Home / Browse projects / Pune, Maharashtra / Govind Apartment
Govind Apartment
RG-MH-86079 · RERA P52100051716 · Last updated on MahaRERA portal: 5 Feb 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 26 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Govind Apartment is a Residential / Group Housing project by Kirit Harilal Jivarajni in Pune, Maharashtra, registered with MahaRERA as P52100051716 on 27 Jun 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 26 months from the original filing. 0 of the 10 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.
At a glance
Project
- NameGovind Apartment
- TypeResidential / Group Housing
- Location
- Shukrawar Peth
- Haveli
- Pune
- 411002
- Pincode411002
- RERA no.P52100051716
- ReraGenie IDRG-MH-86079
Builder
- NameKirit Harilal Jivarajni
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on27 Jun 2023
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Oct 2024)
- Buildings1 building record
- Documents filed77 files
Current status
Figures as on 5 Feb 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Govind Apartment | NA | 4 | 4 | 10 | 0 | 10 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 5 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.
Govind Apartment: 73% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 5 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Arun Bapusaheb Wadekar | Pune (M Corp.) | Pune |
| Shobha Arun Wadekar | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Govind Apartment | NA | Rs 95.17 lakh | Rs 95.00 lakh |
| - | NA | Rs 9.76 lakh | Rs 9.55 lakh |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sonik B Bhandare |
| Engineer | Mayur s Khandwe |
| Chartered Accountant | CA Pushpak Bogati |
| Partner | Role in project |
|---|---|
| Kirit Harilal Jivarajni | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe were planning to expand the project, but there were a delay in receiving the sanction plan from the local authority. This setback has postponed our project timeline as we need the official approval to proceed with the expansion
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 May 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 13 Apr 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 13 Apr 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 13 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed77
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: form 1_Govind Apartment MAR 25.pdf | 5 Feb 2026 |
| Form 2File: form 2 _Govind Apartmen_ march 25.pdf | 5 Feb 2026 |
| Form 3File: Form 3_March 25_Govind apartment..pdf | 5 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold disclosure_March 2025_Govind Apartment.pdf | 5 Feb 2026 |
| Withdrawal Update Form 1File: form 1_Govind Apartment JUN 25.pdf | 5 Feb 2026 |
| Withdrawal Update Form 1File: form 1_Govind Apartment JUN 25.pdf | 5 Feb 2026 |
| Withdrawal Update Form 1File: form 1_Govind Apartment JUN 25.pdf | 5 Feb 2026 |
| Withdrawal Update Form 1File: form 1_Govind Apartment Sep 25.pdf | 5 Feb 2026 |
| Withdrawal Update Form 2File: form 2_Govind Apartment_ June 2025.pdf | 5 Feb 2026 |
| Withdrawal Update Form 2File: form 2_Govind Apartment_ June 2025.pdf | 5 Feb 2026 |
| Withdrawal Update Form 2File: form 2_Govind Apartment_ June 2025.pdf | 5 Feb 2026 |
| Withdrawal Update Form 2File: Form 2_Govind Apartment_Sep 25.pdf | 5 Feb 2026 |
| Withdrawal Update Form 3File: govind apt _ jun 25 form 3.pdf | 5 Feb 2026 |
| Withdrawal Update Form 3File: govind apt _ jun 25 form 3.pdf | 5 Feb 2026 |
| Withdrawal Update Form 3File: govind apt _ jun 25 form 3.pdf | 5 Feb 2026 |
| Withdrawal Update Form 3File: Form 3_Sep 25..pdf | 5 Feb 2026 |
| Form 2A (FY 2023-2024)File: Form 2a_Govind Apartment_2023-24.pdf | 13 Oct 2025 |
| Form 2A (FY 2024-2025)File: form 2a_Govind Apartment_2024-25.pdf | 13 Oct 2025 |
| Form 2File: form 2_Govind Apartment_ June 2025.pdf | 11 Oct 2025 |
| Form 1File: Form 1_Govind Apartment_June 2023.pdf | 11 Oct 2025 |
| Form 3File: Form 3_Govind Apartment_June 2023.pdf | 11 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold disclosure-june 2023_Govind Apartment.pdf | 11 Oct 2025 |
| Form 1File: form 1_Govind Apartment - sep 23.pdf | 11 Oct 2025 |
| Form 2File: Form 2_Govind Apartment_Sep 2023.pdf | 11 Oct 2025 |
| Form 3File: Form 3_Govind Apartment_Sep 2023.pdf | 11 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold disclosure-Sep 2023_Govind Apartment.pdf | 11 Oct 2025 |
| Form 1File: form 1_Govind Apartmen_Dec 2023.pdf | 11 Oct 2025 |
| Form 2File: form 2_Govind Apartment_ Dec 2023.pdf | 11 Oct 2025 |
| Form 3File: Form 3_Govind Apartment_Dec 2023.pdf | 11 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold disclosure-Dec 2023-Govind Apartment.pdf | 11 Oct 2025 |
| Form 1File: form 1_Govind Apartment_ march 2024.pdf | 11 Oct 2025 |
| Form 2File: form 2_Govind Apartment_ march 2024.pdf | 11 Oct 2025 |
| Form 3File: Form 3_Govind Apartment _MArch 2024.pdf | 11 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold disclosure-_March 2024-Govind Apartment.pdf | 11 Oct 2025 |
| Form 1File: form 1_Govind Apartment_june 24.pdf | 11 Oct 2025 |
| Form 2File: Form 2_Govind Apartment_June 2024.pdf | 11 Oct 2025 |
| Form 3File: form 3-Govind Apartment _june 24.pdf | 11 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold disclosure_June 2024_Govind Apartment.pdf | 11 Oct 2025 |
| Form 1File: form 1_Govind Apartment_ sep 2024.pdf | 11 Oct 2025 |
| Form 2File: form 2-Govind Apartment_ sep 24.pdf | 11 Oct 2025 |
| Form 3File: form 3_Govind Apartment _ sep 24.pdf | 11 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold disclosure-Sep 2024_Govind Apartment.pdf | 11 Oct 2025 |
| Form 1File: form 1_Govind Apartment_ oct 2024.pdf | 11 Oct 2025 |
| Form 2File: form 2_ Govind Apartment_Dec 24.pdf | 11 Oct 2025 |
| Form 3File: form 3-Govind Apartment_october 24.pdf | 11 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold disclosure-Oct 2024_Govind Apartment.pdf | 11 Oct 2025 |
| Form 5 (FY 2023-2024)File: form 5_Govind Apartment-FY 2023-2024.pdf | 10 Oct 2025 |
| Form 5 (FY 2024-2025)File: Govind apartment form 5 FY 2024-25.pdf | 10 Oct 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 parvati.pdf | 27 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 parvati.pdf | 27 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: sep23.pdf | 27 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: dec23.pdf | 27 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 13 Jun 2023 |
| Copy of the legal title reportFile: Legal Title report 30 May 2023_compressed.pdf | 30 May 2023 |
| Declaration about Commencement CertificateFile: Declaration of CC.pdf | 17 May 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account.pdf | 9 May 2023 |
| Other - FinanceFile: Declaration- pan card.pdf | 9 May 2023 |
| Details of encumbrances concerned to FinanceFile: No encumbrances letter finance.pdf | 29 Apr 2023 |
| Details of encumbrances concerned to FinanceFile: No Encumbrances letter legal.pdf | 29 Apr 2023 |
| Details of encumbrances concerned to LegalFile: No encumbrances letter finance.pdf | 29 Apr 2023 |
| Details of encumbrances concerned to LegalFile: No Encumbrances letter legal.pdf | 29 Apr 2023 |
| Declaration in FORM BFile: Form B (2)_compressed.pdf | 29 Apr 2023 |
| CERSAI detailsFile: CERSAI_Search_Report_200267416686_For_Asset_Based_Search_29_04_2023_16_07_20_466.pdf | 29 Apr 2023 |
| CERSAI detailsFile: CERSAI_Search_Report_200267419018_For_Asset_Based_Search_29_04_2023_16_13_42_894.pdf | 29 Apr 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other real estate organisations.pdf | 29 Apr 2023 |
| Proforma of Allotment letterFile: Parvati Allotment letter format _compressed.pdf | 29 Apr 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about separate bank account.pdf | 29 Apr 2023 |
| Deviation Report with respect to Allotment letterFile: Deviation- Allotment letter.pdf | 29 Apr 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation agreement for sale.pdf | 29 Apr 2023 |
| Layout approvalFile: layout.pdf | 13 Apr 2023 |
| Building plan approvalFile: layout.pdf | 13 Apr 2023 |
| PAN CardFile: PAN CARD.pdf | 13 Apr 2023 |
| Copy of the legal title reportFile: Legal title report 1.pdf | 13 Apr 2023 |
| Copy of Layout Approval (in case of layout)File: layout.pdf | 13 Apr 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: layout.pdf | 13 Apr 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: C C.pdf | 13 Apr 2023 |
| Proforma of Agreement for saleFile: Agreement For Sale.pdf | 13 Apr 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 77 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Govind Apartment on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Shukrawar peth13,700+ in Pune
NAVI TULSIBAUG
MATOSHRI ESTATE PVT LTD
Shankeshawar Gold Palace
BPO Uprise Lifestyle
24k Aurum Centre
Dreamnest Developers
Shree Kuber Business Hub
Shree Realty
DHANLAXMI MARKET
DHANLAXMI INFRA
PEHLWAN PRATAP SINGH PLAZA
MODERN GROUP
Builder: Kirit Harilal Jivarajni
Kirit Harilal Jivarajni has 1 registration on MahaRERA, including Govind Apartment. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Govind Apartment is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Govind Apartment?
The registered promoter entity is Kirit Harilal Jivarajni, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Govind Apartment?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Govind Apartment?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Govind Apartment?
The professionals named in the filing: Architect: Sonik B Bhandare; Engineer: Mayur s Khandwe; Chartered Accountant: CA Pushpak Bogati. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Govind Apartment?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.