Home / Browse projects / Pune, Maharashtra / GOLDEN PALMS
GOLDEN PALMS
RG-MH-55205 · RERA P52100050226 · Last updated on MahaRERA portal: 11 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GOLDEN PALMS is a Others project by PRAKASH NANDLAL LAKHWANI in Pune, Maharashtra, registered with MahaRERA as P52100050226 on 27 Mar 2023. Possession was promised by 31 Dec 2025 and is now 10 months past that date. 6 of the 21 units on this registration are recorded sold or booked, and 135 of 231 construction stages are filed complete.
At a glance
Project
- NameGOLDEN PALMS
- TypeOthers
- Location
- GAT NO 115 NEAR RAILWAY CROSSING
- PUNE
- Boraj
- Mawal
- 410401
- Pincode410401
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100050226
- ReraGenie IDRG-MH-55205
Builder
- NamePRAKASH NANDLAL LAKHWANI
- Entity typeIndividual
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on27 Mar 2023
- Promised completion31 Dec 2025
- Revised completionNone
- Buildings21 building records
- Documents filed88 files
Current status
Figures as on 11 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING A1 - 1 | NA | 2 | 2 | 1 | 0 | 1 |
| BUILDING A1 - 2 | NA | 2 | 2 | 1 | 0 | 1 |
| BUILDING A1 - 3 | NA | 2 | 2 | 1 | 0 | 1 |
| BUILDING A1 - 4 | NA | 2 | 2 | 1 | 0 | 1 |
| BUILDING A1 - 5 | NA | 2 | 2 | 1 | 0 | 1 |
| BUILDING A1 - 6 | NA | 2 | 2 | 1 | 0 | 1 |
| BUILDING A1 - 7 | NA | 2 | 2 | 1 | 0 | 1 |
| BUILDING A1 - 8 | NA | 2 | 2 | 1 | 0 | 1 |
| BUILDING A1 - 9 | NA | 2 | 2 | 1 | 0 | 1 |
| BUILDING A1 - 10 | NA | 2 | 2 | 1 | 0 | 1 |
| BUILDING A1 - 11 | NA | 2 | 2 | 1 | 0 | 1 |
| BUILDING A1 - 12 | NA | 2 | 2 | 1 | 0 | 1 |
| BUILDING A1 - 13 | NA | 2 | 2 | 1 | 0 | 1 |
| BUILDING A1 - 14 | NA | 2 | 2 | 1 | 0 | 1 |
| BUILDING A1 - 15 | NA | 2 | 2 | 1 | 0 | 1 |
| BUILDING A1 - 16 | NA | 2 | 2 | 1 | 0 | 1 |
| BUILDING A2 - 1 | NA | 2 | 2 | 1 | 0 | 1 |
| BUILDING A2 - 2 | NA | 2 | 2 | 1 | 0 | 1 |
| BUILDING A2 - 3 | NA | 2 | 2 | 1 | 0 | 1 |
| BUILDING A2 - 4 | NA | 2 | 2 | 1 | 0 | 1 |
| BUILDING A2 - 5 | NA | 2 | 2 | 1 | 0 | 1 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 11 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 21 buildings; the table lists the first 20.
135 of 231 construction stages are filed complete across 21 buildings. The stage furthest along is Slabs of Super Structure, at 75%.
BUILDING A1 - 182%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING A1 - 282%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING A1 - 382%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING A1 - 482%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING A1 - 582%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING A1 - 682%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING A1 - 782%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING A1 - 882%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING A1 - 982%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING A1 - 1082%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING A1 - 1152%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 20% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING A1 - 1252%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 20% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING A1 - 1352%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 20% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING A1 - 1452%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 20% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING A1 - 1552%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 20% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING A1 - 1652%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 20% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING A2 - 145%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 75% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 25% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING A2 - 245%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 75% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 25% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING A2 - 345%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 75% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 25% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING A2 - 445%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 75% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 25% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 11 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 60% |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 60% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | Yes | 40% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 40% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| BUILDING A1 - 1 | NA | Rs 75.71 lakh | Rs 40.09 lakh |
| BUILDING A1 - 2 | NA | Rs 75.71 lakh | Rs 40.09 lakh |
| BUILDING A1 - 3 | NA | Rs 75.71 lakh | Rs 40.09 lakh |
| BUILDING A1 - 4 | NA | Rs 75.71 lakh | Rs 40.09 lakh |
| BUILDING A1 - 5 | NA | Rs 75.71 lakh | Rs 40.09 lakh |
| BUILDING A1 - 6 | NA | Rs 75.71 lakh | Rs 40.09 lakh |
| BUILDING A1 - 7 | NA | Rs 75.71 lakh | Rs 40.09 lakh |
| BUILDING A1 - 8 | NA | Rs 75.71 lakh | Rs 40.09 lakh |
| BUILDING A1 - 9 | NA | Rs 75.71 lakh | Rs 40.09 lakh |
| BUILDING A1 - 10 | NA | Rs 75.71 lakh | Rs 40.09 lakh |
| BUILDING A1 - 11 | NA | Rs 75.71 lakh | Rs 40.09 lakh |
| BUILDING A1 - 12 | NA | Rs 75.71 lakh | Rs 40.09 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SPIRO DESIGN |
| Engineer | SUNNY SURESH JADHAV SURESH JADHAV |
| Chartered Accountant | CA ADITYA MASULKAR MASULKAR AND ASSOCIATES FLAT NO 05 BLDG NO 7 VASTU UDYOG Masulkar |
| Chartered Accountant | Kunal Bajaj |
| Partner | Role in project |
|---|---|
| PRAKASH NANDLAL LAKHWANI | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 4 Mar 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 Mar 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 4 Mar 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed88
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2022-2023)File: Structural Engineer 22-23.pdf | 11 Jul 2026 |
| Form 2A (FY 2023-2024)File: Structural Engineer 23-24.pdf | 11 Jul 2026 |
| Form 2A (FY 2024-2025)File: Structural Engineer 24-25.pdf | 11 Jul 2026 |
| Form 5 (FY 2022-2023)File: FORM 5_2022-23.pdf | 11 Jul 2026 |
| Form 5 (FY 2023-2024)File: FORM 5_2023-24.pdf | 11 Jul 2026 |
| Form 5 (FY 2024-2025)File: FORM 5_2024-25.pdf | 11 Jul 2026 |
| Withdrawal Update Form 1File: form 1 28-12-25_Q3.pdf | 5 Jul 2026 |
| Withdrawal Update Form 1File: form 1 25-09-25_Q2.pdf | 5 Jul 2026 |
| Withdrawal Update Form 1File: form 1 28-12-25_Q3.pdf | 5 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2_Q1.pdf | 5 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2_Q2.pdf | 5 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2_Q3.pdf | 5 Jul 2026 |
| Withdrawal Update Form 3File: Q1.pdf | 5 Jul 2026 |
| Withdrawal Update Form 3File: Q2.pdf | 5 Jul 2026 |
| Withdrawal Update Form 3File: Q3.pdf | 5 Jul 2026 |
| Form 1File: FORM 1_Q1.pdf | 27 Apr 2026 |
| Form 2File: FORM 2_Q1.pdf | 27 Apr 2026 |
| Form 3File: Form 3 Q 1 24-25.pdf | 27 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory Q1.pdf | 27 Apr 2026 |
| Form 1File: FORM 1_Q2.pdf | 27 Apr 2026 |
| Form 2File: FORM 2_Q2.pdf | 27 Apr 2026 |
| Form 3File: Form 3 Q 2 24-25.pdf | 27 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory Q2.pdf | 27 Apr 2026 |
| Form 1File: FORM 1_Q3.pdf | 27 Apr 2026 |
| Form 2File: FORM 2_Q2.pdf | 27 Apr 2026 |
| Form 3File: Form 3 Q 3 24-25.pdf | 27 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory Q3.pdf | 27 Apr 2026 |
| Form 1File: FORM 1_Q4.pdf | 27 Apr 2026 |
| Form 2File: FORM 2_Q4.pdf | 27 Apr 2026 |
| Form 3File: Form 3 Q 4 24-25.pdf | 27 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory Q4.pdf | 27 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 ( 14-10-24 ).pdf | 27 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 ( 14-10-24 ).pdf | 27 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 Rera June 23 Final full set_compressed.pdf | 27 Apr 2026 |
| Form 1File: FORM 1_Q4.pdf | 24 Apr 2026 |
| Form 2File: FORM 2.pdf | 24 Apr 2026 |
| Form 3File: Form 3.pdf | 24 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold and booked inventory.pdf | 24 Apr 2026 |
| Form 1File: FORM 1_Q1.pdf | 24 Apr 2026 |
| Form 2File: FORM 2_Q1.pdf | 24 Apr 2026 |
| Form 3File: Form 3 Q 1 23-24.pdf | 24 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: disclosure of sold and booked inventory Q1.pdf | 24 Apr 2026 |
| Form 1File: FORM 1_Q2.pdf | 24 Apr 2026 |
| Form 2File: FORM 2_Q2.pdf | 24 Apr 2026 |
| Form 3File: Form 3 Q 2 23-24.pdf | 24 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: disclosure of sold and booked inventory Q2.pdf | 24 Apr 2026 |
| Form 1File: FORM 1_Q3.pdf | 24 Apr 2026 |
| Form 2File: FORM 2_Q3.pdf | 24 Apr 2026 |
| Form 3File: Form 3 Q 3 23-24.pdf | 24 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold and booked inventory Q3.pdf | 24 Apr 2026 |
| Form 1File: FORM 1_Q4.pdf | 24 Apr 2026 |
| Form 2File: FORM 2_Q4.pdf | 24 Apr 2026 |
| Form 3File: FORM 3_Q4 2023-24.pdf | 24 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold and booked inventory Q4.pdf | 24 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 ( 14-10-24 ).pdf | 24 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 ( 14-10-24 ).pdf | 24 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 Rera June 23 Final full set_compressed.pdf | 24 Feb 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ( 14-10-24 ).pdf | 16 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Rera Sept 2024 Final Scan.pdf | 16 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 ( 14-10-24 ).pdf | 16 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Rera June 23 Final full set_compressed.pdf | 23 Aug 2023 |
| CERSAI detailsFile: CERSAI_Search_Report_200263693189_For_Asset_Based_Search_20_03_2023_21_01_07_563.pdf | 20 Mar 2023 |
| CERSAI detailsFile: Undertaking Cersai Rev.pdf | 20 Mar 2023 |
| Other - FinanceFile: Revised ENCUM_FINANCE.pdf | 20 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate on project cost and fund withdrawal.pdf | 14 Mar 2023 |
| Proforma of Agreement for saleFile: ATS_ goldem palms.pdf | 14 Mar 2023 |
| Details of encumbrances concerned to FinanceFile: Details of Encumbrances concerned to Finance.pdf | 12 Mar 2023 |
| Details of encumbrances concerned to LegalFile: Details of Encumbrances concerned to Finance.pdf | 12 Mar 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: commencement certificate.pdf | 5 Mar 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf | 5 Mar 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK ACCOUNT.pdf | 5 Mar 2023 |
| Layout approvalFile: 1 Copy of Layout Approval (in case of layout).pdf | 4 Mar 2023 |
| Building plan approvalFile: 1 Building Plan Approval _ NA Order for plotted development.pdf | 4 Mar 2023 |
| Building plan approvalFile: 2 Building Plan Approval _ NA Order for plotted development.pdf | 4 Mar 2023 |
| Building plan approvalFile: 3 Building Plan Approval _ NA Order for plotted development.pdf | 4 Mar 2023 |
| Building plan approvalFile: 4 Building Plan Approval _ NA Order for plotted development.pdf | 4 Mar 2023 |
| PAN CardFile: 1 PAN Card.pdf | 4 Mar 2023 |
| Copy of the legal title reportFile: 1 Copy of the legal title report (1).pdf | 4 Mar 2023 |
| Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout).pdf | 4 Mar 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 1 Building Plan Approval _ NA Order for plotted development.pdf | 4 Mar 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| VINAYAK RESIDENCY | BHOSARI HAVELI PUNE | 2 | Completed | Aug 2022 | Aug 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 88 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep GOLDEN PALMS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PUNE13,700+ in Pune
Filed coordinates, straight-line distance. 5 registered projects within 2 km.
CANARY FARMS
CANARY FARMS
HRIDAAN HEIGHTS
R SQUARE BUILDERS AND DEVELOPERS
Amoda Reserve - South Park
Kalpataru Properties (Thane) Private Limit
Nakshatra Valley
Hariom Sai Developers
MANTRA DIVINE PHASE 2
MANTRA UNIVERSE PRIVATE LIMITED
EMERALD VILLAS
ASHWIN ARVIND SANGHVI
Builder: PRAKASH NANDLAL LAKHWANI
PRAKASH NANDLAL LAKHWANI has 1 registration on MahaRERA, including GOLDEN PALMS. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that GOLDEN PALMS shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if GOLDEN PALMS is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GOLDEN PALMS?
The registered promoter entity is PRAKASH NANDLAL LAKHWANI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GOLDEN PALMS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for GOLDEN PALMS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GOLDEN PALMS?
The professionals named in the filing: Architect: SPIRO DESIGN; Engineer: SUNNY SURESH JADHAV SURESH JADHAV; Chartered Accountant: CA ADITYA MASULKAR MASULKAR AND ASSOCIATES FLAT NO 05 BLDG NO 7 VASTU UDYOG Masulkar; Chartered Accountant: Kunal Bajaj. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GOLDEN PALMS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback