Home / Browse projects / Udupi, Karnataka / Golden Orchid

Registration approved Residential/Group Housing project

Golden Orchid

By Rehan Associates

RG-KA-33003 · RERA PRM/KA/RERA/1273/319/PR/190125/002303 · Last updated on RERA Karnataka portal: Not stated

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 2 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Mar 2020Possession promisedmoved 12 months from the original
0 of 12Construction stages donefurthest along: Earth work and other leveling..., 0%
60 of 60Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 54 documents Report an error

Golden Orchid is a Residential/Group Housing project by Rehan Associates in Udupi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1273/319/PR/190125/002303 on 25 Jan 2019. Possession is promised by 31 Mar 2020. The completion date has moved by 12 months from the original filing. 0 of the 60 units on this registration are recorded sold or booked, and 0 of 12 construction stages are filed complete.

At a glance

Project

  • NameGolden Orchid
  • TypeResidential/Group Housing
  • Location
    • Karkala
    • Udupi
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1273/319/PR/190125/002303
  • ReraGenie IDRG-KA-33003

Builder

  • NameRehan Associates
  • Entity typePartnership Firm
  • Authorized SignatoryVivian Ronald Dsouza
  • OthersRichard Alphonso Stanislaus Dsouza, Naveen Anthony Dsouza, Denzil Sylvester Dsouza
  • Declared earlier projects1 →

Key dates

this monthRegisteredJan 2019First promiseMar 2019Revised toMar 2020

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on25 Jan 2019
  • Promised completion31 Mar 2020
  • Revised completionRevised to 31 Mar 2020 (originally 31 Mar 2019)
  • Buildings1 building record
  • Documents filed54 files

Current status

0%0 of 60 units booked

Figures as on Not stated, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Golden Orchid---60060

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on Not stated, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 12 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 0%.

Building: 0% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)Not applicable
Railing and Grill fixingNot applicable
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

As on Not stated, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,024 sq m
Land owned byNot the promoter
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 10.80 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArchitecture Plus
EngineerDesign Associtaes

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2019 → Dec 2020

No reason recorded in the filing

EX/PRM/KA/RERA/1273/319/PR/200526/002303Dec 2020 → Mar 2020

Reason as filed by the promoterShortage of Building Materials, Concrete, Jalli etc

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed54

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1273/319/PR/190125/002303 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Incorporation1.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Arc certificate - work completed_compressed.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engg certificate - work completed_compressed.pdf-
CA Certificate for Funds UtilizationFile: CA Certificate Fund Utilised_compressed.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Arc certificate - work pending_compressed.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engg certificate - work pending_compressed.pdf-
CA Certificate for Funds required for Project CompletionFile: CA Certificate Fund Required_compressed.pdf-
AffidavitFile: affidavit under under sec 18(1).pdf-
Latest Encumbrance CertificateFile: EC_compressed.pdf-
Consent letter from 2/3rd of AllotteesFile: 2 3 rd Concent Letter.pdf-
Details Of Sold/ Un-sold UnitsFile: Sold Unsold Details.xlsx-
Document 1File: Bank Statement.pdf-
Building Plan-
Approved Plan-
Sale Deed-
agreement for sale-
Download File-
Approved Plan with Extension Licence 01-min-
Approval Layout Plan1-compressed-
Broucher-
Project Specification-
EC 12 Years-
RTC-
Deed-
Existing Layout Plan-
Existing Section Plan and Specification-
Change of Land Use-compressed-
Balance Sheet 2017 - 2018File: BS 2018-min.pdf-
Balance Sheet 2016 - 2017File: BS 2017.pdf-
Balance Sheet 2015 - 2016File: BS 2016-min.pdf-
Audited Profit and Loss Statement 2017 - 2018File: P&L 2018-compressed.pdf-
Audited Profit and Loss Statement 2016 - 2017File: P&L 2017.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P&L 2016-min.pdf-
Director's Report 2017 - 2018File: DR 3.pdf-
Director's Report 2016 - 2017File: DR 2.pdf-
Director's Report 2015 - 2016File: DR 1.pdf-
Cash Flow Statement 2017 - 2018File: CF3.pdf-
Cash Flow Statement 2016 - 2017File: CF2.pdf-
Auditor's Report 2017 - 2018File: AR 3.pdf-
Auditor's Report 2016 - 2017File: AR 2.pdf-
Auditor's Report 2015 - 2016File: AR 1.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: ITR 3.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: ITR 2.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR 1.pdf-
Form B-
Prospectus/BrochureFile: REHANS GOLDEN ORCHID BROCHURE - PRAN583_1.jpg-
Advertisement Copy 1File: A4.jpg-
Tower Excel SheetFile: PRM_KA_RERA_1273_319_PR_190125_002303(2).xlsx-
Loan raised documentFile: NOC.pdf-
Occupancy CertificateFile: Occupancy Certificate.pdf-
Architect certificate for having completed the work(in format no 5)File: Form 5 AC.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: Form 4CC -RA.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit.pdf-
Engineer CertificateFile: Form 6 -EC.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
Valley View Appartment-Completed-Not delivered

How this compares with Udupi

0%of this project is bookeddistrict median 0%
22%of Udupi projects moved their completion datethis one moved by 12 months
0%of Udupi registrations have lapsed or been cancelledthis one is on the register

Computed across the 260+ Udupi projects on ReraGenie, from their own filings.

Keep Golden Orchid on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Udupi260+ in Udupi

Builder: Rehan Associates

Rehan Associates has 1 registration on RERA Karnataka, including Golden Orchid. Its filings disclose 1 earlier RERA Karnataka project, none completed yet. Read the full track record. See more projects on the Udupi district page.

Frequently asked questions

What are my rights if Golden Orchid is delayed beyond 31 Mar 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Golden Orchid?

The registered promoter entity is Rehan Associates, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Golden Orchid?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Golden Orchid?

The professionals named in the filing: Architect: Architecture Plus; Engineer: Design Associtaes. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Golden Orchid?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Golden Orchid. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Golden Orchid to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.