Home / Browse projects / Pune, Maharashtra / Giriraj Grandiose Phase 1
Giriraj Grandiose Phase 1
By Vraj Ratan Home Makers (I) Pvt Ltd
RG-MH-21011 · RERA P52100011510 · Last updated on MahaRERA portal: 20 Jan 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 28 months past the filed date
- 4 complaints at MahaRERA
- Completion date moved by 66 months
- 4 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Giriraj Grandiose Phase 1 is a Others project by Vraj Ratan Home Makers (I) Pvt Ltd in Pune, Maharashtra, registered with MahaRERA as P52100011510 on 31 Aug 2017. Possession was promised by 30 Jun 2024 and is now 28 months past that date. The completion date has moved by 66 months from the original filing. 4 complaints are on record with the regulator.
At a glance
Project
- NameGiriraj Grandiose Phase 1
- TypeOthers
- Location
- Wakad
- Mulshi
- Pune
- 411057
- Pincode411057
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100011510
- ReraGenie IDRG-MH-21011
Builder
- NameVraj Ratan Home Makers (I) Pvt Ltd
- Entity typeCompany
- Managing DirectorsPiyush Vasantlal Thakkar, Ajay Vasantlal Thakker, Vicky Shivram Patil, Pravin NArshi Manani
- Other registrations1 more →
- Completed1 of 2
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on31 Aug 2017
- Promised completion30 Jun 2024
- Revised completionRevised to 30 Jun 2024 (originally 31 Dec 2018)
- Buildings3 building records
- Documents filed70 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing A | NA | 17 | 0 | 0 | 0 | 0 |
| Wing B | NA | 17 | 0 | 0 | 0 | 0 |
| Duplex Bungalow | NA | 4 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 20 Jan 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
21 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Staircases, at 97%.
Wing A79%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 92% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 97% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 82% |
Wing B79%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 92% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 97% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 82% |
Duplex Bungalow82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 20 Jan 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 92% |
| Water Supply | Yes | 52% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 72% |
| Landscaping & Tree Planting | Yes | 52% |
| Street Lighting | Yes | 52% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 72% |
| Electrical meter room, sub-station, receiving station | Yes | 72% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed89
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Wing A | 17 | 20 | 37 |
| Wing B | 12 | 20 | 32 |
| Duplex Bungalow | 8 | 12 | 20 |
Land and ownership26
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Santosh Tukaram Bhujbal | Wakad | Pune |
| Sangita Mahatu Bhujbal | Wakad | Pune |
| Tukaram Baban Bhujbal | Wakad | Pune |
| Manoj Tukaram Bhujbal | Wakad | Pune |
| Manisha maruti Bhujbal | Wakad | Pune |
| Anjana Taraman Bhujmal | Wakad | Pune |
| Balkrushna Taraman Bhujbal | Wakad | Pune |
| Chandrakant Kaushaba Bhujbal | Wakad | Pune |
| Jayshree Dilip Bhujbal | Wakad | Pune |
| Kaushaba baban Bhujbal | Wakad | Pune |
| Lilabai Chandrakant Bhujbal | Wakad | Pune |
| Maruti Hiraman Bhujbal | Wakad | Pune |
| Mahatu Kaushaba Bhujbal | Wakad | Pune |
| Rekha Santosh Bhujbal | Wakad | Pune |
| Shila Manoj Bhujbal | Wakad | Pune |
| Taraman Baban Bhujbal | Wakad | Pune |
| Yogita Balkrushna Bhujbal | Wakad | Pune |
| Alka Sanjay Betkar | Wakad | Pune |
| Dilip Taraman Bhujbal | Wakad | Pune |
| kalpana Gokul Alhat | Wakad | Pune |
| Kusum Tukaram Bhujbal | Wakad | Pune |
| Pushpa prakash ramane | Wakad | Pune |
| Sankuntala baban Alhat | Wakad | Pune |
| shantabhai Kaushaba bhujbal | Wakad | Pune |
| Vimal Manohar Gumatkar | Wakad | Pune |
| yamunabai Hiraman Bhulbal | Wakad | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sankalp Designers |
| Partner | Role in project |
|---|---|
| Vraj Ratan Home Makers (I) Pvt Ltd | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe had registered our project "Giriraj Grandiose Phase 1" on 31.08.2017 but due to covid 19 pandemic we had unable to complete the project till 31.12.2018 (as per completion date of MahaRERA) and also till 30.10.2020 (as per first extension completion date on MahaRERA). so that we have requested you to further extend our project till 31.12.2022.
Reason as filed by the promoterExtension requested on account of litigation.
Reason as filed by the promoterReasons for Extension: • Legal Considerations: A stay order was issued by the honorable court in Writ Petition No. 5489 of 2023 (Annexure B), practically causing a delay of 4 to 4.5 months. A contempt petition (No. 497 of 2023) is pending (Annexure C), with a due date of January 5, 2024. • Previous Delays: Delays and stoppage of activities: The project faced significant delays and a halt in all activities, including obtaining approvals from competent authorities, due to status-quo issues. According to the Divisional Commissioner Office, Pune Revenue Department's Sr. No. RTS/Re/Pune/288/2
Reason as filed by the promoterThe following are the reasons why we could not complete the construction work yet: 1. Extensive Delays and Stoppage of all activities including approvals from competent Authority due to Status - quo. 2. Introduction of UDCPR (Unified Rules) resulted in the revision of Sanctioned Plan which was prolonged due to extensive delays in approval. Hence kindly grant us the extension request in order to serve seamlessly the prospective clients/ home-buyers.
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 577/2016 | Pune | Pending |
Complaints filed with MahaRERA4
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000011497 | Piyush Thakkar | Piyush Thakkar | 04/05/2018 |
| CC005000000011707 | Arun More | Piyush Thakkar | 21/08/2018 |
| CC005000000023381 | NIRMAL NANAK PUNWANI & RAVITA NIRMAL PUNWANI | VRAJ RATAN HOME MAKERS (I) PVT. LTD. | 24/09/2019 |
| CC005000000033523 | mahesh Bhujbal | VRAJ RATAN HOME MAKERS I PVT LTIM | 10/10/2019 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Aug 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Jul 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 22 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed70
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Declaration in FORM BFile: form B Rera.pdf | 20 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Rera.pdf | 20 Jan 2024 |
| Certificates of CA (Form 3)File: Form 3 Signed.pdf | 20 Jan 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Interest all directors.pdf | 20 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 FY 2022-23.pdf | 6 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Architets Certificate.pdf | 5 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 19-20 20-21 21-22 grandiose (1).pdf | 5 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: sales mis grandiose(2).pdf | 5 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Architect Certificate.pdf | 24 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A FY 202122.pdf | 24 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Sales MIS Dec 2022.pdf | 24 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 2021-22.pdf | 24 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked Inventory.pdf | 18 Aug 2022 |
| Building plan approvalFile: 1 - HPSC0899 Upload.pdf | 26 Jul 2022 |
| Building plan approvalFile: 2 - HPSC0901 Upload.pdf | 26 Jul 2022 |
| Building plan approvalFile: 3- HPSC0905 Upload.pdf | 26 Jul 2022 |
| Building plan approvalFile: 4 - HPSC0897 Upload.pdf | 26 Jul 2022 |
| Building plan approvalFile: 5 - HPSC0895 Upload.pdf | 26 Jul 2022 |
| Building plan approvalFile: 6 - HPSC0896 Upload.pdf | 26 Jul 2022 |
| Building plan approvalFile: 7 - HPSC0902 Upload.pdf | 26 Jul 2022 |
| Building plan approvalFile: a1 - HPSC0903 Upload.pdf | 26 Jul 2022 |
| Building Plan Approval (IOD)File: 1 - HPSC0899 Upload.pdf | 26 Jul 2022 |
| Building Plan Approval (IOD)File: 2 - HPSC0901 Upload.pdf | 26 Jul 2022 |
| Building Plan Approval (IOD)File: 3- HPSC0905 Upload.pdf | 26 Jul 2022 |
| Building Plan Approval (IOD)File: 4 - HPSC0897 Upload.pdf | 26 Jul 2022 |
| Building Plan Approval (IOD)File: 5 - HPSC0895 Upload.pdf | 26 Jul 2022 |
| Building Plan Approval (IOD)File: 6 - HPSC0896 Upload.pdf | 26 Jul 2022 |
| Building Plan Approval (IOD)File: 7 - HPSC0902 Upload.pdf | 26 Jul 2022 |
| Building Plan Approval (IOD)File: a1 - HPSC0903 Upload.pdf | 26 Jul 2022 |
| CERSAI detailsFile: Vraj Ratan homemakers Cersai.pdf | 26 Jul 2022 |
| Declaration about Commencement CertificateFile: Declaration About Commencement Certificate.pdf | 25 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Architets Certificate - Upload 25072022.pdf | 25 Jul 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2019-20.pdf | 25 Jul 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2020-21.pdf | 25 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Forme 5 CA certificate FY 2020-21.pdf | 25 Jul 2022 |
| Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment Letter.pdf | 25 Jul 2022 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to model copy of Ageement.pdf | 25 Jul 2022 |
| Details of encumbrances concerned to LegalFile: Encumbrance Certificate Concerned to Legal Upload.pdf | 22 Jul 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate 31122015.pdf | 22 Jul 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate 16102019.pdf | 22 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold booked Inventory 31032022 Upload.pdf | 22 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Forme 5 CA certificate FY 2017-18.pdf | 22 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Forme 5 CA certificate FY 2018-19.pdf | 22 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Forme 5 CA certificate FY 2019-20.pdf | 22 Jul 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account.pdf | 22 Jul 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate Grandiose Upload.pdf | 15 Jul 2022 |
| Certificates of CA (Form 3)File: Form 3 - Giriraj Grandiose Phase 1 Upload.pdf | 15 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Architets Certificate Upload.pdf | 30 Jun 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4th qtr architect certificate111-compressed.pdf | 11 Apr 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5th qtr architect certificate112-compressed.pdf | 11 Apr 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 7th qtr architect certificate110_compressed.pdf | 11 Apr 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Compressed architect certificate.pdf | 28 Mar 2018 |
| Proforma of Allotment letterFile: Agreement_to_sell_-_Page_1_to_10 - Copy.pdf | 4 Aug 2017 |
| Proforma of Allotment letterFile: Agreement_to_sell_-_Page_11_to_17.pdf | 4 Aug 2017 |
| Proforma of Allotment letterFile: Agreement_to_sell_-_Page_18_to_24.pdf | 4 Aug 2017 |
| OtherFile: Co promoter decleration.pdf | 4 Aug 2017 |
| Building plan approvalFile: CC.pdf | 3 Aug 2017 |
| Layout approvalFile: Grandiose plan1.pdf | 3 Aug 2017 |
| Copy of the legal title reportFile: Search and title report new_Part1(1).pdf | 3 Aug 2017 |
| Copy of the legal title reportFile: Search and title report new_Part2(2).pdf | 3 Aug 2017 |
| Details of encumbrancesFile: Encumbrance certificate Phase 1.pdf | 3 Aug 2017 |
| Copy of Layout Approval (in case of layout)File: Grandiose plan1.pdf | 3 Aug 2017 |
| Building Plan Approval (IOD)File: CC.pdf | 3 Aug 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Latest EngineerCertificate Grandiose Ph I.pdf | 3 Aug 2017 |
| Certificates of CA (Form 3)File: C_A_Certificate08032017.pdf | 3 Aug 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 2 Aug 2017 |
| Declaration in FORM BFile: Form_B_Company_Declaration (1).pdf | 2 Aug 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate.pdf | 2 Aug 2017 |
| Proforma of Allotment letterFile: Allotment_letter.pdf | 2 Aug 2017 |
| PAN CardFile: Vraj Ratan Home Makers (I) Pvt Ltd Pan Card.pdf | 30 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 70 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Giriraj Grandiose Phase 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Wakad13,700+ in Pune
Filed coordinates, straight-line distance. 261 registered projects within 2 km.
Godrej Evergreen Square
Godrej Projects Development Limited
The Aqua Retreat at Godrej Park World
Maan-Hinje Township Developers Private Lim
The Gale at Godrej Park World
Maan-Hinje Township Developers LLP
VTP BELLISSIMO PHASE 1
MAGNITE DEVELOPERS PRIVATE LIMITED
Life Republic Sector R1 - 1st Avenue
KOLTE-PATIL DEVELOPERS LIMITED
The Greenfront at Godrej Park World
Maan Hinje Township Developers Private Lim
Builder: Vraj Ratan Home Makers (I) Pvt Ltd
Vraj Ratan Home Makers (I) Pvt Ltd has 2 registrations on MahaRERA, including Giriraj Grandiose Phase 1 and Mauli Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Giriraj Grandiose Phase 1 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Giriraj Grandiose Phase 1 is delayed beyond 30 Jun 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Giriraj Grandiose Phase 1?
The registered promoter entity is Vraj Ratan Home Makers (I) Pvt Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Giriraj Grandiose Phase 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Giriraj Grandiose Phase 1?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Giriraj Grandiose Phase 1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Giriraj Grandiose Phase 1?
The professionals named in the filing: Architect: Sankalp Designers. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Giriraj Grandiose Phase 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback