Home / Browse projects / Thane, Maharashtra / GEETANT ASHRAY

Registration lapsed No litigation declared Others project

GEETANT ASHRAY

By VASUDHA CONSTRUCTION COMPANY

RG-MH-05273 · RERA P51700050597 · Last updated on MahaRERA portal: 5 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 12 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
9 of 11Construction stages donefurthest along: Installation of Lifts, 95%
16 of 37Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 64 documents Report an error

GEETANT ASHRAY is a Others project by VASUDHA CONSTRUCTION COMPANY in Thane, Maharashtra, registered with MahaRERA as P51700050597 on 21 Apr 2023. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 12 months from the original filing. 21 of the 37 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameGEETANT ASHRAY
  • TypeOthers
  • Location
    • RAMDASWADI
    • CHIKANGHAR
    • Chavindra
    • Thane
    • 421301
  • Pincode421301
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700050597
  • ReraGenie IDRG-MH-05273

Builder

  • NameVASUDHA CONSTRUCTION COMPANY
  • Entity typePartnership
  • PartnersATUL ANANT MALBARI, AMOL ANANT MALBARI

Key dates

10 months past promisethis monthRegisteredApr 2023First promiseDec 2024Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on21 Apr 2023
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed64 files

Current status

57%21 of 37 units booked
100.0%Work done, per cost certificate

Figures as on 5 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GEETANT ASHRAYNA9728937

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

GEETANT ASHRAY: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 5 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed94

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots94
Closed/Covered47
Open Space47

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area780 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on23 Jul 2025

Approvals and building plan

Sanctioning authorityKalyan Dombivli Municipal Corporation
Permissible FSI1879.66
Proposed, not sanctioned1,880 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 127 PLOT NO 2A SARASWATI BUILDING SANTOSHI MATA ROAD RAMBAUG KALYAN WEST
Estimated costRs 6.84 cr
Cost incurredRs 6.84 cr
Work done100.0%
BuildingWingEstimatedIncurred
GEETANT ASHRAYNARs 5.87 crRs 5.87 cr
-NARs 97.78 lakhRs 97.78 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectA S DASTANE AND ASSOCIATES
EngineerCREATIVE DESIGNS
Chartered AccountantRPMG AND ASSOCIATES CHARTED ACCOUNTANTS
Chartered AccountantD H Purohit & Associates
Chartered AccountantC M LAD & ASSOCIATES
PartnerRole in project
VASUDHA CONSTRUCTION COMPANY-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700025919Dec 2024 → Jun 2025

Reason as filed by the promoterthe project has faced unforeseen delays due to ongoing road construction work in the vicinity, which has significantly impacted the supply of construction materials and availability of labour. The restricted "movement of transportation vehicles and workers has adversely affected the progress of our project, causing unavoidable delays beyond our control

EA23072502169Dec 2024 → Dec 2025

Reason as filed by the promoterThe Project got delayed due to an unforeseen shortage of labour caused by health crises, migration of workers, etc. Despite our best efforts to secure adequate labour resources, the unavailability of skilled labour has led to unavoidable setbacks in the progress of the work. Once the above work is completed, we will make application for Completion Certificate (CC)/Occupancy Certificate (OC) with the respective Municipal Authority. Obtaining CC/OC will take a few months; hence we make a humble request to you to provide an extension.

Litigation declared1

CaseCourtStatus
RCS NO 322 OF 2014/2014KALYAN COURTTHE MATTER IS POSTED FOR AGRUMENT ON THE SAID APPLICATION FOR AMMENDMENT

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Mar 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Mar 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed64

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 DEC25.pdf5 May 2026
Withdrawal Update Form 2File: FORM 2 DEC25.pdf5 May 2026
Withdrawal Update Form 3File: FORM 3 DEC25.pdf5 May 2026
Withdrawal Update Form 1File: FORM 1 SEP25.pdf22 Apr 2026
Withdrawal Update Form 2File: FORM 2 SEP25.pdf22 Apr 2026
Withdrawal Update Form 3File: FORM 3 SEP 25.pdf22 Apr 2026
Form 5 (FY 2024-2025)File: Signed Form 5.pdf31 Jul 2025
Form 1File: Form 1 march-25.pdf18 Jul 2025
Form 2File: Form 2 march-25.pdf18 Jul 2025
Form 3File: FORM 3.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE.pdf18 Jul 2025
Form 1File: Form 1 june 25.pdf18 Jul 2025
Form 2File: Form 2 june 25.pdf18 Jul 2025
Form 3File: FORM 3 JUNE 25.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: sold unsold inventory june 25.pdf18 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 dec24.pdf10 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 dec 24_.pdf10 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 dec24.pdf10 Feb 2025
Declaration in FORM BFile: FORM B.pdf30 Dec 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD.pdf30 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 JUNE24 - .pdf23 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SEPT 24 -.pdf23 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 june 24 .pdf23 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SEP 24_.pdf23 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 JUNE24 - .pdf23 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SEPT 24 .pdf23 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 .pdf23 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 DEC23.pdf13 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 MARCH24.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 DEC23.pdf13 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 MARCH24.pdf13 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A MARCH24.pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 DECEMBER FINAL.pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 FINAL MARCH 24.pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf12 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30 June 2023 Final.pdf25 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30 June 23.pdf21 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30sept23.pdf21 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30june23.pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30sept23.pdf20 Oct 2023
Other - TechnicalFile: Revised CC.pdf5 Apr 2023
Proforma of Agreement for saleFile: Agreement for Sale new.pdf3 Apr 2023
Layout approvalFile: PLAN LAYOUT_Compressed.pdf21 Mar 2023
Building plan approvalFile: PLAN LAYOUT_Compressed.pdf21 Mar 2023
Copy of the legal title reportFile: legal title of report.pdf21 Mar 2023
Details of encumbrances concerned to FinanceFile: Letter of Financial Encumbrances.pdf21 Mar 2023
Details of encumbrances concerned to FinanceFile: Letter of Legal Encumbrances.pdf21 Mar 2023
Details of encumbrances concerned to LegalFile: Letter of Financial Encumbrances.pdf21 Mar 2023
Details of encumbrances concerned to LegalFile: Letter of Legal Encumbrances.pdf21 Mar 2023
Copy of Layout Approval (in case of layout)File: PLAN LAYOUT_Compressed.pdf21 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: PLAN LAYOUT_Compressed.pdf21 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_Compressed.pdf21 Mar 2023
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf21 Mar 2023
Declaration in FORM BFile: Form B.pdf21 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf21 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf21 Mar 2023
CERSAI detailsFile: CERSAI.pdf21 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Compressed.pdf21 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate Organisation.pdf21 Mar 2023
Proforma of Allotment letterFile: Allotment letter.pdf21 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about separate bank account.pdf21 Mar 2023
Deviation Report with respect to Allotment letterFile: No Deviation in Model Allottment Letter.pdf21 Mar 2023
Deviation Report with respect to model copy of AgreementFile: No Deviation in Agreement for sale.pdf21 Mar 2023
PAN CardFile: PAN (Firm).pdf20 Mar 2023

How this compares with Thane

57%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GEETANT ASHRAY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHIKANGHAR7,600+ in Thane

2 kmGEETANT ASHRAYCompleted 86Lapsed / revoked 51Other 131Dot size: filed unitsN

Filed coordinates, straight-line distance. 268 registered projects within 2 km.

Builder: VASUDHA CONSTRUCTION COMPANY

VASUDHA CONSTRUCTION COMPANY has 1 registration on MahaRERA, including GEETANT ASHRAY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that GEETANT ASHRAY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if GEETANT ASHRAY is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GEETANT ASHRAY?

The registered promoter entity is VASUDHA CONSTRUCTION COMPANY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GEETANT ASHRAY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GEETANT ASHRAY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GEETANT ASHRAY?

The professionals named in the filing: Architect: A S DASTANE AND ASSOCIATES; Engineer: CREATIVE DESIGNS; Chartered Accountant: RPMG AND ASSOCIATES CHARTED ACCOUNTANTS; Chartered Accountant: D H Purohit & Associates; Chartered Accountant: C M LAD & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GEETANT ASHRAY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GEETANT ASHRAY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GEETANT ASHRAY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.