment letterFile: Scan_0001_compressed.pdf19 Oct 2023
Deviation Report with respect to Allotment letterFile: Scan_0001.pdf19 Oct 2023

How this compares with Thane

48%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GUNJAI DARSHAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KALAYN7,600+ in Thane

Builder: LAXMI DEVELOPERS

LAXMI DEVELOPERS has 14 registrations on MahaRERA, including LAXMI VISHNUPURAM and KUTUMB. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if GUNJAI DARSHAN is delayed beyond 31 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GUNJAI DARSHAN?

The registered promoter entity is LAXMI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GUNJAI DARSHAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against GUNJAI DARSHAN?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for GUNJAI DARSHAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GUNJAI DARSHAN?

The professionals named in the filing: Architect: DILIP TAMBDAY & ASSOCIATES; Architect: DILIP TAMDAV & ASSOCIATES; Engineer: AARNA STRUCTURAL CONSULATANT; Engineer: aarna structural consultants; Chartered Accountant: MAYUR K JAIN & CO; Chartered Accountant: ANKIT PARAS JAIN & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GUNJAI DARSHAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GUNJAI DARSHAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GUNJAI DARSHAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.