Home / Browse projects / Pune, Maharashtra / GREENVILLE
GREENVILLE
RG-MH-15447 · RERA P52100024364 · Last updated on MahaRERA portal: 25 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 36 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GREENVILLE is a Commercial project by SHREEJI DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100024364 on 7 Feb 2020. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 26 of the 45 units on this registration are recorded sold or booked, and 31 of 44 construction stages are filed complete.
At a glance
Project
- NameGREENVILLE
- TypeCommercial
- Location
- SOMATNE KALE COLONY ROAD
- CHOURAINAGAR
- Somatane
- Mawal
- Pune
- 410506
- Pincode410506
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100024364
- ReraGenie IDRG-MH-15447
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on7 Feb 2020
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2023)
- Buildings4 building records
- Documents filed66 files
Current status
Figures as on 25 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | NA | 8 | 3 | 6 | 6 | 12 |
| WING B | NA | 8 | 3 | 6 | 6 | 12 |
| WING C | NA | 8 | 3 | 6 | 5 | 11 |
| WING D | NA | 8 | 3 | 5 | 5 | 10 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 25 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
31 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Installation of Lifts, at 70%.
WING A75%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
WING B85%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
WING C85%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
WING D85%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
Progress on shared amenities15
As on 25 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 50% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | Yes | 20% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | Yes | 50% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed28
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| WING A | 7 | 7 |
| WING B | 7 | 7 |
| WING C | 7 | 7 |
| WING D | 7 | 7 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| WING A | NA | Rs 85.50 lakh | Rs 83.79 lakh |
| WING B | NA | Rs 85.50 lakh | Rs 83.79 lakh |
| WING C | NA | Rs 85.50 lakh | Rs 83.79 lakh |
| WING D | NA | Rs 85.50 lakh | Rs 83.79 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VILAS TARWADI |
| Engineer | SPECTRUM CONSULTANTS |
| Engineer | DEVENG JOSHI |
| Chartered Accountant | BHARAT SHAH |
| Chartered Accountant | PILLAY & ASSOCIATES |
| Partner | Role in project |
|---|---|
| SHREEJI DEVELOPERS | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWE ARE ALMOST WORK DONE 98% ON SITE WE NEED MORE TIME FOR BUILDING COMPLITION
Reason as filed by the promoterThe project is currently in its final stages, with approximately 98% of the total work already completed. However, due to certain unforeseen and unavoidable circumstances, a marginal portion-around 2%-of the work remains pending, leading to a delay in the final completion and handover.Minor Finishing Work: A small portion of internal finishing work, including final touches, common area development, and utility installations, required more time due to coordination issues and availability of specialized labor.
Reason as filed by the promoterThe project is currently in its final stage, with approximately 98% of the total work completed. However, a marginal portion of about 2% of the work remains pending, resulting in a slight delay in the final completion and handover. The delay has occurred due to minor finishing and coordination-related works, which required additional time for proper execution. These include final internal finishing touches, completion of common area works, and installation/testing of utilities. The delay was primarily caused by coordination challenges among multiple agencies and the limited availability of spe
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 9 Jan 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Jan 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Jan 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Jan 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed66
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Greenville Form 1(2).pdf | 25 Jul 2026 |
| Withdrawal Update Form 1File: Q1 FORM 1.pdf | 25 Jul 2026 |
| Withdrawal Update Form 2File: Greenville Form 2 Engineer Certificate.pdf | 25 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2 APRIL TO JUNE.pdf | 25 Jul 2026 |
| Withdrawal Update Form 3File: Greenville Form 3.pdf | 25 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3 APRIL TO JUNE.pdf | 25 Jul 2026 |
| Withdrawal Update Form 1File: Q 2 FORM 1 JULY TO SEP.pdf | 23 Jan 2026 |
| Withdrawal Update Form 1File: GREENVILLE Form1.pdf | 23 Jan 2026 |
| Withdrawal Update Form 1File: GREENVILLE Form1.pdf | 23 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 JULLY TO SEPT.pdf | 23 Jan 2026 |
| Withdrawal Update Form 2File: GREENVILLE Form2 OCT TO DEC.pdf | 23 Jan 2026 |
| Withdrawal Update Form 2File: GREENVILLE Form2 OCT TO DEC.pdf | 23 Jan 2026 |
| Withdrawal Update Form 3File: Q 2 JULY TO SEP Form 3 Greenville.pdf | 23 Jan 2026 |
| Withdrawal Update Form 3File: Q 3 Form 3 Greenville OCT TO DEC.pdf | 23 Jan 2026 |
| Withdrawal Update Form 3File: Q 3 Form 3 Greenville OCT TO DEC.pdf | 23 Jan 2026 |
| Form 2A (FY 2023-2024)File: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24).pdf | 15 Aug 2025 |
| Form 2A (FY 2024-2025)File: Greenville Form 2A_page-0001.pdf | 15 Aug 2025 |
| Form 2A (FY 2024-2025)File: Greenville Form 2A_page-0001.pdf | 15 Aug 2025 |
| Form 1File: Form 1 Greenville.pdf | 29 Jul 2025 |
| Form 2File: Greenville 2.pdf | 29 Jul 2025 |
| Form 3File: Greenville 3.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Greenville Disclosure.pdf | 29 Jul 2025 |
| Declaration in FORM BFile: Form B Greenville.pdf | 3 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect certificate Greenville.pdf | 3 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA certificates Greenville.pdf | 3 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Greenville.pdf | 3 May 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOK.pdf | 3 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 APRIL TO JUNE.pdf | 2 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 JULY TO SEP.pdf | 2 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 OCT TO DEC.pdf | 2 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Greenville Q1 2024.pdf | 2 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Greenville Q2 2024.pdf | 2 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 OCT TO DEC.pdf | 2 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 APRIL TO JUNE.pdf | 2 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 JULT TO SEP.pdf | 2 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 OCT TO DEC.pdf | 2 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)_page-0001.pdf | 12 Aug 2024 |
| Declaration in FORM BFile: P52100024364_File.pdf | 5 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Greenville Updated 02 08 2024.pdf | 2 Aug 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 GREENVILLE 23 24.pdf | 2 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SHREEJI DEV -GREENVILLE FORM 3 JULY EXT.pdf | 27 Jul 2024 |
| Declaration in FORM BFile: Greenville Affidavit FORM B.pdf | 22 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCT FORM NO 1 GRRENVILLE.pdf | 10 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 ENG greenville.pdf | 10 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A greenville 23 24.pdf | 10 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A greenville 22 23.pdf | 10 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A greenville 23 24.pdf | 10 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD GRRNVILE JUNE 2024.pdf | 10 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shreeji - Greenville FORM 3.pdf | 10 Jul 2024 |
| PAN CardFile: PAN.pdf | 21 Jan 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: archetect certificate final.PDF | 15 Jan 2020 |
| Declaration in FORM BFile: RERA DECLARATION.PDF | 13 Jan 2020 |
| Layout approvalFile: 1 plan layout.PDF | 9 Jan 2020 |
| Building plan approvalFile: 2 plan.PDF | 9 Jan 2020 |
| Building plan approvalFile: 3 plan.PDF | 9 Jan 2020 |
| Building plan approvalFile: 4 plan.PDF | 9 Jan 2020 |
| Copy of the legal title reportFile: SEARCH121.PDF | 9 Jan 2020 |
| Details of encumbrancesFile: encumbrances.PDF | 9 Jan 2020 |
| Copy of Layout Approval (in case of layout)File: 1 plan layout.PDF | 9 Jan 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: 2 plan.PDF | 9 Jan 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: 3 plan.PDF | 9 Jan 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: 4 plan.PDF | 9 Jan 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 9 Jan 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: NA.pdf | 9 Jan 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERT - 121.pdf | 9 Jan 2020 |
| Proforma of Allotment letterFile: ATS GAT_NO_121_1_.pdf | 9 Jan 2020 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SILVANA | G NO 115 P CHOURAINAGAR SOMATNE PHATA MAVAL PUNE | 54 | Completed | Feb 2020 | Dec 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 26 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 66 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep GREENVILLE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near CHOURAINAGAR13,700+ in Pune
Filed coordinates, straight-line distance. 58 registered projects within 2 km.
Everland
EVITA KRISALA TOWNSHIP LLP
EVERLYN
EVITA KRISALA TOWNSHIP LLP
ABHIMAAN HOMES PHASE 3
RISING PROPCON LLP
SURABHI CITY PHASE 1
Surabhi Group
ROHAN ANAND PHASE I
ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITE
Urban Life Phase 1
Kakade Vtp Associates
Builder: SHREEJI DEVELOPERS
SHREEJI DEVELOPERS has 27 registrations on MahaRERA, including SAHAJANAND INTEGRITY and SHREEJI DREAMS. Its filings disclose 7 earlier MahaRERA projects: declares 6 of 7 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if GREENVILLE is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GREENVILLE?
The registered promoter entity is SHREEJI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GREENVILLE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GREENVILLE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GREENVILLE?
The professionals named in the filing: Architect: VILAS TARWADI; Engineer: SPECTRUM CONSULTANTS; Engineer: DEVENG JOSHI; Chartered Accountant: BHARAT SHAH; Chartered Accountant: PILLAY & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GREENVILLE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback