Home / Browse projects / Pune, Maharashtra / GAYATRREE LANDMARK PHASE II

Completed Litigation declared Residential / Group Housing project

GAYATRREE LANDMARK PHASE II

By GAYATRREE SKYSCRAPERS

RG-MH-25034 · RERA P52100007004 · Last updated on MahaRERA portal: 25 Dec 2024

Source: official MahaRERA filing

Red flags

  • Litigation declared, 3 cases
  • 2 complaints at MahaRERA
  • Completion date moved by 48 months
  • 4 extensions taken

Clear

  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2022Possession promisedregistration recorded completed
10 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 80%
2Complaints at MahaRERAon this registration
Jump to the 49 documents Report an error

GAYATRREE LANDMARK PHASE II is a Residential / Group Housing project by GAYATRREE SKYSCRAPERS in Pune, Maharashtra, registered with MahaRERA as P52100007004 on 17 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2022. The completion date has moved by 48 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameGAYATRREE LANDMARK PHASE II
  • TypeResidential / Group Housing
  • Location
    • Aundh Ravet BRT road
    • Dange chowk
    • Thergaon
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100007004
  • ReraGenie IDRG-MH-25034

Builder

  • NameGAYATRREE SKYSCRAPERS
  • Entity typePartnership
  • GSTIN27AALFG5440P1ZU
  • PartnersDIPIKA VISHWANATH VARMA, SANJEEV KRISHNA MAHAJAN, AMIT DILIP KAMAT, UMESH SHRIKANT AGATE, KALURAM GOPALRAO BARNE, HEMANT KRISHAN MAHAJAN, BALWANT ARVIND MARATHE
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseDec 2018Revised toDec 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on17 Aug 2017
  • Promised completion31 Dec 2022
  • Revised completionRevised to 31 Dec 2022 (originally 31 Dec 2018)
  • Buildings3 building records
  • Documents filed49 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING BNA120000
BUILDING ANA120000
BUILDING C AND MHADANA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 25 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 80%.

BUILDING B67%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING A67%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING C AND MHADA0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 25 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes70%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed106

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots106
Closed/Covered106
BuildingClosed/CoveredTotal
BUILDING B4545
BUILDING A4949
BUILDING C AND MHADA1212

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,300 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
Sanjay Gulab BhoirChinchwadPune
Smt. Jaya Gulab BhoirChinchwadPune
Mrs Seema Sanjay BhoirChinchwadPune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad
Permissible FSI8331.26
Proposed, not sanctioned5,618 sq m
Buildings approved5
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNIGADI PUNE

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSWAPNIL KSHIRSAGAR
EngineerANAND BHAGWATWAR
PartnerRole in project
GAYATRREE SKYSCRAPERS-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100000938Dec 2018 → Apr 2020

Reason as filed by the promoterChange in building plan with reference to Maharashtra GOVT GR TPS-1816/1552/.74/17/new-13 dated 15/03/18

EXT52100006357Dec 2018 → Oct 2021

Reason as filed by the promoterEarlier the project application was done for Extention but as there was a technical misunderstanding we had not submitted the Consent and the registration was granted for 3 months only in spite of paying complete fees of 57000/- It was then suggested us to reapply with nominal fees of 5000 and consent of allottees

EXT52100005060Dec 2018 → Apr 2020

Reason as filed by the promoterDelay due CC005000000033491/2019

EXT52100011898Dec 2018 → Dec 2022

Reason as filed by the promoterThe project phase one (building A wing consisting of 62 flats) is completed and occupied by all alottees and the occupancy certificate for same is received and uploaded as well as attached herewith. Due to unavoidable reasons at Municipality office the occupancy certificate is not issued same shall be issued in 45 days till then the payments and registration of unsold flat is on hold due to expiry of RERA registration hence we need this extension. Building on ground is physically completed with part completion and occupancy over 70 percent.

Litigation declared3

CaseCourtStatus
1644/2017sessions courtPending
2303/2020High CourtAppeal filed in supreme court and stay granted by SC
SLP/25863/2024Supereme CourtStay granted to HC order

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC005000000033491MR SANJAY GULAB BHOIR, MRS JAYA GULAB BHOIR AND MRS SEEMA SANJAY BHOIRGAYATRREE SKYSCRAPERS patnership firm, MR VISHWANATHVARMA, MRS DIPIKA VARMA AND OTHERS05/10/2019
CC005000000064806SANJAY BHOIR, JAYA BHOIR AND SEEMA BHOIRM/s Gayatrree Skyscrapers pvt ltd04/11/2020

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Dec 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Aug 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 20 Jul 2024

Documents filed49

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Copy of the legal title reportFile: SC order in Gskyscrappers.pdf25 Dec 2024
Other - LegalFile: SC order in Gskyscrappers.pdf25 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Final_Completion_Certificate_Gayatrree_Landmark_Phase-2.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: sold unsold inventory 2022.pdf25 May 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Landmark PH 2 Soc Reg CERTIFICATE.pdf19 May 2022
Certificates of CA (Form 3)File: form 3 Landmark 2022.pdf18 May 2022
Declaration about Commencement CertificateFile: Declaration of commencement Formate D 2223.pdf16 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Architect Certificate Form 1 April 22.pdf16 May 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate Form 2 April 22.pdf16 May 2022
Disclosure of sold/ booked inventoryFile: Discloser Of Sold And Unsold 2122.pdf16 May 2022
Certificates of CA (Form 3)File: Landmark Form 3 April 22.pdf16 May 2022
CERSAI detailsFile: Cersai Certificate Gayatrree Landmark.pdf23 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 - Gaytree Landmark FY 2018-19.pdf16 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 Gayatree Landmark FY 2019-20.pdf16 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 -Gayatrree Landmark FY 2020-21.pdf16 Aug 2021
Declaration about Commencement CertificateFile: Format D Ph 2 Landmark 2021.pdf13 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Landmark Form 2A 1920 Eng Cert.pdf13 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Landmark form 2 A Eng Cert.pdf13 Jul 2021
Disclosure of sold/ booked inventoryFile: Landmark Sold Inventory Ph 2 2021.pdf13 Jul 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Landmark B wing completion.pdf7 Dec 2019
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society formation Certificate.pdf7 Dec 2019
Certificates of CA (Form 5)File: Form-5 2019.pdf1 Dec 2019
Architect’s Certificate on Completion of Project (Form 4)File: Form-4 2019.pdf1 Dec 2019
Certificates of CA (Form 5)File: Gayatree Scyscrappers.pdf31 Oct 2018
Layout approvalFile: Layout Plan.pdf14 Aug 2017
Building plan approvalFile: 5.pdf14 Aug 2017
Building plan approvalFile: 6.pdf14 Aug 2017
Building plan approvalFile: 7.pdf14 Aug 2017
Building plan approvalFile: 1.pdf14 Aug 2017
Building plan approvalFile: 2.pdf14 Aug 2017
Building plan approvalFile: 3.pdf14 Aug 2017
Building plan approvalFile: 4.pdf14 Aug 2017
PAN CardFile: PAN.pdf14 Aug 2017
Copy of the legal title reportFile: Title Search Report.pdf14 Aug 2017
Details of encumbrancesFile: ENCUMBRANCES.pdf14 Aug 2017
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf14 Aug 2017
Building Plan Approval (IOD)File: 1.pdf14 Aug 2017
Building Plan Approval (IOD)File: 2.pdf14 Aug 2017
Building Plan Approval (IOD)File: 3.pdf14 Aug 2017
Building Plan Approval (IOD)File: 4.pdf14 Aug 2017
Building Plan Approval (IOD)File: 5.pdf14 Aug 2017
Building Plan Approval (IOD)File: 6.pdf14 Aug 2017
Building Plan Approval (IOD)File: 7.pdf14 Aug 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate.pdf14 Aug 2017
Declaration in FORM BFile: FORM B.pdf14 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf14 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERTIFICATE.pdf14 Aug 2017
Certificates of CA (Form 3)File: FORM 3.pdf14 Aug 2017
Proforma of Allotment letterFile: AGREEMENT LANDMARK.pdf14 Aug 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Gayatrree Landmark Phase-121/1F, Thegraon, Dange Chowk, PCMC, Pune109CompletedDec 2016Aug 2016

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 48 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GAYATRREE LANDMARK PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dange chowk13,700+ in Pune

2 kmGAYATRREE LANDMARK PHASECompleted 83Lapsed / revoked 40Other 50Dot size: filed unitsN

Filed coordinates, straight-line distance. 173 registered projects within 2 km.

Builder: GAYATRREE SKYSCRAPERS

GAYATRREE SKYSCRAPERS has 1 registration on MahaRERA, including GAYATRREE LANDMARK PHASE II. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if GAYATRREE LANDMARK PHASE II is delayed beyond 31 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GAYATRREE LANDMARK PHASE II?

The registered promoter entity is GAYATRREE SKYSCRAPERS, a partnership as per the filing. Its GSTIN 27AALFG5440P1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GAYATRREE LANDMARK PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against GAYATRREE LANDMARK PHASE II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for GAYATRREE LANDMARK PHASE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GAYATRREE LANDMARK PHASE II?

The professionals named in the filing: Architect: SWAPNIL KSHIRSAGAR; Engineer: ANAND BHAGWATWAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GAYATRREE LANDMARK PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GAYATRREE LANDMARK PHASE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GAYATRREE LANDMARK PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.