Home / Browse projects / Thane, Maharashtra / GREEN TOUCH BUILDING NO 2
GREEN TOUCH BUILDING NO 2
By SHREE VAKRATUNDA BUILDERS & DEVELOPERS
RG-MH-78387 · RERA P51700033633 · Last updated on MahaRERA portal: 12 Feb 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GREEN TOUCH BUILDING NO 2 is a Residential / Group Housing project by SHREE VAKRATUNDA BUILDERS & DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700033633 on 2 Mar 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date. 32 of the 32 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.
At a glance
Project
- NameGREEN TOUCH BUILDING NO 2
- TypeResidential / Group Housing
- Location
- NEAR HANUMAN MANDIR
- BADLAPUR WEST
- Rahatoli
- Ambarnath
- Thane
- 421503
- Pincode421503
- RERA no.P51700033633
- ReraGenie IDRG-MH-78387
Builder
- NameSHREE VAKRATUNDA BUILDERS & DEVELOPERS
- Entity typePartnership
- PartnerSAMEER DASHRATH BHANDARI
- PartnerSOMNATH DASHRATH BHANDARI
- Other registrations1 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on2 Mar 2022
- Promised completion31 Dec 2025
- Revised completionNone
- Buildings1 building record
- Documents filed72 files
Current status
Figures as on 12 Feb 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GREEN TOUCH BUILDING NO 2 | NA | 10 | 8 | 32 | 0 | 32 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 12 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
GREEN TOUCH BUILDING NO 2: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 12 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed25
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| GREEN TOUCH BUILDING NO 2 | NA | Rs 3.05 cr | Rs 3.05 cr |
| - | NA | Rs 5.78 lakh | Rs 5.78 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SANDEEP PATIL |
| Engineer | AARNA STRUCTURAL CONSULTANTS |
| Chartered Accountant | NILESH A PATKI |
| Chartered Accountant | RAVIRAJ B DANGE AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| SHREE VAKRATUNDA BUILDERS & DEVELOPERS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Feb 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Feb 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Feb 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 14 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed72
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1 BLDG NO 2.pdf | 12 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2 BLDG NO 2.pdf | 12 Feb 2026 |
| Withdrawal Update Form 3File: FORM 3.pdf | 12 Feb 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 26 Nov 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 26 Nov 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 26 Nov 2025 |
| Form 5 (FY 2024-2025)File: Form 5 Bldg no 2.pdf | 18 Sep 2025 |
| Form 1File: Form 1 Bldg no 2.pdf | 19 Jul 2025 |
| Form 2File: Form 2 Bldg No 2.pdf | 19 Jul 2025 |
| Form 3File: Form 3 Vakratund Bldg No 2.pdf | 19 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Bldg 2.pdf | 19 Jul 2025 |
| Form 1File: FORM 1.pdf | 21 May 2025 |
| Form 2File: FORM 2.pdf | 21 May 2025 |
| Form 3File: FORM 3.pdf | 21 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold- unsold Bldg 2.pdf | 21 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 7 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 31 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 31 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE- BLDG NO 2.pdf | 23 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 30 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 30 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf | 30 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf | 30 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 29 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure- bldg 2.pdf | 11 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: SVBD Form 5 building no --2.pdf | 9 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold.pdf | 7 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf | 18 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_11zon.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf | 18 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf | 23 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 2.pdf | 23 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Green Touch bldg 2.pdf | 9 May 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold 2.pdf | 8 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 FOR BUILDING 2.pdf | 30 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE BLDG 2.pdf | 30 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure-Bldg2 Dec22.pdf | 30 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure-Bldg2 Mar23.pdf | 30 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure-Bldg2 June23.pdf | 30 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure-bldg2 Sept23.pdf | 30 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure-Bldg2 Dec23.pdf | 30 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Bldg no 2_11zon.pdf | 30 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Bldg No2 dec-23_11zon.pdf | 30 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate BLDG no2.pdf | 27 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERITIFATE BLDG 2.pdf | 27 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect -Building 2.pdf | 19 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate bldg no 2.pdf | 19 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 CA CERTIFICATE_11zon.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Rera Form 5 -BLDG-2.pdf | 19 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate - BLDG NO 2-1_1_11zon.pdf | 21 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate - Green Touch bldg 2_2_11zon.pdf | 21 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate- Green Touch bldg 2_1_11zon.pdf | 21 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_11zon.pdf | 20 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA Audit ShRee Vakratunda Bldg-2-21-22.pdf | 18 Nov 2022 |
| Layout approvalFile: LAYOUT PLAN.pdf | 24 Feb 2022 |
| Building plan approvalFile: FLOOR PLAN.pdf | 24 Feb 2022 |
| Building plan approvalFile: FLOOR PLAN 02.pdf | 24 Feb 2022 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf | 24 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: FLOOR PLAN.pdf | 24 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: FLOOR PLAN 02.pdf | 24 Feb 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca raviraj.pdf | 21 Feb 2022 |
| PAN CardFile: PAN-VAKRATUND.pdf | 14 Feb 2022 |
| Copy of the legal title reportFile: LEGAL TITLE REPORT_compressed.pdf | 14 Feb 2022 |
| Details of encumbrancesFile: NON ENCUMBRANCE CERTIFICATE.pdf | 14 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE_11zon.pdf | 14 Feb 2022 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf | 14 Feb 2022 |
| Declaration in FORM BFile: FORM B.pdf | 14 Feb 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT'S CERTIFICATE_11zon (1).pdf | 14 Feb 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate-New_11zon.pdf | 14 Feb 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200229569647_For_Asset_Based_Search_04_02_2022_18_49_18_899.pdf | 14 Feb 2022 |
| Proforma of Allotment letterFile: AGREEMENT FOR SALE OF FLAT_11zon.pdf | 14 Feb 2022 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER FORMAT.pdf | 14 Feb 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 72 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep GREEN TOUCH BUILDING NO 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BADLAPUR WEST7,600+ in Thane
PRADHAN MANTRI AWAS YOJANA - URBAN
KULGAON BADLAPUR MUNICIPAL COUNCIL
Mohan Alcoves I
MOHAN LIFESPACES LLP
MANOHAR VIKAS SHREEJI PARAISO PHASE - 2
DEEPLAXMI DEVELOPERS
SHREEJI MILESTONE
DEEP LAXMI ASSOCIATES
Mohan Willows III
MOHAN LIFESPACES LLP
SHREEJI SQUARE PHASE I
SHREEJI DEVELOPERS
See every Thane project, with the district possession charts
Builder: SHREE VAKRATUNDA BUILDERS & DEVELOPERS
SHREE VAKRATUNDA BUILDERS & DEVELOPERS has 2 registrations on MahaRERA, including GREEN TOUCH BUILDING NO 2 and GREEN TOUCH. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that GREEN TOUCH BUILDING NO 2 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if GREEN TOUCH BUILDING NO 2 is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GREEN TOUCH BUILDING NO 2?
The registered promoter entity is SHREE VAKRATUNDA BUILDERS & DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GREEN TOUCH BUILDING NO 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GREEN TOUCH BUILDING NO 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GREEN TOUCH BUILDING NO 2?
The professionals named in the filing: Architect: SANDEEP PATIL; Engineer: AARNA STRUCTURAL CONSULTANTS; Chartered Accountant: NILESH A PATKI; Chartered Accountant: RAVIRAJ B DANGE AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GREEN TOUCH BUILDING NO 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback