Home / Browse projects / Pune, Maharashtra / Grand Horizon
Grand Horizon
RG-MH-25647 · RERA P52100013302 · Last updated on MahaRERA portal: 11 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 12 cases
- 1 complaint at MahaRERA
- Completion date moved by 48 months
- 2 extensions taken
- Rs 24.85 crore secured on the land, in favour of Lokmanya Multi Purpose Co Op Society Ltd, Prabodh Artha Sanchay Pvt Ltd and 1 more
- The declared charge does not appear in the CERSAI report on the filing
Clear
- Separate project account declared
- Allotment letter follows the model form
6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Grand Horizon is a Others project by GRENESIIS CONSTRO PVT LTD in Pune, Maharashtra, registered with MahaRERA as P52100013302 on 22 Sep 2017. Possession is promised by 29 Dec 2027. The completion date has moved by 48 months from the original filing. 58 of the 91 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameGrand Horizon
- TypeOthers
- Location
- Sinhgad Road
- Pune
- Wadgaon Bk
- Haveli
- 411041
- Pincode411041
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100013302
- ReraGenie IDRG-MH-25647
Builder
- NameGRENESIIS CONSTRO PVT LTD
- Entity typeCompany
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on22 Sep 2017
- Promised completion29 Dec 2027
- Revised completionRevised to 29 Dec 2027 (originally 30 Dec 2023)
- Buildings1 building record
- Documents filed155 files
Current status
Figures as on 11 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Grand Horizon | NA | 33 | 10 | 46 | 45 | 91 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 11 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 80%.
Grand Horizon: 57% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 40% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 22% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 31% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 18% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 23% |
Progress on shared amenities15
As on 11 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 42% |
| Water Supply | Yes | 25% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 37% |
| Storm Water Drains | Yes | 10% |
| Landscaping & Tree Planting | Yes | 40% |
| Street Lighting | Yes | 55% |
| Community Buildings | Yes | 10% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 20% |
| Solid Waste Management And Disposal | Yes | 15% |
| Water conservation /Rain water harvesting | Yes | 10% |
| Energy managemcnt | Yes | 5% |
| Fire protection and fire safety requirements | Yes | 23% |
| Electrical meter room, sub-station, receiving station | Yes | 32% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed39
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Grand Horizon | NA | Rs 64.58 cr | Rs 33.57 cr |
| - | NA | Rs 3.25 cr | Rs 1.69 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Pinnac Consulting Pvt Ltd |
| Architect | Rutuja B Shingare |
| Engineer | ANISH ENTERPRISES |
| Chartered Accountant | A N J K & CO LLP |
| Chartered Accountant | G N Mantri and Associates |
| Partner | Role in project |
|---|---|
| GRENESIIS CONSTRO PVT LTD | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe apply for extension of the following project Grand Horizon registered with the regulatory authority vide project registration certificate bearing no. P52100013302 which expired on 30/12/2023. We request you to grant extension of RERA Registration for a further period of 12 months i.e. upto 29/12/2024.
Reason as filed by the promoterThe extension of the project timeline is necessitated due to a combination of administrative and external factors beyond the control of the developer. The key reasons are as follows: 1. Stop Work Order from PMC: A stop work order was issued by the Pune Municipal Corporation (PMC) dated on 21st July 2017, which resulted in a complete halt of construction activities on the residential wings. This significantly impacted the project schedule and progress. 2. Stay order from National Green Tribunal (2016): The project faced delays primarily due to a Stay Order issued by the National Green Tribunal
Litigation declared12
| Case | Court | Status |
|---|---|---|
| 233/2016 | The Bombay High Court | Pending |
| 22/2016 | National Green Tribunal Western Zone Pune | Disposed |
| 3766/2016 | Chief Judicial Magistrate Pune | Disposed |
| 681/2008 | Civil Judge Jr Division Pune | Disposed |
| 9683/2017 | The Bombay High Court | Disposed |
| 13203/2017 | The Bombay High Court | Pending |
| 0032661/2024 | CMM ACMM MM Jaipur Metro I HQ | Pending |
| 9/2023 | National Green Tribunal | Pending |
| 233/2016 | - | Ongoing |
| 94/2017 | Appeal for Bhumi Abhilkh | Ongoing |
| 2570/2022 | Maharashtra Pollution Control Board | Ongoing |
| 38157/2025 | Supreme court of India | Ongoing |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000471327 | Umesh Sheth | GRENESIIS CONSTRO PVT LTD | 29/07/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 May 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 May 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 May 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 29 Dec 2027
Documents filed155
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 155 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf | 11 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate.pdf | 11 Aug 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate.pdf | 11 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate - June 2025.pdf | 19 May 2026 |
| Withdrawal Update Form 1File: ARCH RERA Sep 2025.pdf | 19 May 2026 |
| Withdrawal Update Form 1File: Form 1 Arctitect Certificate Dec 2025.pdf | 19 May 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate March 2026-signed.pdf | 19 May 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate - June 2025.pdf | 19 May 2026 |
| Withdrawal Update Form 2File: FORM 2 Engineer Certificate Sept 2025.pdf | 19 May 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate Dec 2025.pdf | 19 May 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate March 2026.pdf | 19 May 2026 |
| Withdrawal Update Form 3File: CA Certificate June 2025 - Sign.pdf | 19 May 2026 |
| Withdrawal Update Form 3File: FORM 3 CA Certificate Sept 2025_compressed.pdf | 19 May 2026 |
| Withdrawal Update Form 3File: Form 3 CA CERTIFICATE Dec 2025.pdf | 19 May 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate March 2026.pdf | 19 May 2026 |
| Form 1File: Form 1 Architect Certificate - June 2025.pdf | 10 Mar 2026 |
| Form 2File: Form 2 Engineer Certificate - June 2025.pdf | 10 Mar 2026 |
| Form 3File: CA Certificate June 2025 - Sign.pdf | 10 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory June 2025.pdf | 10 Mar 2026 |
| Form 1File: ARCH RERA Sep 2025.pdf | 10 Mar 2026 |
| Form 2File: FORM 2 Engineer Certificate Sept 2025.pdf | 10 Mar 2026 |
| Form 3File: FORM 3 CA Certificate Sept 2025_compressed.pdf | 10 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory Sept 2025.pdf | 10 Mar 2026 |
| Form 5 (FY 2024-2025)File: CA Form 5_FY 2024-25.pdf | 5 Dec 2025 |
| Form 1File: Form 1 Architect certificate.pdf | 25 Sep 2025 |
| Form 2File: Form 2 Engineer Certificate_Compressed.pdf | 25 Sep 2025 |
| Form 3File: CA Certificate December 2024_Signed_Compressed.pdf | 25 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory December 2024_Signed.pdf | 25 Sep 2025 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate - March 2025.pdf | 25 Sep 2025 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate - March 2025.pdf | 25 Sep 2025 |
| Withdrawal Update Form 3File: CA Certificate March 2025 - Sign.pdf | 25 Sep 2025 |
| Form 2A (FY 2024-2025)File: Form 2A Quality Assurance 24-25.pdf | 25 Sep 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate_Compressed.pdf | 24 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect certificate.pdf | 20 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect certificate.pdf | 18 Jan 2025 |
| Certificates of CA (Form 3)File: CA Certificate December 2024_Signed_Compressed.pdf | 18 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory December 2024_Signed.pdf | 18 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate.pdf | 19 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory September 2024.pdf | 19 Nov 2024 |
| Certificates of CA (Form 3)File: CA Certificate September 2024- Signed.pdf | 19 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate.pdf | 19 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate.pdf | 19 Nov 2024 |
| Certificates of CA (Form 3)File: CA Certificate September 2024- Signed.pdf | 19 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate.pdf | 19 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory September 2024.pdf | 19 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate.pdf | 17 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Fom 2 Engineer Certificate.pdf | 17 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory June 2024.pdf | 17 Jul 2024 |
| Certificates of CA (Form 3)File: CA Certificate June 2024 - Sign.pdf | 17 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA Form 5_FY 2023-24.pdf | 18 Jun 2024 |
| Details of encumbrancesFile: Encumbrance Legal and Finance Merged.pdf | 12 Jun 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance Legal and Finance Merged.pdf | 12 Jun 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrance Legal and Finance Merged.pdf | 12 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate.pdf | 8 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate.pdf | 8 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory March 2024.pdf | 8 Jun 2024 |
| Certificates of CA (Form 3)File: CA Certificate March 2024 Signed_11zon (1).pdf | 8 Jun 2024 |
| Certificates of CA (Form 3)File: CA Certificate December 2022 Signed_1_11zon.pdf | 4 Jun 2024 |
| Certificates of CA (Form 3)File: CA Certificate March 2023 Signed_4_11zon.pdf | 4 Jun 2024 |
| Certificates of CA (Form 3)File: CA Certificate June 2023 Signed_3_11zon.pdf | 4 Jun 2024 |
| Certificates of CA (Form 3)File: CA Certificate September 2023 Signed_5_11zon.pdf | 4 Jun 2024 |
| Certificates of CA (Form 3)File: CA Certificate December 2023 Signed_2_11zon.pdf | 4 Jun 2024 |
| Layout approvalFile: compressed_Map-03-09 (1).pdf | 30 May 2024 |
| Building plan approvalFile: compressed_Map-04-09 (1).pdf | 30 May 2024 |
| Building plan approvalFile: compressed_Map-05-09 (1).pdf | 30 May 2024 |
| Building plan approvalFile: compressed_Map-06-09 (1).pdf | 30 May 2024 |
| Building plan approvalFile: compressed_Map-07-09 (1).pdf | 30 May 2024 |
| Building plan approvalFile: compressed_Map-08-09 (1).pdf | 30 May 2024 |
| Building plan approvalFile: compressed_Map-09-09 (2).pdf | 30 May 2024 |
| Copy of Layout Approval (in case of layout)File: compressed_Map-03-09 (1).pdf | 30 May 2024 |
| Building Plan Approval (IOD)File: compressed_Map-04-09 (1).pdf | 30 May 2024 |
| Building Plan Approval (IOD)File: compressed_Map-05-09 (1).pdf | 30 May 2024 |
| Building Plan Approval (IOD)File: compressed_Map-06-09 (1).pdf | 30 May 2024 |
| Building Plan Approval (IOD)File: compressed_Map-07-09 (1).pdf | 30 May 2024 |
| Building Plan Approval (IOD)File: compressed_Map-08-09 (1).pdf | 30 May 2024 |
| Building Plan Approval (IOD)File: compressed_Map-09-09 (2).pdf | 30 May 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf | 30 May 2024 |
| Declaration about Commencement CertificateFile: CC Declaration.pdf | 30 May 2024 |
| Declaration in FORM BFile: Form B.pdf | 30 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate 31-12-2022.pdf | 30 May 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 6 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 155 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Grand Horizon on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Pune13,700+ in Pune
Filed coordinates, straight-line distance. 121 registered projects within 2 km.
VYANA PHASE-I -T5, T6, T7
KOLTE-PATIL DEVELOPERS LIMITED
Pratham Vihar Phase I
LJR Constructions LLP
VYANA PHASE-I-T2,T3 AT THE RESERVE
KOLTE-PATIL DEVELOPERS LIMITED
MAITREE MEGA CITY
MAITREE INFRA
RAMANA MYRA
SAI AND SHANTISHOBHA VENTURE
Apple Regency
Sri Sidhievinayak associetes
Builder: GRENESIIS CONSTRO PVT LTD
GRENESIIS CONSTRO PVT LTD has 1 registration on MahaRERA, including Grand Horizon. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Grand Horizon is delayed beyond 29 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Grand Horizon?
The registered promoter entity is GRENESIIS CONSTRO PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Grand Horizon?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Grand Horizon?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Grand Horizon?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Grand Horizon?
The professionals named in the filing: Architect: Pinnac Consulting Pvt Ltd; Architect: Rutuja B Shingare; Engineer: ANISH ENTERPRISES; Chartered Accountant: A N J K & CO LLP; Chartered Accountant: G N Mantri and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Grand Horizon?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback