GREEN VALLEY
RG-MH-97012 · RERA P51700017701 · Last updated on MahaRERA portal: 9 May 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 48 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GREEN VALLEY is a Others project by M S DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700017701 on 6 Sep 2018. Possession is promised by 31 Dec 2027. The completion date has moved by 48 months from the original filing.
At a glance
Project
- NameGREEN VALLEY
- TypeOthers
- Location
- KALYAN MURBAD ROAD
- KAMBA
- Kalyan
- Thane
- 421301
- Pincode421301
- RERA no.P51700017701
- ReraGenie IDRG-MH-97012
Builder
- NameM S DEVELOPERS
- Entity typePartnership
- PartnersSUNIL GAURISHANKAR PATHAK, RAJENDRASINGH UMEEDSINGH SHEKHAWAT, RAJENDRA DAULAT JADHAV, GAJENDRASINGH RAJENDRASINGH SHEKHAWAT, PRADEEP ANANTA GAIKWAD, HANUMAN SAKHARAM MHATRE, YOGESH SURESH SHINDE, PURUSHOTTAM BAJRNAGLAL SAINI
- Other registrations3 more →
- No longer live3 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on6 Sep 2018
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 30 Dec 2023)
- Buildings5 building records
- Documents filed89 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| LOTUS | NA | 22 | 0 | 0 | 0 | 0 |
| ORCHID | NA | 15 | 0 | 0 | 0 | 0 |
| LILY | NA | 8 | 0 | 0 | 0 | 0 |
| ROSE | NA | 22 | 0 | 0 | 0 | 0 |
| CLOVER | NA | 15 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 9 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
21 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Internal walls, at 96%.
LOTUS27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
ORCHID72%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 96% |
| Sanitary Fittings within the flats / premises | 70% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
LILY66%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 10% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
ROSE27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
CLOVER66%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 9 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed75
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| LOTUS | 0 | 14 | 14 |
| ORCHID | 0 | 10 | 10 |
| LILY | 0 | 3 | 3 |
| ROSE | 14 | 14 | 28 |
| CLOVER | 10 | 10 | 20 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DE CON CONSULTANT |
| Engineer | A N AGASHE |
| Partner | Role in project |
|---|---|
| M S DEVELOPERS | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe completion of project is delayed due to manpower shortage created during and post Pandemic COVID-19. Due to reverse migration of laborers to their native places and break in supply chain of construction material have adversely impacted the construction activities. Further due to financial crisis because of low booking and less realization of receipts from customers there has been funds shortage as raising of funds have been a problem. Currently the construction is going in full swing and work is progressing rapidly and we are expecting the project to be completed in the extended period of
Reason as filed by the promoterOur project comprises of five buildings, of which the construction work of two buildings is nearly complete as can be seen from the Architects Certificate issued in Form-1 dated 31.03.2025. However, certain critical and unforeseen challenges have significantly impacted our ability to complete the remaining work within the earlier approved timeline. The following key factors have contributed to the delay: 1. Change in Partnership Structure: Initially, there were nine partners in the firm. However, w.e.f. Jul’22, only two partners remain, as the rest have exited the partnership. This has resulte
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 23 Aug 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 23 Aug 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 22 Aug 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 10 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed89
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Other - LegalFile: DeclarationletterforCompletionwithAnnx-signed_compressed.pdf | 9 May 2025 |
| Certificates of CA (Form 3)File: Form3-MSDev-Mar25-signed.pdf | 2 May 2025 |
| Disclosure of sold/ booked inventoryFile: Soldunsoldinventory-31032025.pdf | 2 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-5_msdev_Mar25-signed.pdf | 2 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_MSDev_Mar'25-signed.pdf | 20 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2_KAMBA PERCENTAGE COMPLETION MARCH25.pdf | 20 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2A_MSDev_Mar'25_compressed.pdf | 20 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: SoldUnsoldinvetory_31122024.pdf | 4 Apr 2025 |
| Declaration in FORM BFile: Form B Affidavit Jan 2025_500stamp.pdf | 19 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: inventory 31-12-2024_compressed.pdf | 11 Mar 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other projects_merged.pdf | 11 Mar 2025 |
| Details of encumbrances concerned to FinanceFile: Encumbrance Certificate.pdf | 8 Mar 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A_Separate bank Account declaration.pdf | 8 Mar 2025 |
| Deviation Report with respect to Allotment letterFile: Self Declaration with regards to deviation report Allotment letter.pdf | 8 Mar 2025 |
| Details of encumbrances concerned to LegalFile: Encumbrance Certificate.pdf | 8 Mar 2025 |
| Deviation Report with respect to model copy of AgreementFile: Self Declaration with regards to deviation report agreement for sale.pdf | 8 Mar 2025 |
| CERSAI detailsFile: Green Valley.pdf | 7 Mar 2025 |
| Proforma of Agreement for saleFile: RERA AGREEMENT FOR SALE OF FLAT Green VAlley.pdf | 7 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3_MSDevl_Jun24-SINGED-COMPRESSED.pdf | 3 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3_MSDevl_Sep24-SIGNED_compressed.pdf | 3 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3_MSDevl_Dec24-SIGNED_compressed.pdf | 3 Mar 2025 |
| Declaration in FORM BFile: Form B Affidavit Jan 2025.pdf | 27 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form No1 30092024.pdf | 27 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form No1 31-12-2024.pdf | 27 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- KAMBA PERCENTAGE COMPLETION JUNE-24.pdf | 27 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_KAMBA Sep24.pdf | 27 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2 KAMBA DEC-24.pdf | 27 Feb 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: CC Lotus Rose_compressed.pdf | 10 Nov 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC Clover,Orchid _compressed.pdf | 10 Nov 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC Lily_compressed.pdf | 10 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form No1 30062024.pdf | 9 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A2024-MAR24.pdf | 9 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory details_Mar24.pdf | 6 Aug 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form No1 31032024.pdf | 12 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 12 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A 2024.pdf | 12 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 31032024 signed.pdf | 12 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY2023-24.pdf | 12 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory details_Jan'24.pdf | 26 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form No1 Dec23.pdf | 25 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_RERA_DEC23.pdf | 25 Feb 2024 |
| Certificates of CA (Form 3)File: form3_msdev_jun23.pdf | 25 Feb 2024 |
| Certificates of CA (Form 3)File: form3_msdev_sep23.pdf | 25 Feb 2024 |
| Certificates of CA (Form 3)File: form3_msdev_dec23.pdf | 25 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Scan Copy of Signed Form 5.pdf | 27 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A 2020.pdf | 26 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A 2021.pdf | 26 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A 2022.pdf | 26 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A 2023.pdf | 26 Jan 2024 |
| Declaration in FORM BFile: FormB_affidavite cum declaration.pdf | 23 Jan 2024 |
| Declaration about Commencement CertificateFile: Form D.pdf | 18 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory details_Mar'23.pdf | 18 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form no1 2020.pdf | 17 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form No1 2021.pdf | 17 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form No1 2022.pdf | 17 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form No1 2023.pdf | 17 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form No1 Sep23.pdf | 17 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2RERA_SEPT-23.pdf | 8 Jan 2024 |
| Certificates of CA (Form 3)File: Form3_Mar'23_MSDev.pdf | 8 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form5_Signed_MSDev_Mar'23.pdf | 8 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1Engineer Certificate_Final_Mar20toMar23.pdf | 13 Jun 2023 |
| Certificates of CA (Form 3)File: form3_msdev_mar19_.pdf | 13 Jun 2023 |
| Certificates of CA (Form 3)File: form3_msdev_mar20_.pdf | 13 Jun 2023 |
| Certificates of CA (Form 3)File: Form3_msdev_mar21_.pdf | 13 Jun 2023 |
| Certificates of CA (Form 3)File: Form3_msdev_mar22_.pdf | 13 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form5_msdev_FY2018-19.pdf | 13 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: form5_msdev_FY2019-20.pdf | 13 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form5_msdev_fy 20-21.pdf | 13 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5_msdev_fy21-22.pdf | 13 Jun 2023 |
| Proforma of Allotment letterFile: agreement for sale (1).pdf | 5 Sep 2018 |
| Layout approvalFile: CLOVER PLAN.pdf | 23 Aug 2018 |
| Layout approvalFile: LILY PLAN.pdf | 23 Aug 2018 |
| Layout approvalFile: ROSE PLAN.pdf | 23 Aug 2018 |
| Copy of the legal title reportFile: Title.pdf | 23 Aug 2018 |
| Details of encumbrancesFile: encumbrances.pdf | 23 Aug 2018 |
| Copy of Layout Approval (in case of layout)File: CLOVER PLAN.pdf | 23 Aug 2018 |
| Copy of Layout Approval (in case of layout)File: LILY PLAN.pdf | 23 Aug 2018 |
| Copy of Layout Approval (in case of layout)File: ROSE PLAN.pdf | 23 Aug 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: NAGAR RACHANA 1118.pdf | 23 Aug 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: NAGAR RACHANA 1123.pdf | 23 Aug 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations, which the RERA portal never shows together
- All 89 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep GREEN VALLEY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KAMBA7,600+ in Thane
PODDAR RIVIERA PHASE - I
Poddar Housing and Development Limited
Sinhagad by Bhagwati Haware - Wing - B
Bhagwati Haware Properties Supertech
Pratapgad by Bhagwati Haware - Wing - C
Bhagwati Haware Properties Supertech
Rajgad by Bhagwati Haware - Wing - D
Bhagwati Haware Properties Supertech
PODDAR RIVIERA PHASE - III
Poddar Housing and Development Limited
THARWANI PARKGLEN PHASE I
THARWANI REALTORS
See every Thane project, with the district possession charts
Builder: M S DEVELOPERS
M S DEVELOPERS has 4 registrations on MahaRERA, including GREEN VALLEY and Moosa Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if GREEN VALLEY is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GREEN VALLEY?
The registered promoter entity is M S DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GREEN VALLEY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GREEN VALLEY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GREEN VALLEY?
The professionals named in the filing: Architect: DE CON CONSULTANT; Engineer: A N AGASHE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GREEN VALLEY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.