Home / Browse projects / Pune, Maharashtra / Godrej 24

Completed No litigation declared Residential / Group Housing project

Godrej 24

By Pearlite Real Properties Private Limited

RG-MH-10136 · RERA P52100001005 · Last updated on MahaRERA portal: 5 Apr 2023

Source: official MahaRERA filing

Red flags

  • 13 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2022Possession promisedregistration recorded completed
119 of 132Construction stages doneacross 12 buildings; furthest along: Sanitary Fittings within the flats /..., 99%
13Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

Godrej 24 is a Residential / Group Housing project by Pearlite Real Properties Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100001005 on 25 Jul 2017. The registration is recorded completed; possession was promised by 30 Sep 2022. 13 complaints are on record with the regulator.

At a glance

Project

  • NameGodrej 24
  • TypeResidential / Group Housing
  • Location
    • Hinjavadi (CT)
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100001005
  • ReraGenie IDRG-MH-10136

Builder

  • NamePearlite Real Properties Private Limited
  • Entity typeCompany
  • DirectorKrishna Bagaria
  • Other registrations1 more →
  • Completed2 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredJul 2017PromisedSep 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on25 Jul 2017
  • Promised completion30 Sep 2022
  • Revised completionNone
  • Buildings12 building records
  • Documents filed73 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
D1NA190000
D2NA190000
D3NA190000
D4NA190000
D5NA190000
F1NA190000
F2NA190000
G1NA190000
E1NA190000
E2NA190000
E3NA190000
E4NA190000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building12

As on 5 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

119 of 132 construction stages are filed complete across 12 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 99%.

D191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
D291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
D391%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
D491%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises99%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
D591%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
F191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
F291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
G191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E391%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E491%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 5 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes0%
Others UGWTYes100%

Parking filed3046

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3,046
Closed/Covered2,964
Open Space82
BuildingClosed/CoveredOpen SpaceTotal
D12326238
D22327239
D32326238
D42327239
D52316237
F12327239
F22326238
G12326238
E12778285
E22778285
E32777284
E42788286

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area29,912 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
R R Megacity Builders LtdMumbai CityMumbai City
Godrej Properties Limited (as Development Manager)KurlaMumbai Suburban
Pearlite Real Properties Private LimitedMumbai CityMumbai City

Approvals and building plan

Permissible FSI53881.52
Proposed, not sanctioned53,882 sq m
Buildings approved12
Buildings sanctioned12

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMANEKJI WADIA BLDG GROUND FLOOR NANIK MOTWANI MARG FORTMUMBAI - 400001

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKapadia Associates Design LLP
EngineerCBRE South Asia Pvt Ltd,
Chartered AccountantM D Deshpande & Co.
PartnerRole in project
Pearlite Real Properties Private Limited-

Complaints filed with MahaRERA13

Case no.ComplainantRespondentFiled
CC005000000011377JITENDRA KANAKLAL KANDOIJITENDRA KANAKLAL KANDOI04/04/2018
CC005000000053856Aum Gul KeswaniGodrej Properties Limited08/01/2020
CC005000000053862Harsha Gul KeshwaniGodrej Properties Limited08/01/2020
CC005000000106834Lieutnant Colonel Pratap Rajnish Singh and Mrs. Smita Joshi SinghPearllite Real Properties Private Limited26/03/2022
CC005000000096193Jagadish Sudhir AhirraoPEARLITE REAL PROPERTIES PRIVATE LIMITED19/07/2022
CC005000000238619Prasen Girish HawalUjjwal Sarkar09/04/2023
CC005000000310363Kaushal Harkishan ShahSatabdi Chaterjee14/02/2024
CC12401237Pranveer Singh SengarPearlite Real Properties Private Limited25/12/2024
CC12400419Sivaprasad MundarathPearlite Real Properties Private Limited15/10/2024
CC12500423Arpan ChoudhuriPearlite Real Properties Private Limited09/02/2025
CC12501161Venkat Kishanrao HolsambrePearlite Real Properties Private Limited07/04/2025
CC12502913Pranveer Singh SengarPearlite Real Properties Private Limited19/08/2025
CC12604062Akshay Kumar RajagopalPearlite Real Properties Private Limited30/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Jan 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 31 Mar 2023

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4_Godrej 24.pdf5 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC_retail.pdf31 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: GODREJ 24- Form 5.pdf4 Oct 2022
Disclosure of sold/ booked inventoryFile: Disclosure of inventory (1).pdf21 Jul 2022
Disclosure of sold/ booked inventoryFile: Disclosure of inventory.pdf14 Apr 2022
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 ARCHITECT CERTIFICATE.pdf14 Apr 2022
Certificates of CA (Form 3)File: MDD_Godrej 24 Rera Form 3 Q3 21-22A.pdf15 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 24 ARCHITECT CERTIFICATE 311221A.pdf11 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Godrej 24 Engineer Certificate 311221H.pdf11 Feb 2022
Disclosure of sold/ booked inventoryFile: Godrej 24 All Towers 100222G.pdf11 Feb 2022
Layout approvalFile: compressed sheet 1 Building Plan.pdf18 Jan 2022
Layout approvalFile: compressed sheet 2 Building Plan.pdf18 Jan 2022
Copy of Layout Approval (in case of layout)File: compressed sheet 1 Building Plan.pdf18 Jan 2022
Copy of Layout Approval (in case of layout)File: compressed sheet 2 Building Plan.pdf18 Jan 2022
Disclosure of sold/ booked inventoryFile: 24 Sep 21.pdf26 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SEPTEMBER 2021 - FORM 1 ARCHITECT CERTIFICATE GODREJ 24.pdf8 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Godrej 24 Engg Certificate -September 2021.pdf8 Oct 2021
Certificates of CA (Form 5)File: MDD_ G24-Sep 2021 Signed.pdf8 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Godrej 24- RERA certificate FY 20-21-1-7.pdf30 Sep 2021
Disclosure of sold/ booked inventoryFile: Godrej 24 compressed.pdf15 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: JUNE2021 FORM 1 ARCHITECT CERTIFICATE GODREJ 24.pdf10 Jul 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Godrej 24 Engg Certificate June21.pdf10 Jul 2021
Certificates of CA (Form 3)File: MDD G24 June 2021 signed.pdf10 Jul 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: ORIGINAL SOCIETY CERTIFICATE 24.pdf22 Jun 2021
Disclosure of sold/ booked inventoryFile: 24 All Towers Final 220521 compressed opt.pdf25 May 2021
Certificates of CA (Form 3)File: G24-March 2021.pdf25 May 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 200320 OC Copy Page 1 to 4.pdf25 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20210521 FORM 1 ARCHITECT CERTIFICATE DEC 2020 GODREJ 24.pdf23 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20210521 FORM 1 ARCHITECT CERTIFICATE MAR 2021 GODREJ 24.pdf23 May 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Godrej 24 Engg Certificate Monthly Certificate VJ Dec20.pdf12 May 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Godrej 24 Engg Certificate Mar21.pdf12 May 2021
Certificates of CA (Form 3)File: G24-Dec 2020-signed.pdf12 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Godrej 24 RERA Architect certificate_Sept 20.pdf12 Apr 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Godrej 24 Engg Certificate Monthly Certificate Sep20 compressed.pdf12 Apr 2021
Certificates of CA (Form 3)File: G24-Sep 2020-SIGNED.pdf12 Apr 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Godrej 24 Form 5 revised uploaded.pdf1 Oct 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Godrej 24 Architect March 20 uploaded.pdf9 Sep 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Godrej 24 Architect June 20 uploaded.pdf9 Sep 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Godrej 24 Engineer June20 uploaded compressed.pdf9 Sep 2020
Certificates of CA (Form 3)File: G24 June 20 signed uploaded.pdf9 Sep 2020
Certificates of CA (Form 3)File: Q3 FY 2019-20 G24 CA Upload.pdf7 Aug 2020
Certificates of CA (Form 3)File: RERA March20 Pearlite G24 Upload.pdf7 Aug 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Godrej 24 Engg Certificate March 20.pdf27 May 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Godrej 24 Engg Certificate DEC 2019.pdf3 Apr 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Godrej 24 Arch Certificate September 30 2019 compressed.pdf24 Mar 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Godrej 24 Engg Certificate Sept 30 2019 compressed.pdf24 Mar 2020
Certificates of CA (Form 3)File: Godrej 24 Sept 30 2019 CA 1 to 3 compressed.pdf24 Mar 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 24 Architect monthly certificate 31Dec2019.pdf23 Mar 2020
Layout approvalFile: 24- club house 1-71 Layout copy-converted.pdf8 Nov 2019
Copy of Layout Approval (in case of layout)File: 24- club house 1-71 Layout copy-converted.pdf8 Nov 2019
Certificates of CA (Form 5)File: Godrej 24 Form 5.pdf30 Sep 2019
Certificates of CA (Form 5)File: pearlite-ilovepdf-compressed (1).pdf30 Sep 2018
Proforma of Allotment letterFile: Docs 24.pdf5 Jun 2018
Proforma of Allotment letterFile: Docs 24.pdf31 May 2018
Proforma of Allotment letterFile: Godrej 24 - 27-3-18.pdf27 Mar 2018
Proforma of Allotment letterFile: Godrej 24 - updated.pdf6 Mar 2018
Proforma of Allotment letterFile: Godrej 24 - updated.pdf6 Mar 2018
Proforma of Allotment letterFile: G24 RERA - AFS.pdf14 Nov 2017
Declaration in FORM BFile: Form B_Pearlite.pdf22 Jul 2017
Declaration in FORM BFile: Form B_RR MEgacity.pdf22 Jul 2017
Declaration in FORM BFile: Form B_GPL.pdf22 Jul 2017
Layout approvalFile: SANCTION LAYOUT.pdf19 Jul 2017
Building plan approvalFile: COMMENCEMENT CERTIFICATE-compressed.pdf19 Jul 2017
PAN CardFile: Pan Card _Pearlite.pdf19 Jul 2017
Copy of the legal title reportFile: Title Certificaate Supp-compressed.pdf19 Jul 2017
Details of encumbrancesFile: Pearlite-No Encumbarance Certificate.pdf19 Jul 2017
Copy of Layout Approval (in case of layout)File: SANCTION LAYOUT.pdf19 Jul 2017
Building Plan Approval (IOD)File: COMMENCEMENT CERTIFICATE-compressed.pdf19 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE-compressed.pdf19 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE-compressed.pdf19 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf19 Jul 2017
Certificates of CA (Form 3)File: CA CERTIFICATE FOR 24-super compressed.pdf19 Jul 2017
Proforma of Allotment letterFile: Proforma and AFS-compressed.pdf19 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Godrej 24Hinjewadi Taluka Mulshi District Pune816CompletedSep 2021Sep 2021

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Godrej 24 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Hinjavadi (CT)13,700+ in Pune

2 kmGodrej 24Completed 29Lapsed / revoked 15Other 44Dot size: filed unitsN

Filed coordinates, straight-line distance. 88 registered projects within 2 km.

Builder: Pearlite Real Properties Private Limited

Pearlite Real Properties Private Limited has 2 registrations on MahaRERA, including Godrej 24 and Godrej Elements. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Godrej 24 is delayed beyond 30 Sep 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Godrej 24?

The registered promoter entity is Pearlite Real Properties Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Godrej 24?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Godrej 24?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Godrej 24?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Godrej 24?

The professionals named in the filing: Architect: Kapadia Associates Design LLP; Engineer: CBRE South Asia Pvt Ltd,; Chartered Accountant: M D Deshpande & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Godrej 24?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Godrej 24. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Godrej 24 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.