Home / Browse projects / Pune, Maharashtra / Godrej River Crest

Registered Litigation declared Others project

Godrej River Crest

By Manjari Housing Projects LLP

RG-MH-18444 · RERA P52100077127 · Last updated on MahaRERA portal: 26 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 3 cases
  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2030Possession promisedmoved 12 months from the original
2 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 0%
128 of 216Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 121 documents Report an error

Godrej River Crest is a Others project by Manjari Housing Projects LLP in Pune, Maharashtra, registered with MahaRERA as P52100077127 on 23 Jul 2024. Possession is promised by 15 Jun 2030. The completion date has moved by 12 months from the original filing. 88 of the 216 units on this registration are recorded sold or booked, and 2 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameGodrej River Crest
  • TypeOthers
  • Location
    • Off 30 m RP road (Kharadi- Wagholi-Manjari rioad)
    • MANJARI KH
    • Haveli
    • Pune
    • 412307
  • Pincode412307
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100077127
  • ReraGenie IDRG-MH-18444

Builder

  • NameManjari Housing Projects LLP
  • Entity typeOthers
  • Designated PartnersSUBHASISH PATTANAIK, ASHOK DHANRAJ CHORDIA, ATUL ASHOK CHORDIA
  • Other registrations8 more →
  • Completed1 of 9
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects7 →

Key dates

this monthRegisteredJul 2024First promiseJun 2029Revised toJun 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Jul 2024
  • Promised completion15 Jun 2030
  • Revised completionRevised to 15 Jun 2030 (originally 30 Jun 2029)
  • Buildings2 building records
  • Documents filed121 files

Current status

41%88 of 216 units booked
1.4%Work done, per cost certificate

Figures as on 26 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 1NA46261044108
Tower 2NA46261044108

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 26 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.

Tower 19%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower 29%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 26 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed869

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots869
Closed/Covered869
BuildingClosed/CoveredTotal
Tower 1435435
Tower 2434434

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,373 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI40174.67
Proposed, not sanctioned40,175 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop no 789 and 10 Empire Square Off Old Mumbai-Pune Highway Chinchwad - Pune 411019
Estimated costRs 253.19 cr
Cost incurredRs 3.45 cr
Work done1.36%
BuildingWingEstimatedIncurred
Tower 1NARs 128.36 crRs 97.69 lakh
Tower 2NARs 118.56 crRs 98.20 lakh
-NARs 6.27 crRs 1.49 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVK Architecture
ArchitectANA Consortium Pvt Ltd
EngineerMangesh Avinash Lawand
EngineerAnnasaheb Shinde
Chartered AccountantMD Deshpande & Co
Chartered AccountantBSR & Co. LLP
PartnerRole in project
Manjari Housing Projects LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA19012619503Jun 2029 → Jun 2030

Reason as filed by the promoterThe project is expected to start with excavation activity after having received the tree cutting NOC. However, the delay in receipt of final tree cutting NOC was significant and has impacted our construction start timelines and effectively the timeline for project completion. Post receipt of building plan in Jun’24, our project was registered on RERA in Jul’24. Upon registration, the project was launched and unit bookings were realized. However, since last one year, we had been following up with the authorities to get the final tree cutting NOC. After many follow-ups, we have received the fina

Litigation declared3

CaseCourtStatus
SCS No 488/2023/2023Civil Judge Senior Division PunePending
SCS No 489/2023/2023Civil Judge Senior Division PunePending
SCS No 488/2023/2023Civil Judge Senior DivisionOngoing

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12600457Samit Satish SinhaManjari Housing Projects LLP25/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Jul 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jun 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jun 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 15 Jun 2030

Documents filed121

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 121 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Certificate River Crest (23-07-2026).pdf26 Jul 2026
Withdrawal Update Form 2File: R6A Godrej River crest.pdf26 Jul 2026
Withdrawal Update Form 3File: River Crest.pdf26 Jul 2026
Withdrawal Update Form 1File: Godrej River Crest.pdf23 Apr 2026
Withdrawal Update Form 1File: Godrej River Crest.pdf23 Apr 2026
Withdrawal Update Form 2File: R6A Godrej River Crest.pdf23 Apr 2026
Withdrawal Update Form 2File: R6A Godrej River Crest.pdf23 Apr 2026
Withdrawal Update Form 3File: Godrej River Crest.pdf23 Apr 2026
Withdrawal Update Form 3File: Godrej River Crest.pdf23 Apr 2026
Form 2A (FY 2025-2026)File: R6A Annual Quality.pdf23 Apr 2026
Withdrawal Update Form 1File: Form 1_River Crest.pdf20 Jan 2026
Withdrawal Update Form 2File: R6A Godrej River Crest.pdf20 Jan 2026
Withdrawal Update Form 3File: River Crest.pdf20 Jan 2026
Withdrawal Update Form 1File: R6A - River Crest.pdf17 Oct 2025
Withdrawal Update Form 1File: R6A - River Crest.pdf17 Oct 2025
Withdrawal Update Form 2File: R6A Godrej River Crest.pdf17 Oct 2025
Withdrawal Update Form 2File: R6A Godrej River Crest.pdf17 Oct 2025
Withdrawal Update Form 3File: MDD_Godrej River Crest_sept 2025_Signed.pdf17 Oct 2025
Withdrawal Update Form 3File: MDD_Godrej River Crest_sept 2025_Signed.pdf17 Oct 2025
Withdrawal Update Form 1File: River Crest.pdf7 Oct 2025
Withdrawal Update Form 2File: R6A Godrej River Crest.pdf7 Oct 2025
Withdrawal Update Form 3File: River Crest.pdf7 Oct 2025
Withdrawal Update Form 1File: River Crest.pdf3 Oct 2025
Withdrawal Update Form 1File: River Crest.pdf3 Oct 2025
Withdrawal Update Form 1File: River Crest.pdf3 Oct 2025
Withdrawal Update Form 2File: R6A Godrej River Crest.pdf3 Oct 2025
Withdrawal Update Form 2File: R6A Godrej River Crest.pdf3 Oct 2025
Withdrawal Update Form 2File: R6A Godrej River Crest.pdf3 Oct 2025
Withdrawal Update Form 3File: River Crest.pdf3 Oct 2025
Withdrawal Update Form 3File: River Crest.pdf3 Oct 2025
Withdrawal Update Form 3File: River Crest.pdf3 Oct 2025
Form 5 (FY 2024-2025)File: River Crest - 24-25.pdf2 Sep 2025
Form 1File: River Crest.pdf21 Jul 2025
Form 2File: R6A Godrej River Crest.pdf21 Jul 2025
Form 3File: River Crest.pdf21 Jul 2025
Disclosure of Sold and Booked InventoryFile: River Crest.pdf21 Jul 2025
OthersFile: R6A River Crest - Quality assurance certificate - Q1 - June 2025.pdf21 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-Godrej River Crest.pdf21 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: River Crest_Form 1.pdf16 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R6A Godrej River Crest.pdf16 Apr 2025
Disclosure of sold/ booked inventoryFile: River Crest.pdf16 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 _River Crest.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: River crest_Form 3.pdf28 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R6A Godrej River Crest_Form 2.pdf28 Jan 2025
Disclosure of sold/ booked inventoryFile: River Crest_Disclosure Sold Unsold.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: rivercrest_Architect Certificate.pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Rivercrest_CA Certificate.pdf21 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: R6A Godrej River Crest_Engineer Certificate.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: River Crest_Disclosure Sold Unsold.pdf21 Oct 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report_Part3.pdf12 Jul 2024
Copy of the legal title reportFile: Annexure A_part 1_compressed.pdf3 Jul 2024
Copy of the legal title reportFile: Annexure A_part 2_compressed.pdf3 Jul 2024
Copy of the legal title reportFile: Annexure A_part 3_compressed.pdf3 Jul 2024
Copy of the legal title reportFile: Compressed Annexure B - R6 -PDF_updated with litigation table.pdf3 Jul 2024
Copy of the legal title reportFile: Annexure C -R6 PDF_compressed.pdf3 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: PMRDA Mail to MahaRERA.pdf3 Jul 2024
Other - LegalFile: Sccanned_Signed Declaration.pdf3 Jul 2024
Other - LegalFile: Merged Conveyance Document-compressed.pdf3 Jul 2024
Other - LegalFile: Change of Name Certificate.pdf3 Jul 2024
Other - LegalFile: All 712 of Godrej River Crest Survey Numbers.pdf3 Jul 2024
Other - FinanceFile: Signed Declaration_CERSAI Error Report Letter.pdf3 Jul 2024
Other - TechnicalFile: Scanned Annexure A- Declaration cum undertaking.pdf3 Jul 2024
Layout approvalFile: BP-R6A.pdf27 Jun 2024
Layout approvalFile: R6A PLU-Model 1.pdf27 Jun 2024
Building plan approvalFile: 2-33_Parking.pdf27 Jun 2024
Building plan approvalFile: 3-33_GF.pdf27 Jun 2024
Building plan approvalFile: 4-33_Mez.pdf27 Jun 2024
Building plan approvalFile: 5-33_Parking-P1.pdf27 Jun 2024
Building plan approvalFile: 6-33_parking P2.pdf27 Jun 2024
Building plan approvalFile: 7-33_Parking P3.pdf27 Jun 2024
Building plan approvalFile: 8-33_Parking P4.pdf27 Jun 2024
Building plan approvalFile: 9-33_Parking P5.pdf27 Jun 2024
Building plan approvalFile: 10-33_Parking P6.pdf27 Jun 2024
Building plan approvalFile: 11-33_Parking P7.pdf27 Jun 2024
Building plan approvalFile: 12-33_parking P8.pdf27 Jun 2024
Building plan approvalFile: 13-33_First Fl.pdf27 Jun 2024
Building plan approvalFile: 14-33_Even fl.pdf27 Jun 2024
Building plan approvalFile: 15-33_4,6,8fl.pdf27 Jun 2024
Building plan approvalFile: 16-33_Sec.pdf27 Jun 2024
Building plan approvalFile: 17-33_Elev.pdf27 Jun 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Godrej Sky Green Phase 2Sec 5 Gat no 141 P 142 P 146 P Manjari Khurd off Awhalwadi road Taluka Haveli Pune 412307320OngoingMar 2026Mar 2026

How this compares with Pune

41%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Godrej River Crest on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Off 30 m RP road (Kharadi- Wagholi-Manjari rioad)13,700+ in Pune

2 kmGodrej River CrestCompleted 13Lapsed / revoked 5Other 26Dot size: filed unitsN

Filed coordinates, straight-line distance. 44 registered projects within 2 km.

Builder: Manjari Housing Projects LLP

Manjari Housing Projects LLP has 9 registrations on MahaRERA, including GODREJ BOULEVARD and Godrej Park Springs. Its filings disclose 7 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Litigation is declared on 7 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Godrej River Crest is delayed beyond 15 Jun 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Godrej River Crest?

The registered promoter entity is Manjari Housing Projects LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Godrej River Crest?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Godrej River Crest?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Godrej River Crest?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Godrej River Crest?

The professionals named in the filing: Architect: VK Architecture; Architect: ANA Consortium Pvt Ltd; Engineer: Mangesh Avinash Lawand; Engineer: Annasaheb Shinde; Chartered Accountant: MD Deshpande & Co; Chartered Accountant: BSR & Co. LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Godrej River Crest?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Godrej River Crest. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Godrej River Crest to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.