Home / Browse projects / Thane, Maharashtra / GREEN VALLEY PHASE I
GREEN VALLEY PHASE I
RG-MH-03125 · RERA P51700020467 · Last updated on MahaRERA portal: 10 Feb 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 18 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GREEN VALLEY PHASE I is a Others project by GREEN DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700020467 on 15 Apr 2019. Possession was promised by 1 Apr 2025 and is now 18 months past that date.
At a glance
Project
- NameGREEN VALLEY PHASE I
- TypeOthers
- Location
- MOULANA AZAD ROAD
- NAROTTAM NAGAR
- Thane (M Corp.)
- Thane
- 400612
- Pincode400612
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700020467
- ReraGenie IDRG-MH-03125
Builder
- NameGREEN DEVELOPERS
- Entity typePartnership
- PartnersMUSTAFA GAFFAR PATEL, GANI GAFFAR PATEL
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on15 Apr 2019
- Promised completion1 Apr 2025
- Revised completionNone
- Buildings2 building records
- Documents filed68 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING A2 | NA | 26 | 0 | 0 | 0 | 0 |
| BUILDING EWS/LIG B1 | NA | 8 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 10 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 88%.
BUILDING A253%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 88% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 43% |
| Sanitary Fittings within the flats / premises | 10% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 25% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 14% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING EWS/LIG B10%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 10 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed30
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SANDEEP PRABHU |
| Engineer | ANAND KULKARNI |
| Chartered Accountant | Shashank R Jain & Associates |
| Partner | Role in project |
|---|---|
| GREEN DEVELOPERS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 10 Apr 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 10 Apr 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 10 Apr 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 10 Apr 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed68
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: Form 3 Green Valley_Phase 1.pdf | 10 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects certificate.pdf | 7 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate.pdf | 7 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 08 Oct 2024.pdf | 19 Oct 2024 |
| Certificates of CA (Form 3)File: Form -3 final.pdf | 19 Oct 2024 |
| Certificates of CA (Form 3)File: Form -3 final.pdf | 19 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA Form 2-pages (1).pdf | 19 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Green Valley Phase I 23-24-merged.pdf | 15 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Green Valley 30062024.pdf | 23 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 Green Valley 30062024.pdf | 23 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Rera form 30th june 2024.pdf | 22 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A.pdf | 27 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A 23-24.pdf | 27 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf | 31 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Green Valley 3103204.pdf | 2 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Green Valley 31032024.pdf | 2 May 2024 |
| Certificates of CA (Form 3)File: Form 3 Green Developers 31032024 compressed.pdf | 2 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 31122023.pdf | 19 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate 31122023.pdf | 19 Jan 2024 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate 31122023_Uploaded.pdf | 19 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Green Developers Final.pdf | 15 Jan 2024 |
| Certificates of CA (Form 3)File: Form-3 30092023 with sign_compressed.pdf | 2 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form - 1 Architect Certificate 30092023.pdf | 1 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate 30092023.pdf | 1 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf | 1 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 300623.pdf | 30 Aug 2023 |
| Certificates of CA (Form 3)File: Form 3 Green Valley 30062023 signed_compressed.pdf | 30 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4 Green Developers.pdf | 21 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q4 Green Developers.pdf | 21 Apr 2023 |
| Certificates of CA (Form 3)File: Scanned Copy Form 3 Green Valley Merged_compressed.pdf | 21 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1_Phase-1_Q3.pdf | 7 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2_Phase-1_Q3.pdf | 7 Feb 2023 |
| Certificates of CA (Form 3)File: Form-3_Phase-1_Q3_Compressed.pdf | 7 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA FORM-1_compressed.pdf | 21 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rera Form 2.pdf | 21 Oct 2022 |
| Certificates of CA (Form 3)File: FORM-3_compressed (1).pdf | 21 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form-5.pdf | 20 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_compressed.pdf | 20 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Green Valley_30062022_compressed.pdf | 20 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Disclosure_Green Valley_30062022_compressed.pdf | 20 Jul 2022 |
| Certificates of CA (Form 3)File: Form 3_Green valley_30062022_compressed.pdf | 20 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_31032022_compressed.pdf | 30 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 30 Apr 2022 |
| Certificates of CA (Form 3)File: Form 3 _compressed.pdf | 30 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer Certificate (03-01-2022) Signed.pdf | 9 Mar 2022 |
| CERSAI detailsFile: CERSAI Report.pdf | 8 Mar 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_30062021.pdf | 7 Mar 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_30092021.pdf | 7 Mar 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_31122021_compressed.pdf | 7 Mar 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_30062021.pdf | 7 Mar 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_30092021.pdf | 7 Mar 2022 |
| Certificates of CA (Form 3)File: Form 3 - 30062021 signed_compressed.pdf | 7 Mar 2022 |
| Certificates of CA (Form 3)File: Form 3_30092021_Signed_compressed.pdf | 7 Mar 2022 |
| Certificates of CA (Form 3)File: Form 3_31122021_compressed.pdf | 7 Mar 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Green Developers - Final 2020-21.pdf | 5 Jan 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: GREEN DEVELOPERS FORM-5.pdf | 30 Sep 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_GREEN VALLEY.pdf | 12 Aug 2021 |
| Certificates of CA (Form 3)File: CA FORM 3.pdf | 11 Apr 2019 |
| Building plan approvalFile: IOD.pdf | 10 Apr 2019 |
| Layout approvalFile: LAYOUT PLAN.pdf | 10 Apr 2019 |
| PAN CardFile: PAN CARD.pdf | 10 Apr 2019 |
| Copy of the legal title reportFile: LEGAL TITLE REPORT.pdf | 10 Apr 2019 |
| Details of encumbrancesFile: ENCUMBERANCE CERTIFICATE.pdf | 10 Apr 2019 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf | 10 Apr 2019 |
| Building Plan Approval (IOD)File: IOD.pdf | 10 Apr 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf | 10 Apr 2019 |
| Declaration in FORM BFile: FORM B.pdf | 10 Apr 2019 |
| Proforma of Allotment letterFile: ALLOTMENT_AGREEMENT.pdf | 10 Apr 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 68 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep GREEN VALLEY PHASE I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NAROTTAM NAGAR7,600+ in Thane
Filed coordinates, straight-line distance. 54 registered projects within 2 km.
DOSTI PLANET NORTH - SECTOR 3
CHALAMA INFRAPROPERTIES PRIVATE LIMITED
NICE WORLD 1
NICE BUILDERS
CENTRAL PARK
HARMAIN ENTERPRISES
MUKTA GHARONDA
SKYLARK INFRASTRUCTURES
Palm Riveria
YES REALTY
Trinity Paradise Phase 1
Trinity Builders
See every Thane project, with the district possession charts
Builder: GREEN DEVELOPERS
GREEN DEVELOPERS has 1 registration on MahaRERA, including GREEN VALLEY PHASE I. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that GREEN VALLEY PHASE I shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if GREEN VALLEY PHASE I is delayed beyond 1 Apr 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GREEN VALLEY PHASE I?
The registered promoter entity is GREEN DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GREEN VALLEY PHASE I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GREEN VALLEY PHASE I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GREEN VALLEY PHASE I?
The professionals named in the filing: Architect: SANDEEP PRABHU; Engineer: ANAND KULKARNI; Chartered Accountant: Shashank R Jain & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GREEN VALLEY PHASE I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback