ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Greens - Oak - OP

Registered No litigation declared Residential / Group Housing project

Greens - Oak - OP

By AMJ Land Developers

RG-MH-47650 · RERA P52100053285 · Last updated on MahaRERA portal: 15 Jul 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 3 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 95%
4 of 128Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 104 documents Report an error

Greens - Oak - OP is a Residential / Group Housing project by AMJ Land Developers in Pune, Maharashtra, registered with MahaRERA as P52100053285 on 23 Oct 2023. Possession is promised by 31 Dec 2027. 124 of the 128 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameGreens - Oak - OP
  • TypeResidential / Group Housing
  • Location
    • Aditya Birla Hospital Road
    • Chinchwad
    • Thergaon
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100053285
  • ReraGenie IDRG-MH-47650

Builder

  • NameAMJ Land Developers
  • Entity typePartnership
  • Other registrations3 more →
  • Completed2 of 4
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredOct 2023PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Oct 2023
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed104 files

Current status

97%124 of 128 units booked
53.0%Work done, per cost certificate

Figures as on 15 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Greens - Oak - OPNA19161280128

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 95%.

Greens - Oak - OP: 37% average across the applicable activities

ActivityProgress
Excavation95%
Basement (if any)0%
Podiums (if any)45%
Plinth95%
Stilt Floor68%
Slabs of Super Structure83%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises4%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.7%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.5%

Progress on shared amenities15

As on 15 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes88%
Water SupplyYes88%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes88%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes88%
Street LightingYes80%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes88%
Solid Waste Management And DisposalYes88%
Water conservation /Rain water harvestingYes88%
Energy managemcntYes80%
Fire protection and fire safety requirementsYes88%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes88%

Parking filed595

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots595
Closed/Covered192
Open Space403

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,167 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
AMJ Land Holdings Ltd.ThergaonPune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI20360.52
Proposed, not sanctioned19,361 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 1, 2 and 3, Ground Floor, Elpro Commercial Complex, Plot No 4270, Veer Savarkar Rd, Pimpri C
Estimated costRs 60.73 cr
Cost incurredRs 32.21 cr
Work done53.03%
BuildingWingEstimatedIncurred
Greens - Oak - OPNARs 48.19 crRs 24.99 cr
-NARs 12.54 crRs 7.21 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSubhash Shah
ArchitectKanchan Atmaram Gajeshwar
EngineerStrudcom consultants Pvt. Ltd.
EngineerShridhar Vidwans
Chartered AccountantRajeev Arvind Karandikar
Chartered AccountantAniruddha Angal
PartnerRole in project
AMJ Land Developers-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Sep 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Aug 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Aug 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed104

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 104 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Architect Certificate Jun 26.pdf15 Jul 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate Jun 26.pdf15 Jul 2026
Withdrawal Update Form 3File: Form 3 CA Certificate Jun 26.pdf15 Jul 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate Mar 26.pdf17 Apr 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate Mar 26.pdf17 Apr 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate Mar 26.pdf17 Apr 2026
Withdrawal Update Form 2File: Form 2 Engineers Certificate Mar 26.pdf17 Apr 2026
Withdrawal Update Form 2File: Form 2 Engineers Certificate Mar 26.pdf17 Apr 2026
Withdrawal Update Form 2File: Form 2 Engineers Certificate Mar 26.pdf17 Apr 2026
Withdrawal Update Form 3File: CA Certificate.pdf17 Apr 2026
Withdrawal Update Form 3File: Form 3 CA Certificate Mar 26.pdf17 Apr 2026
Withdrawal Update Form 3File: Form 3 CA Certificate Mar 26.pdf17 Apr 2026
Withdrawal Update Form 1File: Architect Certificate.pdf20 Jan 2026
Withdrawal Update Form 2File: Engineers Certificate.pdf20 Jan 2026
Withdrawal Update Form 3File: CA Certificate.pdf20 Jan 2026
Withdrawal Update Form 1File: Architectu0027s Certificate Form1 OP_September 2025.pdf2 Dec 2025
Withdrawal Update Form 2File: Engineeru0027s Certificate Form-2 OP_September 2025.pdf2 Dec 2025
Withdrawal Update Form 3File: CA Certificate Form-3 OP_September 2025.pdf2 Dec 2025
Withdrawal Update Form 1File: Architectu0027s Certificate Form1 OP_June 2025.pdf21 Aug 2025
Withdrawal Update Form 2File: Engineeru0027s Certificate Form-2 OP_June 2025.pdf21 Aug 2025
Withdrawal Update Form 3File: CA Certificate Form-3 OP_June 2025.pdf21 Aug 2025
Form 1File: Architect's Certificate Form1 December 2023.pdf19 Aug 2025
Form 2File: Engineer's Certificate Form-2 December 2023.pdf19 Aug 2025
Form 3File: CA Certificate Form-3 December 2023.pdf19 Aug 2025
Disclosure of Sold and Booked InventoryFile: Booked Inventory Declaration December 2023.pdf19 Aug 2025
Form 1File: Architect's Certificate Form1 OP Mar 2024.pdf19 Aug 2025
Form 2File: Engineer's Certificate Form-2 OP_Mar 2024_0001.pdf19 Aug 2025
Form 3File: CA Certificate Form-3 OP Mar 2024.pdf19 Aug 2025
Disclosure of Sold and Booked InventoryFile: Booked Inventory Declaration OP Mar 2024.pdf19 Aug 2025
Form 1File: Architect's Certificate Form1 OP June 2024.pdf19 Aug 2025
Form 2File: Engineer's Certificate Form-2 OP June 2024.pdf19 Aug 2025
Form 3File: CA Certificate Form-3 OP June 2024.pdf19 Aug 2025
Disclosure of Sold and Booked InventoryFile: Booked Inventory Declaration OP June 2024.pdf19 Aug 2025
Form 1File: Architect's Certificate Form1 OP September 2024.pdf19 Aug 2025
Form 2File: Engineer's Certificate Form-2 OP September 2024.pdf19 Aug 2025
Form 3File: CA Certificate Form-3 OP September 2024.pdf19 Aug 2025
Disclosure of Sold and Booked InventoryFile: Booked Inventory Declaration OP September 2024.pdf19 Aug 2025
Form 1File: Architect's Certificate Form1 OP December 2024.pdf19 Aug 2025
Form 2File: Engineer's Certificate Form-2 OP December 2024.pdf19 Aug 2025
Form 3File: CA Certificate Form-3 OP _December 2024.pdf19 Aug 2025
Disclosure of Sold and Booked InventoryFile: Booked Inventory Declaration OP_December 2024.pdf19 Aug 2025
Form 1File: Architect's Certificate Form1 OP Mar 2024.pdf19 Aug 2025
Form 2File: Engineer's Certificate Form-2 OP_Mar 2024_0001.pdf19 Aug 2025
Form 3File: CA Certificate Form-3 OP Mar 2024.pdf19 Aug 2025
Disclosure of Sold and Booked InventoryFile: Booked Inventory Declaration OP Mar 2024.pdf19 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Form1 OP December 2024.pdf13 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form-3 OP _December 2024.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Form-2 OP December 2024.pdf13 Jan 2025
Disclosure of sold/ booked inventoryFile: Booked Inventory Declaration OP_December 2024.pdf13 Jan 2025
CERSAI detailsFile: CERSAI_Search_Report_200322820133_December 2024.pdf13 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Form1 OP September 2024.pdf11 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form-3 OP September 2024.pdf11 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Form-2 OP September 2024.pdf11 Oct 2024
Disclosure of sold/ booked inventoryFile: Booked Inventory Declaration OP September 2024.pdf11 Oct 2024
CERSAI detailsFile: CERSAI_Search_Report_200322820133_September 2024.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Form1 OP June 2024.pdf10 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Form-2 OP June 2024.pdf10 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer's Quality Certificate 2A OP_Mar 2024_0001.pdf10 Jul 2024
Disclosure of sold/ booked inventoryFile: Booked Inventory Declaration OP June 2024.pdf10 Jul 2024
CERSAI detailsFile: CERSAI_Search_Report_200313048199_June 2024.pdf10 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form-3 OP June 2024.pdf10 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Building OP Form No 5FY23-24.pdf10 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Form1 OP Mar 2024.pdf12 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Form-2 OP_Mar 2024_0001.pdf12 Apr 2024
CERSAI detailsFile: CERSAI_Search_Report_200303522757_March24 Building OP.pdf12 Apr 2024
Disclosure of sold/ booked inventoryFile: Booked Inventory Declaration OP Mar 2024.pdf12 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form-3 OP Mar 2024.pdf12 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Form1 December 2023.pdf12 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate Form-2 December 2023.pdf12 Jan 2024
CERSAI detailsFile: Cersai December 23.pdf12 Jan 2024
Disclosure of sold/ booked inventoryFile: Booked Inventory Declaration December 2023.pdf12 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form-3 December 2023.pdf12 Jan 2024
Details of encumbrances concerned to FinanceFile: Final No Encumbrance- Legal-Greens oak op.pdf3 Oct 2023
Details of encumbrances concerned to LegalFile: Final No Encumbrance- Legal-Greens oak op.pdf3 Oct 2023
Other - LegalFile: Latest Deed of Reconstitutional of Partnership.pdf3 Oct 2023
Copy of the legal title reportFile: Explanatory Note (1).pdf5 Sep 2023
CERSAI detailsFile: Cersai Declaration- Greens-Oak-OP.pdf5 Sep 2023
Other - LegalFile: Explanatory Note (1).pdf5 Sep 2023
Other - TechnicalFile: Explanatory Note (1).pdf5 Sep 2023
Other - TechnicalFile: Declaration for Plot Area to Legal department_0001.pdf24 Aug 2023

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Greens - Cypress - MNP52100030119Chinchwad, Pune-Jul 2021Certificate SignedDec 2025Not delivered
Greens CentreCTS No 5401 Opp PPPML Thergaon Chinchwad Pune - 41103359-CompletedJun 2019Jun 2019
Greens - Beech GHCTS No 5401 Opp PPPML Thergaon Chinchwad Pune - 411033124-CompletedOct 2018May 2018
Greens - Phase - ICTS No. 5401 Opp. PPPML Thergaon Chinchwad Pune - 411033470-CompletedSep 2015Sep 2015

How this compares with Pune

97%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Greens - Oak - OP on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chinchwad13,700+ in Pune

2 kmGreens - Oak - OPCompleted 53Lapsed / revoked 40Other 37Dot size: filed unitsN

Filed coordinates, straight-line distance. 130 registered projects within 2 km.

Builder: AMJ Land Developers

AMJ Land Developers has 4 registrations on MahaRERA, including Greens - Beech - GH and Greens Centre. Its filings disclose 4 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Greens - Oak - OP is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Greens - Oak - OP?

The registered promoter entity is AMJ Land Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Greens - Oak - OP?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Greens - Oak - OP?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Greens - Oak - OP?

The professionals named in the filing: Architect: Subhash Shah; Architect: Kanchan Atmaram Gajeshwar; Engineer: Strudcom consultants Pvt. Ltd.; Engineer: Shridhar Vidwans; Chartered Accountant: Rajeev Arvind Karandikar; Chartered Accountant: Aniruddha Angal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Greens - Oak - OP?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Greens - Oak - OP. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Greens - Oak - OP to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.