ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Ganga Aurum Park C

Registered No litigation declared Residential / Group Housing project

Ganga Aurum Park C

By Ecostar Goel Properties LLP

RG-MH-26339 · RERA P52100014268 · Last updated on MahaRERA portal: 30 Apr 2025

Source: official MahaRERA filing

Red flags

  • 6 complaints at MahaRERA
  • Rs 20.25 crore secured on the land, in favour of PRACHAY CAPITAL LIMITED

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
6 of 11Construction stages donefurthest along: External plumbing and external plaster, 96%
9 of 103Units unsoldnot recorded sold or booked
6Complaints at MahaRERAon this registration
Jump to the 92 documents Report an error

Ganga Aurum Park C is a Residential / Group Housing project by Ecostar Goel Properties LLP in Pune, Maharashtra, registered with MahaRERA as P52100014268 on 17 Nov 2017. Possession is promised by 30 Dec 2026. 94 of the 103 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 6 complaints are on record with the regulator.

At a glance

Project

  • NameGanga Aurum Park C
  • TypeResidential / Group Housing
  • Location
    • Tathawade
    • Tathwade
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100014268
  • ReraGenie IDRG-MH-26339

Builder

  • NameEcostar Goel Properties LLP
  • Entity typePartnership

Key dates

this monthRegisteredNov 2017PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Nov 2017
  • Promised completion30 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed92 files

Current status

91%94 of 103 units booked

Figures as on 30 Apr 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CNA14131030103

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 96%.

C: 84% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises54%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.96%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%

Progress on shared amenities15

As on 30 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area820 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofPRACHAY CAPITAL LIMITED
Secured amountRs 20.25 crore
CERSAI search filedYes
Declared on15 Nov 2025

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI3759.36
Proposed, not sanctioned313 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchEast Street Branch Pune

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectA & T Consultants
Chartered AccountantDMKH & Co
PartnerRole in project
Ecostar Goel Properties LLP-

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC12400003Priyanka Mahesh BansodeEcostar Goel Properties LLP01/09/2024
CC12400004Nitin Namdeo PatilEcostar Goel Properties LLP01/09/2024
CC12400481Pallavi Ganpat PawarEcostar Goel Properties LLP20/10/2024
CC12502244Doris FernandesEcostar Goel Properties LLP05/07/2025
CC12503724Ganesh Balu ShelkeEcostar Goel Properties LLP22/10/2025
CC12602005Atul GuptaEcostar Goel Properties LLP04/04/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Oct 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Oct 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Dec 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2026

Documents filed92

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf30 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf30 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold inventory.pdf30 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Aurum park.pdf21 Apr 2025
Certificates of CA (Form 3)File: Form 3.pdf21 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Aurum Park.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: 4 Disclosure of sold_ booked inventory.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: 4 Disclosure of sold_ booked inventory.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: 4 Disclosure of sold_ booked inventory.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: 4 Disclosure of sold_ booked inventory.pdf21 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 aurum park.pdf21 Jan 2025
Certificates of CA (Form 3)File: Form 3 aurum.pdf21 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Aurum park.pdf21 Jan 2025
Layout approvalFile: layout.pdf30 Oct 2024
Layout approvalFile: C building plan.pdf30 Oct 2024
Layout approvalFile: C building plan.pdf30 Oct 2024
Copy of Layout Approval (in case of layout)File: layout.pdf30 Oct 2024
Copy of Layout Approval (in case of layout)File: C building plan.pdf30 Oct 2024
Copy of Layout Approval (in case of layout)File: C building plan.pdf30 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Aurum park.pdf30 Oct 2024
Certificates of CA (Form 3)File: Form 3 Aurum.pdf30 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Aurum park.pdf30 Oct 2024
Other - FinanceFile: Self Declaration aurum park.pdf30 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Aurum.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Aurum.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Form D aurum.pdf20 Jul 2024
Certificates of CA (Form 3)File: Form 3 Aurum.pdf20 Jul 2024
Certificates of CA (Form 3)File: Form 3.pdf23 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 AURUM.pdf21 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 AURUM.pdf21 Apr 2024
Certificates of CA (Form 3)File: 6 Certificates of CA (Form 3).pdf21 Apr 2024
Certificates of CA (Form 3)File: 7 form 3.pdf21 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf17 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf17 Jan 2024
Disclosure of sold/ booked inventoryFile: Form D.pdf17 Jan 2024
Disclosure of sold/ booked inventoryFile: Form D.pdf17 Jan 2024
Certificates of CA (Form 3)File: Form 3.pdf17 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Form D.pdf17 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf26 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf26 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf26 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf26 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf26 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf26 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Ecostar Annuj Sir.pdf7 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Ecostar Ankit Sir.pdf7 Dec 2023
Details of encumbrancesFile: Ecostar Prachay Loan Mortgage Index II.pdf20 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ecostar goel properties form 1-compressed.pdf9 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 c - bldg.pdf9 Nov 2023
Certificates of CA (Form 3)File: Ganga Aurum Park C Building Sept 23 Form 3 RERA CA Certificate_compressed.pdf9 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf18 Aug 2023
Certificates of CA (Form 3)File: Form 3.pdf18 Aug 2023
Certificates of CA (Form 3)File: Form 3.pdf18 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5.pdf18 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf8 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf8 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf8 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf25 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf29 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 march.pdf17 Apr 2023
Declaration about Commencement CertificateFile: Format D.pdf15 Feb 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold.pdf15 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf9 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect form 1.pdf6 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering certificate form 2.pdf6 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering certificate form 2.pdf6 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quarterly- Quality Assurance form 2A (RERA).pdf6 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quarterly- Quality Assurance form 2A (RERA).pdf6 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quarterly- Quality Assurance form 2A (RERA).pdf6 Jan 2023
Layout approvalFile: ECO.pdf23 Dec 2022
Building plan approvalFile: IOD Layout 2022.pdf23 Dec 2022
PAN CardFile: Ecostar Goel Properties LLP.pdf23 Dec 2022
Copy of Layout Approval (in case of layout)File: ECO.pdf23 Dec 2022
Building Plan Approval (IOD)File: IOD Layout 2022.pdf23 Dec 2022
Commencement Certificates / NA Order for plotted developmentFile: Complete CC (2)_compressed.pdf23 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: ECO.pdf23 Dec 2022
Details of encumbrancesFile: EGPLLP Prachay Mortgage Deed Dt26-12-2020 Index II.pdf7 Mar 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 20210118_C Engineer Certificate_compressed.pdf22 Feb 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ganga aurum park- c bldg.pdf22 Feb 2022

How this compares with Pune

91%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Ganga Aurum Park C on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Tathawade13,700+ in Pune

2 kmGanga Aurum Park CCompleted 115Lapsed / revoked 43Other 91Dot size: filed unitsN

Filed coordinates, straight-line distance. 249 registered projects within 2 km.

Builder: Ecostar Goel Properties LLP

Ecostar Goel Properties LLP has 1 registration on MahaRERA, including Ganga Aurum Park C. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Ganga Aurum Park C is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ganga Aurum Park C?

The registered promoter entity is Ecostar Goel Properties LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ganga Aurum Park C?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Ganga Aurum Park C?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Ganga Aurum Park C?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ganga Aurum Park C?

The professionals named in the filing: Architect: A & T Consultants; Chartered Accountant: DMKH & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ganga Aurum Park C?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ganga Aurum Park C. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ganga Aurum Park C to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.