Home / Browse projects / Pune, Maharashtra / DHANLAXMI MARKET

Registered No litigation declared Others project

DHANLAXMI MARKET

By DHANLAXMI INFRA

RG-MH-22004 · RERA P52100029973 · Last updated on MahaRERA portal: 24 Apr 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 24 months from the original
3 of 11Construction stages donefurthest along: Stilt Floor, 95%
80 of 85Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 64 documents Report an error

DHANLAXMI MARKET is a Others project by DHANLAXMI INFRA in Pune, Maharashtra, registered with MahaRERA as P52100029973 on 18 Jul 2021. Possession is promised by 30 Dec 2026. The completion date has moved by 24 months from the original filing. 5 of the 85 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameDHANLAXMI MARKET
  • TypeOthers
  • Location
    • RAVIWAR PETH
    • Peth
    • Haveli
    • Pune
    • 411002
  • Pincode411002
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100029973
  • ReraGenie IDRG-MH-22004

Builder

  • NameDHANLAXMI INFRA
  • Entity typePartnership
  • PartnersMAHAVIR MOHANLAL JAIN, SHANTILAL LALCHAND JAIN, BHARAT MOHANLAL JAIN, ANAND TARACHAND JAIN, SACHIN DHANRAJ KATARIYA, LALIT HIRALAL JAIN, KISHORE LAKHMICHAND RATHOD, SATISH PARASMAL RATHOD, HASTMAL LAKHMICHAND RATHOD, NILESH HASTIMAL RATHOD

Key dates

this monthRegisteredJul 2021First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Jul 2021
  • Promised completion30 Dec 2026
  • Revised completionRevised to 30 Dec 2026 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed64 files

Current status

6%5 of 85 units booked
64.2%Work done, per cost certificate

Figures as on 24 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DHANLAXMI MARKETNA9838285

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 95%.

DHANLAXMI MARKET: 83% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor95%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%

Progress on shared amenities15

As on 24 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes40%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed92

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots92
Closed/Covered92

Land and ownership6

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,087 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on24 Jan 2026
LandownerVillageDistrict
GOVIND SHAMJI PATELPune (CB)Pune
MANSUKH RANCHOD CHANDATPune (CB)Pune
SANJAY DASHARATH RANEPune (CB)Pune
PARAG DASHARATH RANEPune (CB)Pune
BHARAT DASHARATH RANEPune (CB)Pune
RAJESH DASHARATH RANEPune (CB)Pune

Approvals and building plan

Permissible FSI3171.08
Proposed, not sanctioned3,171 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch694, 2 Poonam Plaza, Plot No 12, Market Yard Road, Pune 411037
Estimated costRs 14.99 cr
Cost incurredRs 9.62 cr
Work done64.15%
BuildingWingEstimatedIncurred
DHANLAXMI MARKETNARs 14.92 crRs 9.62 cr
-NARs 7.00 lakh-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDILIP G KALE AND ASSOCIATES
EngineerSHAILESH VIMALKUMAR OSWAL
Chartered AccountantASHISH R MALPANI AND CO r MALPANI
Chartered AccountantAMIT A SOMANI
PartnerRole in project
DHANLAXMI INFRA-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100027116Dec 2024 → Dec 2026

Reason as filed by the promoterthe project is yet to be completed as it has taken alot of time for sanctioning and internal work is yet to commenced and to work of sanitary Fittings and work of pipeline is pending and lift installation work is yet to be completed as well the project yet not obtained Occupancy certificate hence all this work is pending and that is the reason where extension is required as well the Allottees and landowner know this fact hence they have given consent for the sa

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000096297Vinodchandra Bhogilal ShahDHANLAXMI INFRA26/11/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Jul 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Dec 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Jul 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2026

Documents filed64

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architecture_certificate_.pdf24 Apr 2026
Withdrawal Update Form 1File: FORM 1.pdf24 Apr 2026
Withdrawal Update Form 1File: FORM 1.pdf24 Apr 2026
Withdrawal Update Form 1File: FORM 1.pdf24 Apr 2026
Withdrawal Update Form 2File: Engineer_certificate.pdf24 Apr 2026
Withdrawal Update Form 2File: FORM 2_compressed (1).pdf24 Apr 2026
Withdrawal Update Form 2File: ENGINEER CERTIFICATE.pdf24 Apr 2026
Withdrawal Update Form 2File: ENGINEER CERTIFICATE.pdf24 Apr 2026
Withdrawal Update Form 3File: CA_certificate_ - converted.pdf24 Apr 2026
Withdrawal Update Form 3File: FORM 3_compressed .....pdf24 Apr 2026
Withdrawal Update Form 3File: CA CERTIFICATE_compressed.pdf24 Apr 2026
Withdrawal Update Form 3File: CA CERTIFICATE_compressed.pdf24 Apr 2026
Form 1File: FORM 1.pdf19 Aug 2025
Form 2File: Form 2 Dhanlaxmi Infra June 2025.pdf19 Aug 2025
Form 3File: FORM 3.pdf19 Aug 2025
Disclosure of Sold and Booked InventoryFile: sold and unsold inventory.pdf19 Aug 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate - converted.pdf13 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate - converted.pdf13 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate.pdf13 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5-(2023-24).pdf13 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A (2023-24 ).pdf10 Mar 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf24 Feb 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf19 Feb 2025
Declaration in FORM BFile: DECLARATION FORM B.pdf5 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch certificate form 1 for Raviwar peth.pdf5 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE NEW.pdf25 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE NEW.pdf12 Apr 2024
Disclosure of sold/ booked inventoryFile: UPDATED SOLD AND UNSOLD INVENTORY.pdf13 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A 2021-22.pdf6 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A 2022-23.pdf6 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 2023.pdf5 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 2022.pdf5 Mar 2024
Disclosure of sold/ booked inventoryFile: UPDATED SOLD AND UNSOLD INVENTORY.pdf8 Jan 2024
Disclosure of sold/ booked inventoryFile: SOLD AND UNSOLD INVENTORY.pdf3 Jan 2024
Layout approvalFile: PLAN1.pdf30 Dec 2023
Layout approvalFile: PLAN2.PDF30 Dec 2023
Layout approvalFile: PLAN3.pdf30 Dec 2023
Layout approvalFile: PLAN4.PDF30 Dec 2023
Layout approvalFile: PLAN5.PDF30 Dec 2023
Copy of Layout Approval (in case of layout)File: PLAN1.pdf30 Dec 2023
Copy of Layout Approval (in case of layout)File: PLAN2.PDF30 Dec 2023
Copy of Layout Approval (in case of layout)File: PLAN3.pdf30 Dec 2023
Copy of Layout Approval (in case of layout)File: PLAN4.PDF30 Dec 2023
Copy of Layout Approval (in case of layout)File: PLAN5.PDF30 Dec 2023
Declaration about Commencement CertificateFile: DECLARATION REGARDING CC.pdf30 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf30 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg certificate dec 2023 raviwar peth.pdf30 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE1.pdf30 Dec 2023
Other - LegalFile: DEVELOPMENT AGREEMENT WITH GOVIND SHAMJI PATEL1.pdf30 Dec 2023
Other - LegalFile: DEVELOPMENT AGREEMENT WITH SANJAY RANA1 (1).pdf30 Dec 2023
Layout approvalFile: LAYOUT PLAN1.pdf2 Jul 2021
Building plan approvalFile: BUILDING LAYOUT1.pdf2 Jul 2021
PAN CardFile: PAN CARD.pdf2 Jul 2021
Copy of the legal title reportFile: TITLE SEARCH REPORT.pdf2 Jul 2021
Details of encumbrancesFile: DETAILS OF EMCUMBRANCES.pdf2 Jul 2021
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN1.pdf2 Jul 2021
Building Plan Approval / NA Order for plotted developmentFile: BUILDING LAYOUT1.pdf2 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE1.pdf2 Jul 2021
Declaration about Commencement CertificateFile: Declaration_commencement.pdf2 Jul 2021
Declaration in FORM BFile: DECLARATION IN FORM B.pdf2 Jul 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf2 Jul 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CETIFICATE.pdf2 Jul 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf2 Jul 2021
Proforma of Allotment letterFile: PROFORMA OF ALLOTMENT LETTER.pdf2 Jul 2021

How this compares with Pune

6%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DHANLAXMI MARKET on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near RAVIWAR PETH13,700+ in Pune

2 kmDHANLAXMI MARKETCompleted 172Lapsed / revoked 138Other 157Dot size: filed unitsN

Filed coordinates, straight-line distance. 467 registered projects within 2 km.

Builder: DHANLAXMI INFRA

DHANLAXMI INFRA has 1 registration on MahaRERA, including DHANLAXMI MARKET. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if DHANLAXMI MARKET is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DHANLAXMI MARKET?

The registered promoter entity is DHANLAXMI INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DHANLAXMI MARKET?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against DHANLAXMI MARKET?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for DHANLAXMI MARKET?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DHANLAXMI MARKET?

The professionals named in the filing: Architect: DILIP G KALE AND ASSOCIATES; Engineer: SHAILESH VIMALKUMAR OSWAL; Chartered Accountant: ASHISH R MALPANI AND CO r MALPANI; Chartered Accountant: AMIT A SOMANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DHANLAXMI MARKET?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DHANLAXMI MARKET. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DHANLAXMI MARKET to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.