Home / Browse projects / GSV Vertica
GSV Vertica
By GSV Ventures
RG-MH-22584 · RERA P52100034653 · Last updated on MahaRERA portal: 23 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Possession 1 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 21 months
- 2 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GSV Vertica is a Commercial project by GSV Ventures in Kharadkar park, 411030, registered with MahaRERA as P52100034653 on 20 Apr 2022. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 21 months from the original filing. 42 of the 87 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameGSV Vertica
- TypeCommercial
- Location
- Kharadi mundhava by pass
- Kharadkar park
- 411030
- Pincode411030
- RERA no.P52100034653
- ReraGenie IDRG-MH-22584
Builder
- NameGSV Ventures
- Entity typePartnership
- PartnersVishal Dharmendra Soni, Gopal Shivraj Varma, Nilesh Dilip Ghule
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on20 Apr 2022
- Promised completion30 Sep 2026
- Revised completionRevised to 30 Sep 2026 (originally 30 Dec 2024)
- Buildings1 building record
- Documents filed155 files
Current status
Figures as on 23 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GSV Vertica | NA | 19 | 10 | 0 | 87 | 87 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 23 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
GSV Vertica: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 23 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed56
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership10
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| PRASAD KRUSHNA PATHARE | - | Pune |
| JYOTSNA PRASAD PATHARE | - | Pune |
| SHRIKANT KANIFNATH PATHARE | - | Pune |
| SWAPNIL KANIFNATH PATHARE | - | Pune |
| DARSHANA SWAPNIL PATHARE | - | Pune |
| MAHENDRA PANDHARINATH PATHARE | - | Pune |
| PRANITA MAHENDRA PATHARE | - | Pune |
| PANDHARINATH DNYANOBA GARUD | - | Pune |
| SHITAL PANDHARINATH GARUD | - | Pune |
| NIKITA SHRIKANT PATHARE | - | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| GSV Vertica | NA | Rs 19.08 cr | Rs 19.08 cr |
| - | NA | Rs 2.00 cr | Rs 2.00 cr |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | CUBIX ARCHITECTS ASSOCIATES |
| Engineer | RATHIS GROUP |
| Chartered Accountant | K J S AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| GSV Ventures | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project has been delayed by few months as we did not get CC for PMC. We have minor work pending at site due to labour shortage, non availibility of construction materials.
Reason as filed by the promoterWe Received the Part OC on 15/10/2025, based on which we have handed over possession. At present, the Allottee is not available for signing. We have received the Full Completion Certificate from Planning Authority on 10/03/2026. delayed by the authority due to technical reasons. But We observed that the number of sanctioned floors and parking details mentioned in our application are incorrect as per the sanctioned plan. We would like to correct these details in the application. we have added Undertaking on 500 stamp for correction.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12502222 | Gautam Madan | GSV Ventures | 04/07/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Jul 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Mar 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Feb 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed155
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 155 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: ARCHITECT CERTIFICATE GSV.pdf | 23 Jul 2026 |
| Withdrawal Update Form 1File: ARCHITECT CERTIFICATE GSV.pdf | 23 Jul 2026 |
| Withdrawal Update Form 2File: ENGINEER CERTIFICATE GSV.pdf | 23 Jul 2026 |
| Withdrawal Update Form 2File: ENGINEER CERTIFICATE GSV.pdf | 23 Jul 2026 |
| Withdrawal Update Form 3File: CHARTERED ACCOUNTANT CERIFICATE GSV_compressed.pdf | 23 Jul 2026 |
| Withdrawal Update Form 3File: CHARTERED ACCOUNTANT CERIFICATE GSV_compressed.pdf | 23 Jul 2026 |
| Form 2A (FY 2024-2025)File: RATHI GROUP FORM 2A.PDF | 23 Jul 2026 |
| Form 2A (FY 2025-2026)File: RATHI GROUP FORM 2A 2.PDF | 23 Jul 2026 |
| Form 1File: GSV Vertica Architect Certificate FORM 1.pdf | 20 Jan 2026 |
| Form 2File: GSV Vertica Engineer Certificate FORM 2.pdf | 20 Jan 2026 |
| Form 3File: GSV Vertica CA Certificate FORM 3_compressed.pdf | 20 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: GSV Vertica Disclosure Of Sold Booked Inventory.pdf | 20 Jan 2026 |
| Form 5 (FY 2024-2025)File: GSV Vertica Form 5.pdf | 24 Nov 2025 |
| Form 1File: GSV Vertica Architect Certificate SEP 2025.pdf | 14 Oct 2025 |
| Form 2File: GSV Vertica Enginner Certificate SEP 2025.pdf | 14 Oct 2025 |
| Form 3File: GSV Vertica CA Certificate SEP 2025.pdf | 14 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: GSV Vertica Disclouser of Sold Unsold SEP 2025.pdf | 14 Oct 2025 |
| Form 1File: GSV Ventures FORM 1.pdf | 3 Aug 2025 |
| Form 2File: GSV Ventures FORM 2.pdf | 3 Aug 2025 |
| Form 3File: GSV Ventures FORM 3.pdf | 3 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclose of sold-booked inventory GSv Vertica.pdf | 3 Aug 2025 |
| Form 1File: Gsv Venture Form 1.pdf | 3 Aug 2025 |
| Form 2File: Form 2 GSV Venture.pdf | 3 Aug 2025 |
| Form 3File: GSV Vertica FORM 3 APRIL.pdf | 3 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclose of sold booked inventory GSV Vertica 35 Sold Units.pdf | 3 Aug 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 27 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 27 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 27 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 27 Jul 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 27 Jul 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 27 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf | 27 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf | 27 Jul 2025 |
| Declaration in FORM BFile: FORM B PROMOTER.pdf | 20 Jul 2025 |
| CERSAI detailsFile: CERSAI DETAILS.pdf | 20 Jul 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST.pdf | 20 Jul 2025 |
| Disclosure for secured/unsecured finance availed for the projectFile: DISCLOSURE OF SECURED AND UNSECURED FINANCE.pdf | 20 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate - GSV Vertica.pdf | 16 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 16 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 16 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure Sold - Unsold List.pdf | 16 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATI.pdf | 26 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ANNUAT REPORT ON STATEMENT OF ACCOUNTS (FORM 5).pdf | 26 Dec 2024 |
| Declaration in FORM BFile: FORM B Promoter - Affidavit Cum Declaration.pdf | 25 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT'S CERTIFICATI.pdf | 25 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD - BOOKED - UNSOLD TNVENTORY.pdf | 25 Dec 2024 |
| CERSAI detailsFile: Declaration - CERSAI Report.pdf | 25 Dec 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration About separate Format A.pdf | 25 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: ENGINEER'S CERTIFICATE FOR QUALITY ASSURANCE (FORM 2A).pdf | 25 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: ENGINEER'S CERTIFICATE FOR QUALITY ASSURANCE (FORM 2A).pdf | 25 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ANNUAT REPORT ON STATEMENT OF ACCOUNTS (FORM 5).pdf | 25 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kharadi cubix.pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kharadi CA certificate.pdf | 19 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: kharadi Form 2 Engineer certificate.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory stmt.pdf | 19 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: kharadi Form 2A Rathi Group.pdf | 19 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Annual Report Form-5.pdf | 19 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form - 1 Architect.pdf | 14 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 14 May 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory stmt.pdf | 14 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3.pdf | 14 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annual Report Form-5.pdf | 4 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annual Report Form-5.pdf | 4 Mar 2024 |
| Building plan approvalFile: plan no1.pdf | 16 Feb 2024 |
| Building plan approvalFile: plan no2.pdf | 16 Feb 2024 |
| Building plan approvalFile: plan no3.pdf | 16 Feb 2024 |
| Building plan approvalFile: plan no4.pdf | 16 Feb 2024 |
| Building plan approvalFile: plan no5.pdf | 16 Feb 2024 |
| Building plan approvalFile: plan no6.pdf | 16 Feb 2024 |
| Building plan approvalFile: plan no7.pdf | 16 Feb 2024 |
| Building plan approvalFile: plan no8.pdf | 16 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: plan no1.pdf | 16 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: plan no2.pdf | 16 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: plan no3.pdf | 16 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: plan no4.pdf | 16 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: plan no5.pdf | 16 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: plan no6.pdf | 16 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: plan no7.pdf | 16 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: plan no8.pdf | 16 Feb 2024 |
| Declaration about Commencement CertificateFile: Cc new.pdf | 16 Feb 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- All 155 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep GSV Vertica on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kharadkar park
NYATI EVANIA
NYATI CONSTRUCTION PRIVATE LIMITED
CENTRALVISTA
NAIKNAVARE DEVELOPERS PVT. LTD.
Guardian Cityscapes Phase-3
Guardian Homes Private Limited
SARASNAGAR
CITY ETHERNAL LLP
PROFITBAY
LAXMI SPACECON LLP
SUN GLORY
Jindal Mittal Graha Nirman Pvt. Ltd.
Builder: GSV Ventures
GSV Ventures has 1 registration on MahaRERA, including GSV Vertica. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What are my rights if GSV Vertica is delayed beyond 30 Sep 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GSV Vertica?
The registered promoter entity is GSV Ventures, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GSV Vertica?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against GSV Vertica?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for GSV Vertica?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GSV Vertica?
The professionals named in the filing: Architect: CUBIX ARCHITECTS ASSOCIATES; Engineer: RATHIS GROUP; Chartered Accountant: K J S AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GSV Vertica?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.