Home / Browse projects / Pune, Maharashtra / GREENVILLE

Registered No litigation declared Commercial project

GREENVILLE

By SHREEJI DEVELOPERS

RG-MH-15447 · RERA P52100024364 · Last updated on MahaRERA portal: 25 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 36 months from the original
31 of 44Construction stages doneacross 4 buildings; furthest along: Installation of Lifts, 70%
19 of 45Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 66 documents Report an error

GREENVILLE is a Commercial project by SHREEJI DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100024364 on 7 Feb 2020. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 26 of the 45 units on this registration are recorded sold or booked, and 31 of 44 construction stages are filed complete.

At a glance

Project

  • NameGREENVILLE
  • TypeCommercial
  • Location
    • SOMATNE KALE COLONY ROAD
    • CHOURAINAGAR
    • Somatane
    • Mawal
    • Pune
    • 410506
  • Pincode410506
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100024364
  • ReraGenie IDRG-MH-15447

Builder

  • NameSHREEJI DEVELOPERS
  • Entity typePartnership
  • PartnersSACHIN SHABU MURHE, POONAM DILIP PATEL
  • Other registrations26 more →
  • Completed11 of 27
  • No longer live4 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects7 →

Key dates

this monthRegisteredFeb 2020First promiseDec 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on7 Feb 2020
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2023)
  • Buildings4 building records
  • Documents filed66 files

Current status

58%26 of 45 units booked
98.0%Work done, per cost certificate

Figures as on 25 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA836612
WING BNA836612
WING CNA836511
WING DNA835510

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 25 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

31 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Installation of Lifts, at 70%.

WING A75%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%
WING B85%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%
WING C85%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%
WING D85%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%

Progress on shared amenities15

As on 25 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes20%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntYes50%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed28

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots28
Closed/Covered28
BuildingClosed/CoveredTotal
WING A77
WING B77
WING C77
WING D77

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,366 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on16 Jan 2026

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI1604.28
Proposed, not sanctioned1,604 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRADHE CAPITAL F11 SECTOR 26 PCNTDA NIGDI PUNE 211044
Estimated costRs 3.42 cr
Cost incurredRs 3.35 cr
Work done98.0%
BuildingWingEstimatedIncurred
WING ANARs 85.50 lakhRs 83.79 lakh
WING BNARs 85.50 lakhRs 83.79 lakh
WING CNARs 85.50 lakhRs 83.79 lakh
WING DNARs 85.50 lakhRs 83.79 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVILAS TARWADI
EngineerSPECTRUM CONSULTANTS
EngineerDEVENG JOSHI
Chartered AccountantBHARAT SHAH
Chartered AccountantPILLAY & ASSOCIATES
PartnerRole in project
SHREEJI DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024495Dec 2023 → Feb 2025

Reason as filed by the promoterWE ARE ALMOST WORK DONE 98% ON SITE WE NEED MORE TIME FOR BUILDING COMPLITION

EXT52100028434Dec 2023 → Dec 2025

Reason as filed by the promoterThe project is currently in its final stages, with approximately 98% of the total work already completed. However, due to certain unforeseen and unavoidable circumstances, a marginal portion-around 2%-of the work remains pending, leading to a delay in the final completion and handover.Minor Finishing Work: A small portion of internal finishing work, including final touches, common area development, and utility installations, required more time due to coordination issues and availability of specialized labor.

EA23012619563Dec 2023 → Dec 2026

Reason as filed by the promoterThe project is currently in its final stage, with approximately 98% of the total work completed. However, a marginal portion of about 2% of the work remains pending, resulting in a slight delay in the final completion and handover. The delay has occurred due to minor finishing and coordination-related works, which required additional time for proper execution. These include final internal finishing touches, completion of common area works, and installation/testing of utilities. The delay was primarily caused by coordination challenges among multiple agencies and the limited availability of spe

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Jan 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Jan 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Jan 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Jan 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed66

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Greenville Form 1(2).pdf25 Jul 2026
Withdrawal Update Form 1File: Q1 FORM 1.pdf25 Jul 2026
Withdrawal Update Form 2File: Greenville Form 2 Engineer Certificate.pdf25 Jul 2026
Withdrawal Update Form 2File: FORM 2 APRIL TO JUNE.pdf25 Jul 2026
Withdrawal Update Form 3File: Greenville Form 3.pdf25 Jul 2026
Withdrawal Update Form 3File: FORM 3 APRIL TO JUNE.pdf25 Jul 2026
Withdrawal Update Form 1File: Q 2 FORM 1 JULY TO SEP.pdf23 Jan 2026
Withdrawal Update Form 1File: GREENVILLE Form1.pdf23 Jan 2026
Withdrawal Update Form 1File: GREENVILLE Form1.pdf23 Jan 2026
Withdrawal Update Form 2File: FORM 2 JULLY TO SEPT.pdf23 Jan 2026
Withdrawal Update Form 2File: GREENVILLE Form2 OCT TO DEC.pdf23 Jan 2026
Withdrawal Update Form 2File: GREENVILLE Form2 OCT TO DEC.pdf23 Jan 2026
Withdrawal Update Form 3File: Q 2 JULY TO SEP Form 3 Greenville.pdf23 Jan 2026
Withdrawal Update Form 3File: Q 3 Form 3 Greenville OCT TO DEC.pdf23 Jan 2026
Withdrawal Update Form 3File: Q 3 Form 3 Greenville OCT TO DEC.pdf23 Jan 2026
Form 2A (FY 2023-2024)File: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24).pdf15 Aug 2025
Form 2A (FY 2024-2025)File: Greenville Form 2A_page-0001.pdf15 Aug 2025
Form 2A (FY 2024-2025)File: Greenville Form 2A_page-0001.pdf15 Aug 2025
Form 1File: Form 1 Greenville.pdf29 Jul 2025
Form 2File: Greenville 2.pdf29 Jul 2025
Form 3File: Greenville 3.pdf29 Jul 2025
Disclosure of Sold and Booked InventoryFile: Greenville Disclosure.pdf29 Jul 2025
Declaration in FORM BFile: Form B Greenville.pdf3 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect certificate Greenville.pdf3 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA certificates Greenville.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Greenville.pdf3 May 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOK.pdf3 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 APRIL TO JUNE.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 JULY TO SEP.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 OCT TO DEC.pdf2 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Greenville Q1 2024.pdf2 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Greenville Q2 2024.pdf2 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 OCT TO DEC.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 APRIL TO JUNE.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 JULT TO SEP.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 OCT TO DEC.pdf2 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)_page-0001.pdf12 Aug 2024
Declaration in FORM BFile: P52100024364_File.pdf5 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Greenville Updated 02 08 2024.pdf2 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 GREENVILLE 23 24.pdf2 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SHREEJI DEV -GREENVILLE FORM 3 JULY EXT.pdf27 Jul 2024
Declaration in FORM BFile: Greenville Affidavit FORM B.pdf22 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCT FORM NO 1 GRRENVILLE.pdf10 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 ENG greenville.pdf10 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A greenville 23 24.pdf10 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A greenville 22 23.pdf10 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A greenville 23 24.pdf10 Jul 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD GRRNVILE JUNE 2024.pdf10 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shreeji - Greenville FORM 3.pdf10 Jul 2024
PAN CardFile: PAN.pdf21 Jan 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: archetect certificate final.PDF15 Jan 2020
Declaration in FORM BFile: RERA DECLARATION.PDF13 Jan 2020
Layout approvalFile: 1 plan layout.PDF9 Jan 2020
Building plan approvalFile: 2 plan.PDF9 Jan 2020
Building plan approvalFile: 3 plan.PDF9 Jan 2020
Building plan approvalFile: 4 plan.PDF9 Jan 2020
Copy of the legal title reportFile: SEARCH121.PDF9 Jan 2020
Details of encumbrancesFile: encumbrances.PDF9 Jan 2020
Copy of Layout Approval (in case of layout)File: 1 plan layout.PDF9 Jan 2020
Building Plan Approval / NA Order for plotted developmentFile: 2 plan.PDF9 Jan 2020
Building Plan Approval / NA Order for plotted developmentFile: 3 plan.PDF9 Jan 2020
Building Plan Approval / NA Order for plotted developmentFile: 4 plan.PDF9 Jan 2020
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf9 Jan 2020
Commencement Certificates / NA Order for plotted developmentFile: NA.pdf9 Jan 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERT - 121.pdf9 Jan 2020
Proforma of Allotment letterFile: ATS GAT_NO_121_1_.pdf9 Jan 2020

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SILVANAG NO 115 P CHOURAINAGAR SOMATNE PHATA MAVAL PUNE54CompletedFeb 2020Dec 2019

How this compares with Pune

58%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 36 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GREENVILLE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHOURAINAGAR13,700+ in Pune

2 kmGREENVILLECompleted 24Lapsed / revoked 18Other 16Dot size: filed unitsN

Filed coordinates, straight-line distance. 58 registered projects within 2 km.

Builder: SHREEJI DEVELOPERS

SHREEJI DEVELOPERS has 27 registrations on MahaRERA, including SAHAJANAND INTEGRITY and SHREEJI DREAMS. Its filings disclose 7 earlier MahaRERA projects: declares 6 of 7 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if GREENVILLE is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GREENVILLE?

The registered promoter entity is SHREEJI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GREENVILLE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GREENVILLE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GREENVILLE?

The professionals named in the filing: Architect: VILAS TARWADI; Engineer: SPECTRUM CONSULTANTS; Engineer: DEVENG JOSHI; Chartered Accountant: BHARAT SHAH; Chartered Accountant: PILLAY & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GREENVILLE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GREENVILLE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GREENVILLE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.