GEETA PLAZA

By ROYAL DEVELOPERS

RG-MH-29487 · RERA P51700028915 · Last updated on MahaRERA portal: 1 Oct 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 18 months, 4 of them under MahaRERA's automatic 4-month extension
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 18 months from the original
4 of 11Construction stages donefurthest along: Staircases, 95%
35 of 43Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 94 documents Report an error

GEETA PLAZA is a Others project by ROYAL DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700028915 on 12 Apr 2021. Possession is promised by 31 Dec 2027. The completion date has moved by 18 months from the original filing, 4 of them under MahaRERA's automatic 4-month extension for the West Asia conflict. 8 of the 43 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameGEETA PLAZA
  • TypeOthers
  • Location
    • FARID ROAD
    • MAHAGIRI THANE
    • Chavindra
    • Thane
    • 400601
  • Pincode400601
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700028915
  • ReraGenie IDRG-MH-29487

Builder

  • NameROYAL DEVELOPERS
  • Entity typePartnership
  • PartnerYOGESH BHOSALE
  • Other registrations16 more →
  • Completed5 of 17
  • No longer live6 lapsed, de-registered or revoked
  • Declared earlier projects6 →

Key dates

this monthRegisteredApr 2021First promiseJun 2026Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on12 Apr 2021
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Jun 2026)
  • Buildings1 building record
  • Documents filed94 files

Current status

19%8 of 43 units booked
80.2%Work done, per cost certificate

Figures as on 1 Oct 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ROYAL VILLANA75331043

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 95%.

ROYAL VILLA: 68% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 1 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area507 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Jun 2025

Approvals and building plan

Sanctioning authorityThane Munciple corporation
Permissible FSI1237.65
Proposed, not sanctioned1,238 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKHARKARARLI THANE WEST
Estimated costRs 4.22 cr
Cost incurredRs 3.39 cr
Work done80.23%
BuildingWingEstimatedIncurred
ROYAL VILLANARs 3.93 crRs 3.36 cr
-NARs 28.83 lakhRs 2.99 lakh

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMAKRAND TORASKAR
EngineerTECH LINE
EngineerNimbalkar Enterprises
Chartered AccountantRAHUL
Chartered AccountantRAHUL Thorve
Chartered AccountantPBG & ASSOCIATES
Chartered AccountantN N Bagwan and Associates
PartnerRole in project
ROYAL DEVELOPERS-

Extensions2

A revised date filed with the regulator does not change the possession date in your agreement for sale. Commentary on the order notes that a buyer's right to interest for delay under section 18 of RERA may still stand; that question has not been tested.

MahaRERA order of 7 Aug 2026Jun 2026 → Oct 2026

Granted by MahaRERA, not applied for by the promoterMahaRERA's order of 7 August 2026 extended the completion date of eligible registered projects by four months, treating the West Asia conflict as force majeure. Promoters did not have to apply for it.

EA22092638959Jun 2026 → Dec 2027

Reason as filed by the promoter1. Procedural delays at planning authority for revision of sanctioned plans has taken longer than expected time which lead to delay of approx. 8-10 months. 2. Also due to prevailing War conditions, fuel availability issues, building material availability and labour migrations in the region project work was affected nearly 1-2 months. 3. Promoters are near to completion of the project and hopeful that they will get part completion certificate for these building by June 2027. Hence on this basis also we request Your Honor to extend the proposed completion date of project till 31-12-2027.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Feb 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Feb 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Sep 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Sep 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed94

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1- 31-03-2026.pdf1 Oct 2026
Withdrawal Update Form 2File: 12June 2026.pdf1 Oct 2026
Withdrawal Update Form 3File: 11FORM-3 30062026.pdf1 Oct 2026
Form 1File: Form 1- 31-03-2022.pdf29 Sep 2026
Form 2File: 1March 2022.pdf29 Sep 2026
Form 3File: 1FORM-3 31032022.pdf29 Sep 2026
Disclosure of Sold and Booked InventoryFile: 1DISCLOSURE OF INVENTORY MARCH 2022.pdf29 Sep 2026
Form 1File: Form 1 - 01-07-2024.pdf29 Sep 2026
Form 2File: 2March 2023.pdf29 Sep 2026
Form 3File: 2FORM-3 31032023.pdf29 Sep 2026
Disclosure of Sold and Booked InventoryFile: 2DISCLOSURE OF INVENTORY MARCH 2023.pdf29 Sep 2026
Form 1File: Form 1 - 01-07-2024.pdf29 Sep 2026
Form 2File: 3March 2024.pdf29 Sep 2026
Form 3File: 3FORM-3 31032024.pdf29 Sep 2026
Disclosure of Sold and Booked InventoryFile: 3DISCLOSURE OF INVENTORY MARCH 2024.pdf29 Sep 2026
Form 1File: Form 1- 31-03-2025.pdf29 Sep 2026
Form 2File: 7March 2025.pdf29 Sep 2026
Form 3File: 6FORM-3 31032025.pdf29 Sep 2026
Disclosure of Sold and Booked InventoryFile: 7DISCLOSURE OF INVENTORY MARCH 2025.pdf29 Sep 2026
Form 1File: Form 1 - 01-07-2024.pdf29 Sep 2026
Form 2File: 4June 2024.pdf29 Sep 2026
Form 3File: 4FORM-3 30062024.pdf29 Sep 2026
Disclosure of Sold and Booked InventoryFile: 4DISCLOSURE OF INVENTORY JUNE 2024.pdf29 Sep 2026
Form 1File: Form 1 - 30-09-2024.pdf29 Sep 2026
Form 2File: 5Sept 2024.pdf29 Sep 2026
Form 3File: 5FORM-3 31122024.pdf29 Sep 2026
Disclosure of Sold and Booked InventoryFile: 5DISCLOSURE OF INVENTORY SEPT 2024.pdf29 Sep 2026
Form 1File: Form 1- 31-12-2024.pdf29 Sep 2026
Form 2File: 6Dec 2024.pdf29 Sep 2026
Form 3File: 5FORM-3 31122024.pdf29 Sep 2026
Disclosure of Sold and Booked InventoryFile: 6DISCLOSURE OF INVENTORY DEC 2024.pdf29 Sep 2026
Form 2A (FY 2021-2022)File: FORM-2A FY 2022.pdf25 Sep 2026
Form 2A (FY 2022-2023)File: FORM-2A FY 2023.pdf25 Sep 2026
Form 2A (FY 2023-2024)File: FORM-2A FY 2024.pdf25 Sep 2026
Building plan approvalFile: 1 of 3.pdf22 Sep 2026
Building plan approvalFile: 2 of 3.pdf22 Sep 2026
Building plan approvalFile: 3 of 3.pdf22 Sep 2026
Commencement certificateFile: CC.pdf22 Sep 2026
Withdrawal Update Form 1File: Form 1 - 30-06-2025.pdf22 Sep 2026
Withdrawal Update Form 1File: Form 1 - 30-06-2025.pdf22 Sep 2026
Withdrawal Update Form 1File: Form 1- 31-03-2026.pdf22 Sep 2026
Withdrawal Update Form 1File: Form 1- 31-03-2026.pdf22 Sep 2026
Withdrawal Update Form 1File: Form 1- 31-03-2026.pdf22 Sep 2026
Withdrawal Update Form 1File: Form 1- 31-03-2026.pdf22 Sep 2026
Withdrawal Update Form 2File: 8June 2025.pdf22 Sep 2026
Withdrawal Update Form 2File: 9Sept 2025.pdf22 Sep 2026
Withdrawal Update Form 2File: 10Dec 2025.pdf22 Sep 2026
Withdrawal Update Form 2File: 11March 2026.pdf22 Sep 2026
Withdrawal Update Form 2File: 12June 2026.pdf22 Sep 2026
Withdrawal Update Form 2File: 12June 2026.pdf22 Sep 2026
Withdrawal Update Form 3File: 7FORM-3 30062025.pdf22 Sep 2026
Withdrawal Update Form 3File: 8FORM-3 30092025.pdf22 Sep 2026
Withdrawal Update Form 3File: 9FORM-3 31122025.pdf22 Sep 2026
Withdrawal Update Form 3File: 10FORM-3 31032026.pdf22 Sep 2026
Withdrawal Update Form 3File: 11FORM-3 30062026.pdf22 Sep 2026
Withdrawal Update Form 3File: 11FORM-3 30062026.pdf22 Sep 2026
Form 2A (FY 2024-2025)File: FORM-2A FY 2025.pdf16 Sep 2026
Form 2A (FY 2025-2026)File: FORM-2A FY 2026.pdf10 Sep 2026
Form 5 (FY 2021-2022)File: Form 5 21-22.pdf9 Sep 2026
Form 5 (FY 2022-2023)File: Form 5 22-23.pdf9 Sep 2026
Form 5 (FY 2023-2024)File: FORM 5 23-24.pdf9 Sep 2026
Form 5 (FY 2024-2025)File: FORM 5 24-25.pdf9 Sep 2026
Form 5 (FY 2025-2026)File: Form 5 25-26.pdf9 Sep 2026
Withdrawal Update Form 1File: form 1.pdf8 Jul 2025
Withdrawal Update Form 1File: form 1.pdf8 Jul 2025
Withdrawal Update Form 1File: form 1.pdf8 Jul 2025
Withdrawal Update Form 1File: form 1.pdf8 Jul 2025
Withdrawal Update Form 1File: form 1.pdf8 Jul 2025
Withdrawal Update Form 2File: Engineeru0027s Certificate[40510].pdf8 Jul 2025
Withdrawal Update Form 2File: Engineeru0027s Certificate[40510].pdf8 Jul 2025
Withdrawal Update Form 2File: Engineeru0027s Certificate[40510].pdf8 Jul 2025
Withdrawal Update Form 2File: Engineeru0027s Certificate[40510].pdf8 Jul 2025
Withdrawal Update Form 2File: Engineeru0027s Certificate[40510].pdf8 Jul 2025
Withdrawal Update Form 3File: Form 3 signed.pdf8 Jul 2025
Withdrawal Update Form 3File: Form 3 signed.pdf8 Jul 2025
Withdrawal Update Form 3File: Form 3 signed.pdf8 Jul 2025
Withdrawal Update Form 3File: Form 3 signed.pdf8 Jul 2025
Withdrawal Update Form 3File: Form 3 signed.pdf8 Jul 2025
Declaration about Commencement CertificateFile: CC Declaration.pdf28 Jun 2021
Disclosure of sold/ booked inventoryFile: Sold.pdf23 Jun 2021

How this compares with Thane

19%of this project is bookeddistrict median 24%
25%of Thane projects moved their completion datethis one moved by 18 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,700+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GEETA PLAZA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MAHAGIRI THANE7,700+ in Thane

2 kmGEETA PLAZACompleted 102Lapsed / revoked 72Other 145Dot size: filed unitsN

Filed coordinates, straight-line distance. 319 registered projects within 2 km.

Builder: ROYAL DEVELOPERS

ROYAL DEVELOPERS has 17 registrations on MahaRERA, including UTSAV RESIDENCY and Gurukripa Appartment. Its filings disclose 6 earlier MahaRERA projects: declares 6 of 6 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if GEETA PLAZA is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GEETA PLAZA?

The registered promoter entity is ROYAL DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GEETA PLAZA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GEETA PLAZA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GEETA PLAZA?

The professionals named in the filing: Architect: MAKRAND TORASKAR; Engineer: TECH LINE; Engineer: Nimbalkar Enterprises; Chartered Accountant: RAHUL; Chartered Accountant: RAHUL Thorve; Chartered Accountant: PBG & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GEETA PLAZA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GEETA PLAZA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GEETA PLAZA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.