ReraGenieLog inGet a buyer report

Home / Browse projects / Ratnagiri, Maharashtra / GAURI GANESH HEIGHTS

Registered No litigation declared Others project

GAURI GANESH HEIGHTS

By Omkar Dattaram Joshi

RG-MH-18738 · RERA P52800077547 · Last updated on MahaRERA portal: 28 Mar 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 40%
32 of 46Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 113 documents Report an error

GAURI GANESH HEIGHTS is a Others project by Omkar Dattaram Joshi in Ratnagiri, Maharashtra, registered with MahaRERA as P52800077547 on 10 Oct 2024. Possession is promised by 31 Dec 2027. 14 of the 46 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameGAURI GANESH HEIGHTS
  • TypeOthers
  • Location
    • Ratnagiri Lanja Main Road
    • Kuwarbav
    • Kuwarbav (CT)
    • Ratnagiri
    • 415639
  • Pincode415639
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52800077547
  • ReraGenie IDRG-MH-18738

Builder

  • NameOmkar Dattaram Joshi
  • Entity typeIndividual
  • GSTIN27BAPPJ7730N1Z0

Key dates

this monthRegisteredOct 2024PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Oct 2024
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed113 files

Current status

30%14 of 46 units booked
23.3%Work done, per cost certificate

Figures as on 28 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GAURI GANESH HEIGHTSNA98301646

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 28 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 40%.

GAURI GANESH HEIGHTS: 40% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 28 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes25%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes25%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed75

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots75
Open Space75

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,500 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authoritySub Divisional Office Ratnagiri
Permissible FSI2525.53
Proposed, not sanctioned2,526 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKHAREGHAT RD., RATNAGIRI, PIN415612
Estimated costRs 7.15 cr
Cost incurredRs 1.66 cr
Work done23.26%
BuildingWingEstimatedIncurred
GAURI GANESH HEIGHTSNARs 6.22 crRs 1.62 cr
-NARs 93.31 lakhRs 4.67 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRupesh Pavankumar Salvi
EngineerRupesh Pavankumar Salvi
Chartered AccountantShrikant P Vaidya
Chartered AccountantShrikant Pandurang Vaidya
Chartered AccountantShrirang Pandurang Vaidya
PartnerRole in project
Omkar Dattaram Joshi-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Aug 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Aug 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Aug 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Aug 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed113

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 113 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Certificate 30-06-2025.pdf28 Mar 2026
Withdrawal Update Form 1File: Architect Certificate 30-09-2025.pdf28 Mar 2026
Withdrawal Update Form 1File: Architect Certificate 31-12-2025.pdf28 Mar 2026
Withdrawal Update Form 2File: Engineer Certificate 30-06-2025.pdf28 Mar 2026
Withdrawal Update Form 2File: Engineer Certificate 30-09-2025.pdf28 Mar 2026
Withdrawal Update Form 2File: Engineer Certificate 31-12-2025.pdf28 Mar 2026
Withdrawal Update Form 3File: CA Certificate 30-06-2025.pdf28 Mar 2026
Withdrawal Update Form 3File: CA Certificate 30-09-2025.pdf28 Mar 2026
Withdrawal Update Form 3File: CA Certificate 31-12-2025.pdf28 Mar 2026
Form 1File: Architect certificate 31-12-2024.pdf19 May 2025
Form 2File: Engineer certificate 31-12-2024.pdf19 May 2025
Form 3File: CA CERTIFICATE 31-12-2024.pdf19 May 2025
Disclosure of Sold and Booked InventoryFile: SOLD -BOOKED INVENTORY.pdf19 May 2025
Form 1File: Architect certificate 31-03-2025.pdf19 May 2025
Form 2File: Engineer certificate 31-03-2025.pdf19 May 2025
Form 3File: CA CERTIFICATE 31-03-2025.pdf19 May 2025
Disclosure of Sold and Booked InventoryFile: Sold Book INVENTORY 2025.pdf19 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate 31-12-2024.pdf5 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate 31-12-2024.pdf5 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE 31-12-2024.pdf5 Feb 2025
Disclosure of sold/ booked inventoryFile: SOLD -BOOKED INVENTORY.pdf5 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate 31-12-2024.pdf5 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate 31-12-2024.pdf5 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE 31-12-2024.pdf5 Feb 2025
Disclosure of sold/ booked inventoryFile: SOLD -BOOKED INVENTORY.pdf5 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate 31-12-2024.pdf5 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE 31-12-2024.pdf5 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate 31-12-2024.pdf5 Feb 2025
Disclosure of sold/ booked inventoryFile: SOLD -BOOKED INVENTORY.pdf5 Feb 2025
Other - TechnicalFile: ANNEXURE 'A'.pdf6 Oct 2024
Deviation Report with respect to model copy of AgreementFile: DEVIATION FROM AGREEMENT FOR SALE.pdf6 Oct 2024
Proforma of Agreement for saleFile: Model Copy Of ASF 1.pdf6 Oct 2024
Other - TechnicalFile: ANNEXURE 'A'.pdf6 Oct 2024
Deviation Report with respect to model copy of AgreementFile: DEVIATION FROM AGREEMENT FOR SALE.pdf6 Oct 2024
Proforma of Agreement for saleFile: Model Copy Of ASF 1.pdf6 Oct 2024
Other - TechnicalFile: ANNEXURE 'A'.pdf6 Oct 2024
Deviation Report with respect to model copy of AgreementFile: DEVIATION FROM AGREEMENT FOR SALE.pdf6 Oct 2024
Proforma of Agreement for saleFile: Model Copy Of ASF 1.pdf6 Oct 2024
Proforma of Agreement for saleFile: Model Copy Of ASF 1.pdf6 Oct 2024
Deviation Report with respect to model copy of AgreementFile: DEVIATION FROM AGREEMENT FOR SALE.pdf6 Oct 2024
Other - TechnicalFile: ANNEXURE 'A'.pdf6 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf14 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf14 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf14 Aug 2024
Building plan approvalFile: Blueprint.pdf9 Aug 2024
Layout approvalFile: plot nakasha .pdf9 Aug 2024
Building plan approvalFile: Blueprint.pdf9 Aug 2024
Layout approvalFile: plot nakasha .pdf9 Aug 2024
Building plan approvalFile: Blueprint.pdf9 Aug 2024
Layout approvalFile: plot nakasha .pdf9 Aug 2024
Copy of the legal title reportFile: Search Report.pdf9 Aug 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Certificate.pdf9 Aug 2024
Copy of Layout Approval (in case of layout)File: plot nakasha .pdf9 Aug 2024
Proforma of Allotment letterFile: Allotment Letter.pdf9 Aug 2024
Declaration in FORM BFile: Form B.pdf9 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf9 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf9 Aug 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf9 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: Blueprint.pdf9 Aug 2024
Other - LegalFile: land sale deed_compressed.pdf9 Aug 2024
Declaration about Commencement CertificateFile: Format - D.pdf9 Aug 2024
CERSAI detailsFile: CERSAI_Search_Report_200316555272_For_Asset_Based_Search_09_08_2024_12_24_36_207.pdf9 Aug 2024
CERSAI detailsFile: CERSA.pdf9 Aug 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format 'A'Bank Accounts.pdf9 Aug 2024
Deviation Report with respect to Allotment letterFile: NO DEVIATION FROM ALLOTMENT LETTER.pdf9 Aug 2024
Details of encumbrances concerned to LegalFile: Encumbrance Certificate.pdf9 Aug 2024
Other - TechnicalFile: CC Mail-2.pdf9 Aug 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf9 Aug 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: FORMAT B BANK LETTER.pdf9 Aug 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secured-unsecured finance availed for the project.pdf9 Aug 2024
Copy of the legal title reportFile: Search Report.pdf9 Aug 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Certificate.pdf9 Aug 2024
Copy of Layout Approval (in case of layout)File: plot nakasha .pdf9 Aug 2024
Proforma of Allotment letterFile: Allotment Letter.pdf9 Aug 2024
Declaration in FORM BFile: Form B.pdf9 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf9 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf9 Aug 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf9 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: Blueprint.pdf9 Aug 2024
Other - LegalFile: land sale deed_compressed.pdf9 Aug 2024

How this compares with Ratnagiri

30%of this project is bookeddistrict median 23%
15%of Ratnagiri projects moved their completion datethis one has not
30%of Ratnagiri registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.

Keep GAURI GANESH HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kuwarbav1,100+ in Ratnagiri

2 kmGAURI GANESH HEIGHTSCompleted 10Lapsed / revoked 7Other 7Dot size: filed unitsN

Filed coordinates, straight-line distance. 24 registered projects within 2 km.

Builder: Omkar Dattaram Joshi

Omkar Dattaram Joshi has 1 registration on MahaRERA, including GAURI GANESH HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Ratnagiri district page.

Frequently asked questions

What are my rights if GAURI GANESH HEIGHTS is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GAURI GANESH HEIGHTS?

The registered promoter entity is Omkar Dattaram Joshi, an individual as per the filing. Its GSTIN 27BAPPJ7730N1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GAURI GANESH HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GAURI GANESH HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GAURI GANESH HEIGHTS?

The professionals named in the filing: Architect: Rupesh Pavankumar Salvi; Engineer: Rupesh Pavankumar Salvi; Chartered Accountant: Shrikant P Vaidya; Chartered Accountant: Shrikant Pandurang Vaidya; Chartered Accountant: Shrirang Pandurang Vaidya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GAURI GANESH HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GAURI GANESH HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GAURI GANESH HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.