Home / Browse projects / Mumbai Suburban, Maharashtra / GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED
GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED
By GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED
RG-MH-75638 · RERA P51800048383 · Last updated on MahaRERA portal: 20 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED is a Residential / Group Housing project by GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800048383 on 3 Jan 2023. Possession is promised by 31 Jul 2027. The completion date has moved by 24 months from the original filing. 14 of the 56 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameGET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED
- TypeResidential / Group Housing
- Location
- MILITARY ROAD
- MAROL
- Andheri
- Mumbai Suburban
- 400059
- Pincode400059
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800048383
- ReraGenie IDRG-MH-75638
Builder
- NameGET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED
- Entity typeSociety
- SecretoryDHIRAJLAL MAGANLAL SHETH
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on3 Jan 2023
- Promised completion31 Jul 2027
- Revised completionRevised to 31 Jul 2027 (originally 31 Jul 2025)
- Buildings1 building record
- Documents filed135 files
Current status
Figures as on 20 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED | NA | 7 | 7 | 43 | 13 | 56 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.
GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED: 49% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 10% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 85% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed54
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED | Andheri | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED | NA | Rs 21.00 cr | Rs 22.38 cr |
| - | NA | Rs 6.00 cr | Rs 2.45 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SANJAY JADHAV |
| Engineer | SHAHNAWAZ NIYAZ AHMED SIDDIQUI |
| Engineer | BILAL MS LAKDAWALA |
| Chartered Accountant | A B C & ASSOCIATES |
| Partner | Role in project |
|---|---|
| GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterPromoter has applied for Floor rise and Revalidation of CC
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000591031 | ASHOK KUMAR MOOLCHAND BAPNA | GET TOGETHER CO OPERATIVE HOUSING SOCIETY LTD | 05/07/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 23 Sep 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Oct 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Oct 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Jul 2027
Documents filed135
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 135 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Architect Certificate.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: 2026-07-17_Form 2 Engineer Certificate_GTG_Updated.pdf | 20 Jul 2026 |
| Withdrawal Update Form 3File: GET TOGETHER RERA CERTIFICATE Form 3_June 2026_1.pdf | 20 Jul 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 20 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate-GetTogether.pdf | 20 Apr 2026 |
| Withdrawal Update Form 3File: GET TOGETHER RERA CERTIFICATE Form 3_March 2026.pdf | 20 Apr 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 20 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate_Q3.pdf | 20 Jan 2026 |
| Withdrawal Update Form 3File: GET TOGETHER RERA CERTIFICATE Form 3_Dec 2025.pdf | 20 Jan 2026 |
| Withdrawal Update Form 1File: Architect Application Letter.pdf | 13 Jan 2026 |
| Withdrawal Update Form 2File: Form 2_2025-26_Q2.pdf | 13 Jan 2026 |
| Withdrawal Update Form 3File: GET TOGETHER RERA CERTIFICATE Form 3_Sept 2025.pdf | 13 Jan 2026 |
| Form 5 (FY 2024-2025)File: Form 5_Get Together 31032025.pdf | 24 Oct 2025 |
| Withdrawal Update Form 1File: Architect Application Letter.pdf | 18 Oct 2025 |
| Withdrawal Update Form 2File: Form 2_2025-26_Q2.pdf | 18 Oct 2025 |
| Withdrawal Update Form 3File: GET TOGETHER RERA CERTIFICATE Form 3_Sept 2025.pdf | 18 Oct 2025 |
| Form 2A (FY 2024-2025)File: Form2A_Get Together 2024-25.pdf | 30 Jul 2025 |
| Form 2A (FY 2023-2024)File: 5_Form_2A_Jan 24-April 2024.pdf | 30 Jul 2025 |
| Form 2A (FY 2022-2023)File: 2_Form 2A_Get Together - Jan23 to Mar23.pdf | 30 Jul 2025 |
| Form 5 (FY 2022-2023)File: Form 5_Get Together 2022-23.pdf | 30 Jul 2025 |
| Form 1File: Form 1_Q4 2024-25_Architect.pdf | 29 Jul 2025 |
| Form 2File: 5_Form_2A_APRIL2025 docx[1] Signed.pdf | 29 Jul 2025 |
| Form 3File: GET TOGETHER RERA CERTIFICATE Form 3_March 2025.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold ,Booked Inventory -Building.pdf | 29 Jul 2025 |
| Self-declaration of Quarterly ProgressFile: Self Declaration Get Together.pdf | 29 Jul 2025 |
| Form 1File: Form 1_Architects Certificate Signed.pdf | 29 Jul 2025 |
| Form 2File: 5_Engineer_Certificate_ Dec 2024-Jan 25.pdf | 29 Jul 2025 |
| Form 3File: GET TOGETHER RERA CERTIFICATE Form 3_March 2025.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold ,Booked Inventory -Building.pdf | 29 Jul 2025 |
| Self-declaration of Quarterly ProgressFile: Self Declaration Get Together.pdf | 29 Jul 2025 |
| Form 1File: Form 1_Get Together_Q2_2024-25.pdf | 29 Jul 2025 |
| Form 2File: Form 2_Get Together_Q2_2024-25.pdf | 29 Jul 2025 |
| Form 3File: Form 3_Get Together Quarter 1_2024-25.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold ,Booked Inventory -Building.pdf | 29 Jul 2025 |
| Form 1File: 5_Form_2A April24-June 2024 (1).pdf | 29 Jul 2025 |
| Form 2File: 5_Engineer Certificate_APRIL2024-JUNE 24 (1).pdf | 29 Jul 2025 |
| Form 3File: Form 3_Get Together Quarter 1_2024-25.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold ,Booked Inventory -Building.pdf | 29 Jul 2025 |
| Form 1File: Architect Certificate.pdf | 29 Jul 2025 |
| Form 2File: 5_Engineer Certificate_JAN 2024-April 24.pdf | 29 Jul 2025 |
| Form 3File: GET TOGETHER RERA CERTIFICATE Form 3_March 2024.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold ,Booked Inventory -Building.pdf | 29 Jul 2025 |
| Form 1File: Architect Certificate 08 01 2024 final signed.pdf | 29 Jul 2025 |
| Form 2File: Form 2_Engineer Certificate_Oct23 to Dec23.pdf | 29 Jul 2025 |
| Form 3File: GET TOGETHER RERA CERTIFICATE Form 3_Dec 2023.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold ,Booked Inventory -Building.pdf | 29 Jul 2025 |
| Form 1File: Architect Certificate 08 01 2024 final signed.pdf | 29 Jul 2025 |
| Form 2File: Form 2_Engineer Certificate_Oct23 to Dec23.pdf | 29 Jul 2025 |
| Form 3File: GET TOGETHER RERA CERTIFICATE Form 3_Dec 2023.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold ,Booked Inventory -Building.pdf | 29 Jul 2025 |
| Form 1File: Architect Certificate 01 04 2023 signed.pdf | 29 Jul 2025 |
| Form 2File: 3_Engineer Certificate_Apr23 to Jun23.pdf | 29 Jul 2025 |
| Form 3File: GET TOGETHER RERA CERTIFICATE Form 3_June 2023.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold ,Booked Inventory -Building.pdf | 29 Jul 2025 |
| Form 1File: Architect Certificate 01 01 2023 signed.pdf | 29 Jul 2025 |
| Form 2File: 2_Engineer Certificate_Jan23 to Mar23.pdf | 29 Jul 2025 |
| Form 3File: GET TOGETHER RERA CERTIFICATE Form 3_Mar 2023.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold ,Booked Inventory -Building.pdf | 29 Jul 2025 |
| Form 1File: Architect Certificate 16 07 2025 signed.pdf | 20 Jul 2025 |
| Form 2File: Form 2 Engineer Certificate-signed.pdf | 20 Jul 2025 |
| Form 3File: Form 3_GET TOGETHER RERA CERTIFICATE_June 2025.pdf | 20 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold ,Booked Inventory -Building.pdf | 20 Jul 2025 |
| Self-declaration of Quarterly ProgressFile: Self Declaration Get Together.pdf | 20 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Q4 2024-25_Architect.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: GET TOGETHER RERA CERTIFICATE Form 3_March 2025.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architects Certificate Signed.pdf | 25 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5_Engineer_Certificate_ Dec 2024-Jan 25.pdf | 25 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Get Together_Q2_2024-25.pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: GET TOGETHER RERA CERTIFICATE Form 3_June 2024.pdf | 19 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5_Engineer_Certificate_july24_to_sept24 (1).pdf | 18 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 5_Form_2A_JULY- SEPT 2024 docx (1).pdf | 18 Oct 2024 |
| Layout approvalFile: Drawing-1-4.pdf | 17 Oct 2024 |
| Layout approvalFile: Drawing-5-7.pdf | 17 Oct 2024 |
| Copy of Layout Approval (in case of layout)File: Drawing-1-4.pdf | 17 Oct 2024 |
| Copy of Layout Approval (in case of layout)File: Drawing-5-7.pdf | 17 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA COMPLETION OF WORK 13 07 2024 signed.pdf | 17 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5_Engineer Certificate_APRIL2024-JUNE 24 (1).pdf | 17 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 5_Form_2A April24-June 2024 (1).pdf | 17 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Get Together Quarter 1_2024-25.pdf | 17 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 19 Apr 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 135 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep GET TOGETHER CO OPERATIVE HOUSING SOCIETY LI on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MAROL6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 110 registered projects within 2 km.
SKYLINE BUSINESS WORLD WING C
Skyline Prashasti
NAMAN PREMIER
SHREE NAMAN DEVELOPERS PVT LTD
I STAY TOWER K (STUDIO)
I-STAY HOUSING PRIVATE LIMITED
CHANDAK SARVAM
CHANDAK REALTORS PRIVATE LIMITED
TRILIVE MAROL TOWER B
I-STAY HOUSING PRIVATE LIMITED
TBC Marol Phase 1
AGATE REALTORS AND DEVELOPERS
See every Mumbai Suburban project, with the district possession charts
Builder: GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED
GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED has 1 registration on MahaRERA, including GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED is delayed beyond 31 Jul 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED?
The registered promoter entity is GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED, a society as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED?
The professionals named in the filing: Architect: SANJAY JADHAV; Engineer: SHAHNAWAZ NIYAZ AHMED SIDDIQUI; Engineer: BILAL MS LAKDAWALA; Chartered Accountant: A B C & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GET TOGETHER CO OPERATIVE HOUSING SOCIETY LIMITED?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback