ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / GBT

Registered No litigation declared Commercial project

GBT

By GOKHALE DECCAN LANDMARKS LLP

RG-MH-89807 · RERA P52100048728 · Last updated on MahaRERA portal: 9 Mar 2026

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 60 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2030Possession promisedmoved 60 months from the original
0 of 11Construction stages donefurthest along: Excavation, 95%
9 of 9Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 98 documents Report an error

GBT is a Commercial project by GOKHALE DECCAN LANDMARKS LLP in Pune, Maharashtra, registered with MahaRERA as P52100048728 on 17 Jan 2023. Possession is promised by 1 Sep 2030. The completion date has moved by 60 months from the original filing. 0 of the 9 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameGBT
  • TypeCommercial
  • Location
    • -
    • SHIVAJINGAR BHAMBURDA
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411004
  • Pincode411004
  • RERA no.P52100048728
  • ReraGenie IDRG-MH-89807

Builder

  • NameGOKHALE DECCAN LANDMARKS LLP
  • Entity typePartnership
  • PartnersNISHANT BEHEDE, MANISH DURGAPRASAD KASAT

Key dates

this monthRegisteredJan 2023First promiseSep 2025Revised toSep 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Jan 2023
  • Promised completion1 Sep 2030
  • Revised completionRevised to 1 Sep 2030 (originally 1 Sep 2025)
  • Buildings1 building record
  • Documents filed98 files

Current status

0%0 of 9 units booked

Figures as on 9 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GBTNA21099

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 95%.

GBT: 9% average across the applicable activities

ActivityProgress
Excavation95%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 9 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed12

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots12
Closed/Covered4
Open Space8

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,066 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
M/S H.R. PROMOTERS AND BUILDERS PVT. LTD.Pune (M Corp.)Pune
M/S LAXMI NARAYAN THEATERS LLPSwargatePune

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI20468.95
Proposed, not sanctioned469 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGULTEKDI, MARKET YARD, PUNE

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSandeep Hardikar
EngineerVIJENDRA GAIKWAD
EngineerMAHESH MATE
Chartered AccountantS S SMART AND ASSOCIATES
Chartered AccountantG. D APTE AND CO.
PartnerRole in project
GOKHALE DECCAN LANDMARKS LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA10032620151Sep 2025 → Sep 2030

Reason as filed by the promoterDue to some issues, previous contractor is cancelled and the new contractor is appointed for the work of said project.

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
SM12500207Ram GawaliGOKHALE DECCAN LANDMARKS LLP27/11/2025
SM12500219Ram GawaliGOKHALE DECCAN LANDMARKS LLP27/11/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Dec 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Dec 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 1 Sep 2030

Documents filed98

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 98 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: GBT-FORM1-30-9-25.pdf9 Mar 2026
Form 2File: Form 2 GBT Sep - 25.pdf9 Mar 2026
Form 3File: GBT- FORM 3- 30-9-25.pdf9 Mar 2026
Disclosure of Sold and Booked InventoryFile: 01-09-25.pdf9 Mar 2026
Form 2A (FY 2024-2025)File: GBT-FORM 2A-2024-25.pdf6 Mar 2026
Form 1File: GBT-FORM1-31-3-25.pdf5 Mar 2026
Form 2File: GBT Form-2 FY2024-25 -Q4-31-03-2025.pdf5 Mar 2026
Form 3File: GBT Form 3 31032025.pdf5 Mar 2026
Disclosure of Sold and Booked InventoryFile: 31-03-25.pdf5 Mar 2026
Form 1File: GBT-FORM1-30-6-25.pdf5 Mar 2026
Form 2File: GBT Form-2 FY2026-26 -Q1-30-06-2025.pdf5 Mar 2026
Form 3File: GBT Form 3 30062025.pdf5 Mar 2026
Disclosure of Sold and Booked InventoryFile: 30-06-25.pdf5 Mar 2026
Form 2A (FY 2022-2023)File: GBT-FORM 2A-2022-23.pdf5 Mar 2026
Form 2A (FY 2023-2024)File: GBT-FORM 2A-2023-24.pdf5 Mar 2026
Form 5 (FY 2022-2023)File: signed GBT FY 22-23.pdf3 Mar 2026
Form 5 (FY 2023-2024)File: signed GBT FY 23-24.pdf3 Mar 2026
Form 5 (FY 2024-2025)File: signed GBT FY 24-25.pdf3 Mar 2026
Form 1File: GBT Form-1 FY2022-23 -Q4- 31-03-2023.pdf13 Jan 2026
Form 2File: GBT Form-2 FY2022-23 -Q4-31-03-2023.pdf13 Jan 2026
Disclosure of Sold and Booked InventoryFile: 31-03-23.pdf13 Jan 2026
Form 3File: Form 3 - GBT.PDF13 Jan 2026
Form 1File: GBT Form-1 FY2023-24 -Q1- 30-06-2023.pdf13 Jan 2026
Form 2File: GBT Form-2 FY2023-24 -Q1-30-06-2023.pdf13 Jan 2026
Form 3File: GBT Form 3 30062023.pdf13 Jan 2026
Disclosure of Sold and Booked InventoryFile: 30-06-23.pdf13 Jan 2026
Form 1File: 30-09-23.pdf13 Jan 2026
Form 2File: GBT Form-2 FY2023-24 -Q2-30-09-2023.pdf13 Jan 2026
Form 3File: GBT Form 3 30092023.pdf13 Jan 2026
Disclosure of Sold and Booked InventoryFile: 30-09-23.pdf13 Jan 2026
Form 1File: GBT Form-1 FY2023-24 -Q3- 31-12-2023.pdf13 Jan 2026
Form 2File: GBT Form-2 FY2023-24 -Q3-31-12-2023.pdf13 Jan 2026
Disclosure of Sold and Booked InventoryFile: 31-12-23.pdf13 Jan 2026
Form 3File: GBT Form 3 31122023.pdf13 Jan 2026
Form 1File: GBT Form-1 FY2023-24 -Q4-31-03-2024.pdf13 Jan 2026
Form 2File: GBT Form-2 FY2023-24 -Q4-31-03-2024.PDF13 Jan 2026
Form 3File: GBT Form 3 31032024.pdf13 Jan 2026
Disclosure of Sold and Booked InventoryFile: 31-03-24.pdf13 Jan 2026
Form 1File: GBT Form-1 FY2024-25 -Q1-30-06-2024.pdf13 Jan 2026
Form 2File: GBT Form-2 FY2024-25 -Q1-30-06-2024.PDF13 Jan 2026
Form 3File: GBT Form 3 30062024.pdf13 Jan 2026
Disclosure of Sold and Booked InventoryFile: 30-06-24.pdf13 Jan 2026
Form 1File: GBT Form-1 FY2024-25 -Q2-30-09-2024.pdf13 Jan 2026
Form 2File: GBT Form-2 FY2024-25 -Q2-30-09-2024.pdf13 Jan 2026
Form 3File: GBT Form 3 30092024.pdf13 Jan 2026
Disclosure of Sold and Booked InventoryFile: 30-09-24.PDF13 Jan 2026
Form 1File: GBT Form-1 FY2024-25 -Q3-31-12-2024.pdf13 Jan 2026
Form 2File: GBT Form-2 FY2024-25 -Q3-31-12-2024.pdf13 Jan 2026
Form 3File: GBT Form 3 31122024.pdf13 Jan 2026
Disclosure of Sold and Booked InventoryFile: 31-12-24.pdf13 Jan 2026
Disclosure of sold/ booked inventoryFile: GBT Sold Unsold 30092024.pdf11 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_GBT_30062024.pdf3 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_GBT 31032023.PDF3 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 GBB A6 30092023.pdf3 Jan 2025
Disclosure of sold/ booked inventoryFile: GBT Sold Unsold 300624 Signed ok.pdf3 Jan 2025
Disclosure of sold/ booked inventoryFile: GBT Sold Unsold 30 06 24 - Signed.pdf10 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - GBT 30 06 2024.PDF19 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: GBT 2A 22-23 - Signed.pdf3 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: GBT 2A 23-24 - Signed.pdf3 May 2024
Disclosure of sold/ booked inventoryFile: GBT Sold Unsold 31 3 23 - Signed.pdf2 May 2024
Disclosure of sold/ booked inventoryFile: GBT Sold Unsold 30 6 23 - Signed.pdf2 May 2024
Disclosure of sold/ booked inventoryFile: GBT Sold Unsold 30 9 23 - Signed.pdf2 May 2024
Disclosure of sold/ booked inventoryFile: GBT Sold Unsold 31 12 23 - Signed.pdf2 May 2024
Disclosure of sold/ booked inventoryFile: GBT Sold Unsold 31 3 24 - Signed.pdf2 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GBT - Form 1 - 31 03 2024.pdf30 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - GBT 31 03 2024.PDF30 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GBT - Form 1 - 30 06 2023.pdf13 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GBT - Form 1 - 30 09 2023.pdf13 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GBT - Form 1 - 31 12 2023.pdf13 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GBT 30 06 2023.pdf24 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GBT 30 09 2023.pdf24 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GBT 31 12 2023.pdf24 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - GBT 31-03-2023.PDF12 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 GBT Architect Certificate 31-03-2023.pdf30 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate GBT 31-03-2023.pdf30 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 GBT CA Certificate 06-01-2023.PDF30 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 GOKHALE CONSTRUCTION .pdf6 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure - A Vishal Sir.PDF6 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure-Survat Deshpande.PDF6 Jan 2023
Copy of the legal title reportFile: GBT Search final_compressed.pdf3 Jan 2023

How this compares with Pune

0%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 60 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GBT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SHIVAJINGAR BHAMBURDA13,700+ in Pune

Builder: GOKHALE DECCAN LANDMARKS LLP

GOKHALE DECCAN LANDMARKS LLP has 1 registration on MahaRERA, including GBT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if GBT is delayed beyond 1 Sep 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GBT?

The registered promoter entity is GOKHALE DECCAN LANDMARKS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GBT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against GBT?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for GBT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GBT?

The professionals named in the filing: Architect: Sandeep Hardikar; Engineer: VIJENDRA GAIKWAD; Engineer: MAHESH MATE; Chartered Accountant: S S SMART AND ASSOCIATES; Chartered Accountant: G. D APTE AND CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GBT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GBT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GBT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.